SlideShare a Scribd company logo
1 of 43
Download to read offline
Selcted Architectural Work
Brendan M Crosby, LEED GA
750 N Dearborn St. #705
Chicago, IL 60654
4   Table of Contents
5




masters thesis work   8


undergraduate work    16


professional work     28


graphics/misc.        38
masters thesis
8   Masters Thesis Work
         As part of a new pedagogical approach to its masters curriculum, Northeastern University proposed its students
         identify and study the inherenices in design of particular building typologies. After choosing the path of “office”
         typology, a thesis was developed in response to the requirement of transforming the existing type in terms of
         programmatic efficiencies, designs and user relations.
ns




trics



                                                                                                                               Transforming the typology_Figure 1.1
9
The inherent design of mechanical systems, usually driven by service
requirements and overall building function has been a recurring                                               1
                                                                                 11
paradigm in the typology of the high-rise office building. This design
                                                                                                              8                9
not only dictates plant level program and service, but also forcefully
embeds itself into architectural design and aesthetics. Could it be
feasible to manipulate the pragmatics of the mechanical level, so
                                                                                                                      10
to serve the building more architecturally, introduce tenant-defined
                                                                                  7                           1
occupiable space, and design a user oriented mechanical floor rather
than a service driven one?                                                                                                         9
They typical pragmatism for mechanical decisions in the design of                                     8
high rise offices is that plant levels should number ten percent of total
floors. In the essence of time, constructability, and efficiency of system                                    1
loads, theses levels are placed at roughly equal intervals through out       7

the structure and occupy the entire floor plate at double height. If in a                                         6
multitenant office building, mechanical level frequencies were doubled                                                         6
and relegated to intervals not confined by serviceability and efficiency         4
of constructability, but by occupant relationship, one may begin to see a                                 1
change in how the nexus is perceived throughout the building in terms of                                              5
interconnectivity, program, and human-scale relation.
Increasing plant level frequencies will result in the deduction from total            4                       1
square footage per level, as inherencies such as numbers of air handling
units and required duct space will decrease. Reclaimable space for                            3
occupant use is a direct summation of that decrease and now the
mechanical level may begin to transform into an element of architectural                                  4
inter-connectivity through programmatic decisions now feasible. The
sky lobby is a feature commonly used in the typology of office high-
rise, which incorporates public retail and service program with building                                      1
                                                                                              2
circulation. The reclaimable space on these mechanical levels can
now serve as public retail, sky lobby, and tenant-specific front of house
services; e.g. lobby and reception areas.                                                                                          3
The objective of the proposal of this prototype is to transform the                               2
                                                                                          1
mechanical floor, identify and reprogram consequent conditions,
                                                                                                      1
ultimately reinventing the typology of the office high rise. Subsequently,                                                 1
one can begin to propose new, fully grounded architectural decisions
interrelated to site, tenant need, and program.
                                                                                                                       Programing the Prototype_Figure 1.2
10   Masters Thesis Work                                                                                    4.
                                                                                                                                                    3.




                                                                                                                                                                    2.


                                                                                                                                                                                                            1.




                                                                                                                                                                                                                       8.
                                                                                                                                                                                                  8.
                                                                                                                                                                         8.




                                                                                                        9.                                           7.



                                                                                                  5.
                                                                                                                           6.
                                                                                                                                               6.




                                                                                                                                                         2.




                                                                                                                                                                                                                  4.

                                                                                                                                5.

                                                                                                                                                                                                  3.

                                                                                                                                                                                   6.




                                                                                                                                     1.




                                                                                                                                                               1.

                                                                                                                                                                                                             8.
                                                                                                                                                                                             8.
                                                                                                                                                                                                                  7.




                                                                                                                                                                                                   6.


                                                                                                                                                                                        4.

                           Site Conncections Ground Level and Roof Garden_(Fig. 1.3 - 1.4)
                                                                                                                 2.                                            5.
                                                                                             3.




                                                                                                                       3.




                                                                                                                                                4.
                                                                                                        3.




                                                                                                                                                                                                            5.



                                                                                                       2.




                                                                                                                                               1.




                                                                                                                                                              2.




                                                                                                                                                               3.
                                                                                                                                          3.
                                                                                                                                                                                                                  1.




                                                                                                                                                                                                       1.

                                                                                                                      6.                                                      5.
                                                                                                                                                          4.




                                                                                                                                                    7.
11




                                      Open Atrium Section_Fig. 1.7




                                     Operable Skin Section_Fig. 1.8




Variations in floor plates in each ‘block’ of building mass lead to
subsequent conditions in facade and skin treatment. Open-to-air atria
conditions presented themselves in areas where the building skin was
stretched past its actual glass facade and operable climate controlled
spaces manifested in section where facade screening followed the
buildings glass envelope.
12   Masters Thesis Work
13
14   Masters Thesis Work




                           Introduction to a downtown Financial District site presented both challenges and opportunities for
                           design and programming. A study of views from varying heights was conducted and placement
                           of mechanical floors were derived according to changes in view. Programmatic and floor plan
                           decisions were then made in relation to which part of the floor plate was most desirable. Mechanical
                           spaces were placed in portions of the floor where views were blocked and the entire floor plate was
                           twisted and programmed to take advantage of desirable views.
15
undergraduate
18   Local 7 Union Hall, Boston MA
     Unlike traditional design studios which produce a schematic idea before considering the feasibility of construction, this project
     grounds design proposals upon a conceived tectonic strategy. Students were asked to propose a new Union Hall for the Local
     7 Ironworkers Labor Union on a prominent corner of the historic North End neighborhood of Boston. Preliminary research on
     Unions and their facilities preceded individual composition of a thesis, which was were used to drive design decisions. Program
     of the 30,000 sf structure includes lobby/gallery spaces, classrooms, a training facility, meeting halls, community rooms,
     dining halls, day care, exercise space, as well as administrative work rooms. An open plan and the elimination of segregated
     offices and floors for administration, along with large areas of glass penetration of the facade were a few techniques meant to
     integrate workers with community, and give the structure functionality to the public as well as the laborer.




                                     Rendering looking at northwest corner_(Fig. 2.6 )                                      Site Plan North End, Boston_(Fig. 2.6 )
19




Rendering looking at northwest corner_(Fig. 2.6 )
20   Local 7 Union Hall, Boston MA
21




Fifth Floor Level    58’-0”




Fourth Floor Level   44’-6”




Third Floor Level    31’-0”




Second Floor Level 31’-0”




First Floor Level    0’-0”
22   Local 7 Union Hall, Boston MA
23
24   South Boston Redevelopment Project
     This studio project focused on the design and development of urban housing, office space, and retail program within the
     Boston Redevelopment Authority’s ‘100 Acre Master Plan’ for the Fort Point District of South Boston. Students were assigned
     an undeveloped parcel with-in the master plan to program and design. Guidelines of the original master plan established by
     the governing planning agency were adhered to strictly in order to become aware of architectural issues that are controlled
     by such regulations. In addition, potential freedoms, and design opportunities that these situations present were studied and
     incorporated. Design responsibilities included street, pedestrian path and open space redesign, as well as open discussion and
     negotiation on reciprocal design relationships with abutting property owners.
25
26   South Boston Redevelopment Project
27
professional
30   Bayport -Bluepoint Public Library
     This proposed addition and renovation of Bayport-Bluepoint Public Library’s existing 12,800 sf. building was carried from
     schematics through design development in its pre-refferendum stage. In addition to the complete renovation of its existing
     interior spaces, BHA and the Library Board agreed that a 14,300 sf. addition was needed to house a new Childrens LIbrary and
     Program Room. Responsibilities included composing presentation drawings (Elevation and site renderings, proposed floor plan
     reditions etc.) as well as attending client meetings and public design charrettes.
31
32   Flanders Nutritional & Community Center
     The scope of work on this project included the renovation of the existing 3,800 sf. Flanders Community Center, a senior center
     in Southampton, NY. The facility underwent major demolition, down to the steel structure. Also part of the scope, a 6,200 sf.
     two story addition at the south end of the building was constructed along with two smaller additions. As a major team member
     on this project, responsibilities ranged from site verification to schematic layout, through construction documentation and
     construction administration.
33
34   Flanders Nutritional & Community Center
35
36   Touro College Dormitories
     The school of Law at Touro College sought the services of BHA to design the residence hall for its campus in Islip, New York.
     The low-rise design consists of 12 single and 59 double units to accommodate its student population. This project was carried
     through to a complete set of bidding documents. Main responsibilities included schematic presentation and development, as
     well as bid set production. The wood frame design of the residences pushed the limits of wood frame construction, making
     meticulous coordination with structural and MEP engineers a vital part of the design process.
37
graphics/photography
40   Learning Center, Los Angeles CA
41
42   Office Typology & Pattern Book
     As part of a group assignment aimed at thoroughly researching and documenting inherent designs of the office building
     typology, “Office: A Pattern Book” was written and published through Northeastern University. The publication studies and
     graphically displays the design patterns of typical office buildings categorized by size. Meticulous research, coordination and
     team efforts were displayed in the realization of this book which will serve as a guide and research source in the Northeastern
     University Architecture library.




     A RC G691 TY PO LO G Y PAT T E RN B O O K                                                                            6.4 Shading Systems   107   108   6.5 Atria




     Seasonal Shading                                                                                                                                 6.5 Atria                                                            In buildings with deeper floorplates or where a high
     While preventing solar gain is an important                                                                                                                                                                           quality of natural light is a design priority, an atrium
     requirement of shading during the spring and                                                                                                                                                                          is an excellent way of increasing the amount of
     summer months, solar gain can often be beneficial                                                                                                                                                                      daylight that enters a building. The implementation
     during the colder months of the year. Allowing                                                                                                                                                                        of an atrium effectively cuts an occupants
     solar gain in winter can reduce the amount                                                                                                                                                                            maximum distance to daylight in half and allows
     of mechanical heating required to achieve a                                                                                                                                               h      l                    for a higher and more even level of daylighting
                                                                                                                                                                  Attached                                                 throughout the space.
     comfortable working environment, thus reducing
     a building’s total energy costs. For this reason,
     some of the most effective shading systems are                                                                                                                                                       w                The best way to quantify the daylighting
     those that take advantage of the difference in solar                                                                                                                                                                  performance of an atrium is by measuring
     angle between winter and summer. In addition to                                                                                                                                       Fig. 21 - Atrium Measurements   its Daylight Factor (DF). The Daylight Factor
     the solar heat gain benefits, these strategies will                                                                                                                                                                    describes the ratio of outside illuminance over
     allow sunlight to penetrate deeper into the building                                                                                                                                                                  inside illuminance, usually expressed as a
     during the dimmer winter months.                                                                                                                                                                                      percentage. The higher the DF, the more natural
                                                                                                                                                                  Linear
                                                                                                                                                                                           PAR =          w                light is available in the atrium. The Daylight Factor
     One way to take advantage of this principle is to                                                                                                                                                    l                is affected by the geometry of the atrium, as well
     size and position a building’s louvers so that they                                                                                                                                                                   as its roof form and the reflectivity of its materials.
     block direct sunlight in the summer, when sun’s
     azimuth is greater, and allow sunlight to enter                                                                                                                                       SAR =          h                Plan Aspect Ratio (PAR)
     in the winter, when the angle is lower (Fig. 18).                                                                                                                                                                     The most efficient shape for the plan of an atrium
                                                                                                                                                                                                          w
     Another effective strategy is to use strategically                                                                                                                                                                    is a circle. In atria with non-circular plans, the
     placed trees as a form of natural shading. In the                                                                                                            Enclosed                                                 PAR can be used to measure the effectiveness
     summer, the trees will block sunlight and provide                                                                                                                                                                     of the space’s geometry. The PAR is equal to the
     the building with shade. In the winter, when their                                                                                                                                    WI =       h x (l + w)          atrium’s width divided by its length. An atrium
     branches are bare, they will allow sunlight to pass                                                                                                                                              2xlxw                with a PAR closer to 1 (square) will have better
     through and enter the building. (Fig. 19)                                                                                                                                                                             dayighting performance than one with a PAR
                                                                                                                                                                                                                           closer to 0 (linear).


                                                                                                                                                                                                                           Section Aspect Ratio (SAR)
                                                            Fig. 18 - Seasonal Shading, Summer   Fig. 19 - Natural Shading, Summer                                Semi-Enclosed                                            The SAR measures the ratio of an atrium’s height
                                                            (above) and Winter                   (above) and Winter                                               Fig. 20 - Atrium Types
                                                                                                                                                                                                                           to its width. A low SAR indicates a shallow atrium
                                                                                                                                                                                                                           and a relatively high Daylight Factor.
128     7.3 Space Planning Patterns                                                                                                                                                                           AR C G691 TYPOLOGY PATTER N BOOK                                                                                             7.3 Space Planning Patterns   129




  7.3 Space Planning Patterns
  The Organism                                                                                                                                                                                                                                                                                                                                                                   43


                                                                                                                                             240°
                                                                                                                                             Program- Creative, Corporate
                                                                                                                                             -High Density
                                                                                                                                             -High Net Workspace Within Primary Reach
                                                                                                                                                                                                                 Low           High                 Low           High
                                                                                                                                             -High Acoustic Transmission
                                                                                                                                             -High Potential Shared Worspace/Team Overlap


                                                                                                                                             -Moderate-High Visibility                                          Sound Intesity                      Visual Overlap
                                                                                                                                             -Moderate Personal Identity
                                                                                                                                             -Moderate Project Team Mobility


                                                                                                                                             -Low-Moderate Enclosure

                                                                                                                                             Metrics
                                                                                                                                             Workspaces-                                         32
                                                                                                                                             SF Per Worker-                                      85 sf
                                                                                                                                             LF worksurface-                                     320 lf
                                                                                                                                             LF Per Worker-                                      10 ft
                                                                                                                                             Floor Area-                                         2,728 sf
                                                                                                                                             Total Area of Worksurfaces-                         768 sf
                                                                                                                                             Worksurface Area Per Worker-                        24 sf
                                                                                                                                             Floor Area : Worksurface Area-                      3.55:1



                                                                                                                                                                                                                Plan Detail
              Fig. 15                                                                                                                                                                                                                                                                                Fig. 16




ARC G691 TY P O LO G Y PAT T E RN B O O K                                                                                                                                 3.2 Mechanical Circulation       51   52     3.3 Localized Air Distribution Systems




 Typical Mech. Space Req. for High Rise Office                          Typical Mech. Space Req. for Mid Rise Office                                                                                              3.3 Localized Air Distribution Systems                                                            Variable Air Volume System (VAV)
                                                                                                                                                                                                                                                                                                                  Typically in office building settings, the most efficient
 Penthouse Levels                                                      Penthouse Levels                                                                                                                                                                                             45’
                                                                                                                                                                                                                                                                                                                  and cost effective way to distribute air is a VAV system
Air-cooled chillers                                  3,200 Sq. Ft.    Air-cooled chillers                                  2,500 Sq. Ft.
                                                                                                                                                                                                                                                                                                                  (Variable Air Volume). These systems use an air
                                                                                                                                                Air Handlers
Cooling towers                                       7,000 Sq. Ft.    Cooling towers                                       3,000 Sq. Ft.
                                                                                                                                                Back-up Generator                                                            3’                                                                                   handling unit (supply fans w/filters and cooling coils) to
Tenant standby generators                            1,000 Sq. Ft.    Tenant standby generators                            1,000 Sq. Ft.
                                                                                                                                                                                                                                                                                                                  distribute conditioned air at pre-determined tempera-
House domestic water tanks                           600 Sq. Ft.      House domestic water tanks                           600 Sq. Ft.          Fuel oil piping                                                              2’                                                                                   tures in sufficient quantity to offset heat gains See sec-
Stair Pressurization Fans                            800 Sq. Ft.      Stair Pressurization Fans                            400 Sq. Ft.          Supply Ducts
                                                                                                                                                                                                                                                                                                                  tion 3.3. The space temperatures would be controlled
 Typical Floor Levels                                                  Typical Floor Levels                                                                                                                          14’                                                                                          by varying the volume flow rate of supply air by the use
                                                                                                                                                Return Ducts
Mechanical fan room                                  500 Sq. Ft.      Mechanical fan room                                  400 Sq. Ft.                                                                                                                                                                            of VAV control dampers above the ceiling. The on-floor
                                                                                                                                                                                                                             9’
 Basement Levels                                                       Basement Levels                                                                                                                                                                                                                            VAV system is a re-circulating system in which the air
Life saftey & tenant generators                      800 Sq. Ft.      Life saftey & tenant generators                      500 Sq. Ft.          Chiller                                                                                                                                                           from the space is returned above the hung ceiling acting
                                                                                                                                                Stair Pres. Fans
Fuel oil storage                                     1,000 Sq. Ft.    Fuel oil storage                                     300 Sq. Ft.                                                                                                                                                                            as a plenum. The air is then returned to the fan room
                                                                                                                                                Exhaust Chases
Boiler & chiller plant                               15,000 Sq. Ft.   Boiler Room                                          1,500 Sq. Ft.                                                                                                                                                                          at the core and back to chiller plants to be re-cooled.
                                                                                                                                                                                                                                      Fig. 12                                                                     Cooling loads distributed vary along with occupancy
                                                                                                                                                                                                                                      Typical VAV system air distribution showing above ceiling supply            levels and solar gain through the exterior skin. See sec-
                                                                                                                                                                                                                                      and return ducts and overhead diffusers to cool office spaces.
                                                                                                                                                                                                                                                                                                                  tion 6.2
                   Fuel Oil Piping
                   System Components
                                                                                                                                                                                                                                                                         45’
                   Return Air                                                                                                                                                                                                                                                                                     Raised Floor Distribution System
                   Supply Air
                   Exhaust                                                                                                                                                                                                                                                                                        In response to the demand for flexibility and change
                                                                                                                                                                                                                              3’                                                                                  in an office building, raised floors for distribution of air
                                                                                                                                                                                                                                                                                                                  and cabling are another design choice that provides
                                                                                                                                                                                                                             4”
                                                                                                                                                                                                                                                                                                                  easy modification and relocation options after they are
                                                                                                                                                Boilers
                                                                                                                                                                                                                                                                                                                  installed. Typically raised above the slab 12-18 inches,
                                                                                                                                                                                                                       14’
                                                                                                                                                                                                                                                                                                                  raised floors utilize lift-out floor modules that allow for
                                                                                                                                                                                                                                                                                                                  easy cable and outlet modification. In this case owner-
                                                                                                                                                                                                                             9’2
                                                                                                                                                                                                                                                                                                                  occupied buildings use this system more frequent be-
                                                                                                                                                                                                                                                                                                                  cause the occupant derives most of the benefit through
                                                                                                                                                                                                                                                                                                                  the buildings life. Air is supplied to the space from floor
                                                                                                                                                Fuel oil storage                                                             18”
                                                                                                                                                                                                                                                                                                                  diffusers instead of overhead, while on floor handlers
Fig. 9                                                                Fig. 10                                                              Fig. 11
Diagrammatic section of a typical low rise office building showing     Diagrammatic section of a typical mid rise office building showing    Diagrammatic section of a typical high rise office building showing                         Fig. 13                                                                     blow air into the floor cavities via supply ducts. Warm air
mechanical components and connections                                 mechanical components and connections                                mechanical components and connections                                                      Typical raised floor air distribution diagram showing under floor air
                                                                                                                                                                                                                                      supply ducts fed by a local AHU and plenum return duct back to
                                                                                                                                                                                                                                                                                                                  is returned to the air handlers by way of open plenum
                                                                                                                                                                                                                                      the core. Floor swirl diffusers allow for a cleaner striation of cool air   above the hung ceiling as the cool air, diffused low,
                                                                                                                                                                                                                                      below to warmer air above.
                                                                                                                                                                                                                                                                                                                  begins to heat and rise.
Portfolio 2010

More Related Content

Similar to Portfolio 2010

Microsoft Smart Buildings White Paper
Microsoft Smart Buildings White PaperMicrosoft Smart Buildings White Paper
Microsoft Smart Buildings White PaperMicrosoft India
 
Best Practices for React Developer Test Technical Assessment for Hiring.pdf
Best Practices for React Developer Test Technical Assessment for Hiring.pdfBest Practices for React Developer Test Technical Assessment for Hiring.pdf
Best Practices for React Developer Test Technical Assessment for Hiring.pdfDarshanaMallick
 
ReactJs Training in Hyderabad | ReactJS Training
ReactJs Training in Hyderabad  | ReactJS TrainingReactJs Training in Hyderabad  | ReactJS Training
ReactJs Training in Hyderabad | ReactJS Trainingeshwarvisualpath
 
ABC Architecture A New Approach To Build Reusable And Adaptable Business Tie...
ABC Architecture  A New Approach To Build Reusable And Adaptable Business Tie...ABC Architecture  A New Approach To Build Reusable And Adaptable Business Tie...
ABC Architecture A New Approach To Build Reusable And Adaptable Business Tie...Joshua Gorinson
 
IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...
IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...
IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...IRJET Journal
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESijwscjournal
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESijwscjournal
 
Referring Expressions with Rational Speech Act Framework: A Probabilistic App...
Referring Expressions with Rational Speech Act Framework: A Probabilistic App...Referring Expressions with Rational Speech Act Framework: A Probabilistic App...
Referring Expressions with Rational Speech Act Framework: A Probabilistic App...IJDKP
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESijwscjournal
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESijwscjournal
 
SADP PPTs of all modules - Shanthi D.L.pdf
SADP PPTs of all modules - Shanthi D.L.pdfSADP PPTs of all modules - Shanthi D.L.pdf
SADP PPTs of all modules - Shanthi D.L.pdfB.T.L.I.T
 
Lecture 9 - SOA in Context
Lecture 9 - SOA in ContextLecture 9 - SOA in Context
Lecture 9 - SOA in Contextphanleson
 
What is React programming used for_ .pdf
What is React programming used for_ .pdfWhat is React programming used for_ .pdf
What is React programming used for_ .pdfayushinwizards
 
The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...
The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...
The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...Mandar Trivedi
 
Reusability Framework for Cloud Computing
Reusability Framework for Cloud ComputingReusability Framework for Cloud Computing
Reusability Framework for Cloud ComputingDr Sukhpal Singh Gill
 
Tail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and Maps
Tail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and MapsTail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and Maps
Tail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and MapsTail-f Systems
 
IRJET- Code Reuse & Reusability of the Software
IRJET- Code Reuse & Reusability of the SoftwareIRJET- Code Reuse & Reusability of the Software
IRJET- Code Reuse & Reusability of the SoftwareIRJET Journal
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9VancityInstitute
 
3 f6 11_softdevmethodologies
3 f6 11_softdevmethodologies3 f6 11_softdevmethodologies
3 f6 11_softdevmethodologiesop205
 

Similar to Portfolio 2010 (20)

Microsoft Smart Buildings White Paper
Microsoft Smart Buildings White PaperMicrosoft Smart Buildings White Paper
Microsoft Smart Buildings White Paper
 
Best Practices for React Developer Test Technical Assessment for Hiring.pdf
Best Practices for React Developer Test Technical Assessment for Hiring.pdfBest Practices for React Developer Test Technical Assessment for Hiring.pdf
Best Practices for React Developer Test Technical Assessment for Hiring.pdf
 
ReactJs Training in Hyderabad | ReactJS Training
ReactJs Training in Hyderabad  | ReactJS TrainingReactJs Training in Hyderabad  | ReactJS Training
ReactJs Training in Hyderabad | ReactJS Training
 
ABC Architecture A New Approach To Build Reusable And Adaptable Business Tie...
ABC Architecture  A New Approach To Build Reusable And Adaptable Business Tie...ABC Architecture  A New Approach To Build Reusable And Adaptable Business Tie...
ABC Architecture A New Approach To Build Reusable And Adaptable Business Tie...
 
IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...
IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...
IRJET- Cloud-Based Naive Bayes Classifier for Dynamic Design to Support Usabi...
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
 
Referring Expressions with Rational Speech Act Framework: A Probabilistic App...
Referring Expressions with Rational Speech Act Framework: A Probabilistic App...Referring Expressions with Rational Speech Act Framework: A Probabilistic App...
Referring Expressions with Rational Speech Act Framework: A Probabilistic App...
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
 
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICESEARLY PERFORMANCE PREDICTION OF WEB SERVICES
EARLY PERFORMANCE PREDICTION OF WEB SERVICES
 
SADP PPTs of all modules - Shanthi D.L.pdf
SADP PPTs of all modules - Shanthi D.L.pdfSADP PPTs of all modules - Shanthi D.L.pdf
SADP PPTs of all modules - Shanthi D.L.pdf
 
Lecture 9 - SOA in Context
Lecture 9 - SOA in ContextLecture 9 - SOA in Context
Lecture 9 - SOA in Context
 
What is React programming used for_ .pdf
What is React programming used for_ .pdfWhat is React programming used for_ .pdf
What is React programming used for_ .pdf
 
The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...
The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...
The development of_the_lifecycle_function_model_by_idef0_for_construction_pro...
 
Reusability Framework for Cloud Computing
Reusability Framework for Cloud ComputingReusability Framework for Cloud Computing
Reusability Framework for Cloud Computing
 
Tail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and Maps
Tail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and MapsTail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and Maps
Tail f Systems Whitepaper - EMS and NMS Platforms - Beyond Alarms and Maps
 
IRJET- Code Reuse & Reusability of the Software
IRJET- Code Reuse & Reusability of the SoftwareIRJET- Code Reuse & Reusability of the Software
IRJET- Code Reuse & Reusability of the Software
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9
 
3 f6 11_softdevmethodologies
3 f6 11_softdevmethodologies3 f6 11_softdevmethodologies
3 f6 11_softdevmethodologies
 
Bl26411418
Bl26411418Bl26411418
Bl26411418
 

Portfolio 2010

  • 1. Selcted Architectural Work Brendan M Crosby, LEED GA 750 N Dearborn St. #705 Chicago, IL 60654
  • 2.
  • 3. 4 Table of Contents
  • 4. 5 masters thesis work 8 undergraduate work 16 professional work 28 graphics/misc. 38
  • 6.
  • 7. 8 Masters Thesis Work As part of a new pedagogical approach to its masters curriculum, Northeastern University proposed its students identify and study the inherenices in design of particular building typologies. After choosing the path of “office” typology, a thesis was developed in response to the requirement of transforming the existing type in terms of programmatic efficiencies, designs and user relations. ns trics Transforming the typology_Figure 1.1
  • 8. 9 The inherent design of mechanical systems, usually driven by service requirements and overall building function has been a recurring 1 11 paradigm in the typology of the high-rise office building. This design 8 9 not only dictates plant level program and service, but also forcefully embeds itself into architectural design and aesthetics. Could it be feasible to manipulate the pragmatics of the mechanical level, so 10 to serve the building more architecturally, introduce tenant-defined 7 1 occupiable space, and design a user oriented mechanical floor rather than a service driven one? 9 They typical pragmatism for mechanical decisions in the design of 8 high rise offices is that plant levels should number ten percent of total floors. In the essence of time, constructability, and efficiency of system 1 loads, theses levels are placed at roughly equal intervals through out 7 the structure and occupy the entire floor plate at double height. If in a 6 multitenant office building, mechanical level frequencies were doubled 6 and relegated to intervals not confined by serviceability and efficiency 4 of constructability, but by occupant relationship, one may begin to see a 1 change in how the nexus is perceived throughout the building in terms of 5 interconnectivity, program, and human-scale relation. Increasing plant level frequencies will result in the deduction from total 4 1 square footage per level, as inherencies such as numbers of air handling units and required duct space will decrease. Reclaimable space for 3 occupant use is a direct summation of that decrease and now the mechanical level may begin to transform into an element of architectural 4 inter-connectivity through programmatic decisions now feasible. The sky lobby is a feature commonly used in the typology of office high- rise, which incorporates public retail and service program with building 1 2 circulation. The reclaimable space on these mechanical levels can now serve as public retail, sky lobby, and tenant-specific front of house services; e.g. lobby and reception areas. 3 The objective of the proposal of this prototype is to transform the 2 1 mechanical floor, identify and reprogram consequent conditions, 1 ultimately reinventing the typology of the office high rise. Subsequently, 1 one can begin to propose new, fully grounded architectural decisions interrelated to site, tenant need, and program. Programing the Prototype_Figure 1.2
  • 9. 10 Masters Thesis Work 4. 3. 2. 1. 8. 8. 8. 9. 7. 5. 6. 6. 2. 4. 5. 3. 6. 1. 1. 8. 8. 7. 6. 4. Site Conncections Ground Level and Roof Garden_(Fig. 1.3 - 1.4) 2. 5. 3. 3. 4. 3. 5. 2. 1. 2. 3. 3. 1. 1. 6. 5. 4. 7.
  • 10. 11 Open Atrium Section_Fig. 1.7 Operable Skin Section_Fig. 1.8 Variations in floor plates in each ‘block’ of building mass lead to subsequent conditions in facade and skin treatment. Open-to-air atria conditions presented themselves in areas where the building skin was stretched past its actual glass facade and operable climate controlled spaces manifested in section where facade screening followed the buildings glass envelope.
  • 11. 12 Masters Thesis Work
  • 12. 13
  • 13. 14 Masters Thesis Work Introduction to a downtown Financial District site presented both challenges and opportunities for design and programming. A study of views from varying heights was conducted and placement of mechanical floors were derived according to changes in view. Programmatic and floor plan decisions were then made in relation to which part of the floor plate was most desirable. Mechanical spaces were placed in portions of the floor where views were blocked and the entire floor plate was twisted and programmed to take advantage of desirable views.
  • 14. 15
  • 16.
  • 17. 18 Local 7 Union Hall, Boston MA Unlike traditional design studios which produce a schematic idea before considering the feasibility of construction, this project grounds design proposals upon a conceived tectonic strategy. Students were asked to propose a new Union Hall for the Local 7 Ironworkers Labor Union on a prominent corner of the historic North End neighborhood of Boston. Preliminary research on Unions and their facilities preceded individual composition of a thesis, which was were used to drive design decisions. Program of the 30,000 sf structure includes lobby/gallery spaces, classrooms, a training facility, meeting halls, community rooms, dining halls, day care, exercise space, as well as administrative work rooms. An open plan and the elimination of segregated offices and floors for administration, along with large areas of glass penetration of the facade were a few techniques meant to integrate workers with community, and give the structure functionality to the public as well as the laborer. Rendering looking at northwest corner_(Fig. 2.6 ) Site Plan North End, Boston_(Fig. 2.6 )
  • 18. 19 Rendering looking at northwest corner_(Fig. 2.6 )
  • 19. 20 Local 7 Union Hall, Boston MA
  • 20. 21 Fifth Floor Level 58’-0” Fourth Floor Level 44’-6” Third Floor Level 31’-0” Second Floor Level 31’-0” First Floor Level 0’-0”
  • 21. 22 Local 7 Union Hall, Boston MA
  • 22. 23
  • 23. 24 South Boston Redevelopment Project This studio project focused on the design and development of urban housing, office space, and retail program within the Boston Redevelopment Authority’s ‘100 Acre Master Plan’ for the Fort Point District of South Boston. Students were assigned an undeveloped parcel with-in the master plan to program and design. Guidelines of the original master plan established by the governing planning agency were adhered to strictly in order to become aware of architectural issues that are controlled by such regulations. In addition, potential freedoms, and design opportunities that these situations present were studied and incorporated. Design responsibilities included street, pedestrian path and open space redesign, as well as open discussion and negotiation on reciprocal design relationships with abutting property owners.
  • 24. 25
  • 25. 26 South Boston Redevelopment Project
  • 26. 27
  • 28.
  • 29. 30 Bayport -Bluepoint Public Library This proposed addition and renovation of Bayport-Bluepoint Public Library’s existing 12,800 sf. building was carried from schematics through design development in its pre-refferendum stage. In addition to the complete renovation of its existing interior spaces, BHA and the Library Board agreed that a 14,300 sf. addition was needed to house a new Childrens LIbrary and Program Room. Responsibilities included composing presentation drawings (Elevation and site renderings, proposed floor plan reditions etc.) as well as attending client meetings and public design charrettes.
  • 30. 31
  • 31. 32 Flanders Nutritional & Community Center The scope of work on this project included the renovation of the existing 3,800 sf. Flanders Community Center, a senior center in Southampton, NY. The facility underwent major demolition, down to the steel structure. Also part of the scope, a 6,200 sf. two story addition at the south end of the building was constructed along with two smaller additions. As a major team member on this project, responsibilities ranged from site verification to schematic layout, through construction documentation and construction administration.
  • 32. 33
  • 33. 34 Flanders Nutritional & Community Center
  • 34. 35
  • 35. 36 Touro College Dormitories The school of Law at Touro College sought the services of BHA to design the residence hall for its campus in Islip, New York. The low-rise design consists of 12 single and 59 double units to accommodate its student population. This project was carried through to a complete set of bidding documents. Main responsibilities included schematic presentation and development, as well as bid set production. The wood frame design of the residences pushed the limits of wood frame construction, making meticulous coordination with structural and MEP engineers a vital part of the design process.
  • 36. 37
  • 38.
  • 39. 40 Learning Center, Los Angeles CA
  • 40. 41
  • 41. 42 Office Typology & Pattern Book As part of a group assignment aimed at thoroughly researching and documenting inherent designs of the office building typology, “Office: A Pattern Book” was written and published through Northeastern University. The publication studies and graphically displays the design patterns of typical office buildings categorized by size. Meticulous research, coordination and team efforts were displayed in the realization of this book which will serve as a guide and research source in the Northeastern University Architecture library. A RC G691 TY PO LO G Y PAT T E RN B O O K 6.4 Shading Systems 107 108 6.5 Atria Seasonal Shading 6.5 Atria In buildings with deeper floorplates or where a high While preventing solar gain is an important quality of natural light is a design priority, an atrium requirement of shading during the spring and is an excellent way of increasing the amount of summer months, solar gain can often be beneficial daylight that enters a building. The implementation during the colder months of the year. Allowing of an atrium effectively cuts an occupants solar gain in winter can reduce the amount maximum distance to daylight in half and allows of mechanical heating required to achieve a h l for a higher and more even level of daylighting Attached throughout the space. comfortable working environment, thus reducing a building’s total energy costs. For this reason, some of the most effective shading systems are w The best way to quantify the daylighting those that take advantage of the difference in solar performance of an atrium is by measuring angle between winter and summer. In addition to Fig. 21 - Atrium Measurements its Daylight Factor (DF). The Daylight Factor the solar heat gain benefits, these strategies will describes the ratio of outside illuminance over allow sunlight to penetrate deeper into the building inside illuminance, usually expressed as a during the dimmer winter months. percentage. The higher the DF, the more natural Linear PAR = w light is available in the atrium. The Daylight Factor One way to take advantage of this principle is to l is affected by the geometry of the atrium, as well size and position a building’s louvers so that they as its roof form and the reflectivity of its materials. block direct sunlight in the summer, when sun’s azimuth is greater, and allow sunlight to enter SAR = h Plan Aspect Ratio (PAR) in the winter, when the angle is lower (Fig. 18). The most efficient shape for the plan of an atrium w Another effective strategy is to use strategically is a circle. In atria with non-circular plans, the placed trees as a form of natural shading. In the Enclosed PAR can be used to measure the effectiveness summer, the trees will block sunlight and provide of the space’s geometry. The PAR is equal to the the building with shade. In the winter, when their WI = h x (l + w) atrium’s width divided by its length. An atrium branches are bare, they will allow sunlight to pass 2xlxw with a PAR closer to 1 (square) will have better through and enter the building. (Fig. 19) dayighting performance than one with a PAR closer to 0 (linear). Section Aspect Ratio (SAR) Fig. 18 - Seasonal Shading, Summer Fig. 19 - Natural Shading, Summer Semi-Enclosed The SAR measures the ratio of an atrium’s height (above) and Winter (above) and Winter Fig. 20 - Atrium Types to its width. A low SAR indicates a shallow atrium and a relatively high Daylight Factor.
  • 42. 128 7.3 Space Planning Patterns AR C G691 TYPOLOGY PATTER N BOOK 7.3 Space Planning Patterns 129 7.3 Space Planning Patterns The Organism 43 240° Program- Creative, Corporate -High Density -High Net Workspace Within Primary Reach Low High Low High -High Acoustic Transmission -High Potential Shared Worspace/Team Overlap -Moderate-High Visibility Sound Intesity Visual Overlap -Moderate Personal Identity -Moderate Project Team Mobility -Low-Moderate Enclosure Metrics Workspaces- 32 SF Per Worker- 85 sf LF worksurface- 320 lf LF Per Worker- 10 ft Floor Area- 2,728 sf Total Area of Worksurfaces- 768 sf Worksurface Area Per Worker- 24 sf Floor Area : Worksurface Area- 3.55:1 Plan Detail Fig. 15 Fig. 16 ARC G691 TY P O LO G Y PAT T E RN B O O K 3.2 Mechanical Circulation 51 52 3.3 Localized Air Distribution Systems Typical Mech. Space Req. for High Rise Office Typical Mech. Space Req. for Mid Rise Office 3.3 Localized Air Distribution Systems Variable Air Volume System (VAV) Typically in office building settings, the most efficient Penthouse Levels Penthouse Levels 45’ and cost effective way to distribute air is a VAV system Air-cooled chillers 3,200 Sq. Ft. Air-cooled chillers 2,500 Sq. Ft. (Variable Air Volume). These systems use an air Air Handlers Cooling towers 7,000 Sq. Ft. Cooling towers 3,000 Sq. Ft. Back-up Generator 3’ handling unit (supply fans w/filters and cooling coils) to Tenant standby generators 1,000 Sq. Ft. Tenant standby generators 1,000 Sq. Ft. distribute conditioned air at pre-determined tempera- House domestic water tanks 600 Sq. Ft. House domestic water tanks 600 Sq. Ft. Fuel oil piping 2’ tures in sufficient quantity to offset heat gains See sec- Stair Pressurization Fans 800 Sq. Ft. Stair Pressurization Fans 400 Sq. Ft. Supply Ducts tion 3.3. The space temperatures would be controlled Typical Floor Levels Typical Floor Levels 14’ by varying the volume flow rate of supply air by the use Return Ducts Mechanical fan room 500 Sq. Ft. Mechanical fan room 400 Sq. Ft. of VAV control dampers above the ceiling. The on-floor 9’ Basement Levels Basement Levels VAV system is a re-circulating system in which the air Life saftey & tenant generators 800 Sq. Ft. Life saftey & tenant generators 500 Sq. Ft. Chiller from the space is returned above the hung ceiling acting Stair Pres. Fans Fuel oil storage 1,000 Sq. Ft. Fuel oil storage 300 Sq. Ft. as a plenum. The air is then returned to the fan room Exhaust Chases Boiler & chiller plant 15,000 Sq. Ft. Boiler Room 1,500 Sq. Ft. at the core and back to chiller plants to be re-cooled. Fig. 12 Cooling loads distributed vary along with occupancy Typical VAV system air distribution showing above ceiling supply levels and solar gain through the exterior skin. See sec- and return ducts and overhead diffusers to cool office spaces. tion 6.2 Fuel Oil Piping System Components 45’ Return Air Raised Floor Distribution System Supply Air Exhaust In response to the demand for flexibility and change 3’ in an office building, raised floors for distribution of air and cabling are another design choice that provides 4” easy modification and relocation options after they are Boilers installed. Typically raised above the slab 12-18 inches, 14’ raised floors utilize lift-out floor modules that allow for easy cable and outlet modification. In this case owner- 9’2 occupied buildings use this system more frequent be- cause the occupant derives most of the benefit through the buildings life. Air is supplied to the space from floor Fuel oil storage 18” diffusers instead of overhead, while on floor handlers Fig. 9 Fig. 10 Fig. 11 Diagrammatic section of a typical low rise office building showing Diagrammatic section of a typical mid rise office building showing Diagrammatic section of a typical high rise office building showing Fig. 13 blow air into the floor cavities via supply ducts. Warm air mechanical components and connections mechanical components and connections mechanical components and connections Typical raised floor air distribution diagram showing under floor air supply ducts fed by a local AHU and plenum return duct back to is returned to the air handlers by way of open plenum the core. Floor swirl diffusers allow for a cleaner striation of cool air above the hung ceiling as the cool air, diffused low, below to warmer air above. begins to heat and rise.