INTERNSHIP
Phase –2 Review Presentation
By
Under the Guidence of
Mr.Gopalakrishnan N
Department of Civil Engineering
ASST. PROFESSOR
1
Name Roll Number
Mohammed Faizan ahmed 20191CIV9006
Section 8CIV02
2
1. Raft foundation
2. Column
3. Construction of beam and sand
4. Cement
5. Sands and aggregates
6. Materials
7. Time line
Content :
Raft Foundation:
3
Specification;
Area of Raft :506.17 m
• Thickness of Raft :550mm
• Grade of Concrete :M25(1:1:2)
• Grade of Steel :Fe500D
• Bottom reinforcement :20mm @110mmc/c (both ways)
• Top reinforcement :20mm @110mmc/c (both ways)
• Clear Cover :50mm Lap Length : 40
4
COLUMN :
• Layout of columns:
Check the location of columns from the datum location. If any deficiency take
place within permissible limits, made adjustments accordingly, otherwise
reconstruction of column is done.
Filling of starters:
Starters make the actual positions for const of column made of mortar or lean
concrete. Thickness varies from 4-6mm. Make the base to shuttering.
5
6
• Reinforcement of Columns:
Reinforcement is done as per given in drawings. Check should be made to the
splice length. As the lateral ties spacing varies along the length of column hence
spacing should be properly maintained.
Shuttering of columns;
Shuttering is either made of wooden or steel(Preferably steel). Vertically of
shuttering could be checked by using plumb bob and thread. Cover block must be
provided for better finishing of column.
Construction of beam and slab:
• Formwork of beam and slab :
Form work of main beam is first laid on the column, then secondary
beam shuttering is placed. After it, slab formwork is laid.
Shuttering is supported by tubular scaffolding which can be
adjusted later on .
8
9
10
• Reinforcement of slabs :
Firstly reinforcement of beam is done as per given in drawings. Care should be
taken for curtailed bar and maintain the spacing of sttruips. Then steel of slab is
laid down to the required spacing. Top bar and sunken portion should be properly
checked.
Levelling of beam and slab:
After the reinforcement the level of beam and slab are checked
a) Marking with the paint on the column bar at equal level mean of water pipe
b) Joint the all point by means of thread then with the help of tape check the
level of beam and slab. If required adjustment by mean of jack in scaffoldings.
11
CEMENT :
OPC ( Ordinary Portland cement )
• Used in construction of foundation, column, beam and slab
• Company name is Shree ultera cement
PPC ( Pozzolona Portland cement )
Used in finishing work like plastering pointing and brick work
Company name is Shree ultera cement
12
13
Sands and aggregates :
Sands :
• Classified as coarse sands and fine sands
• Having sizes varies from ….to….mm
• Obtained from Pathankot river
• Rate of one cubic meter is 750/- to 920/-
• Having effect of bulking if batching by volume.
14
• Aggregates :
• Classified as two sizes 10mm and 20mm
• Obtained from Pathankot crusher
• Rate of one cubic meter is 780/- to 850/-
15
16
Materials :
• Cement
• Coarse sand Battens
• Fine sand
• 10mm aggregates
• 20mm aggregates
• Steel
• Brick
• Admixture
• chips
17
18
TIME LINE
Commencement of project - 01 September 2022
Commencement of foundation and basement – January 17 2023
Expected completion of foundation and basement – April 30 2013
Expected Completion of project - December 2026
THANK YOU
19

More Related Content

Similar to Phase2 final.pptx

Basic Details (1).pptx
Basic Details (1).pptxBasic Details (1).pptx
Basic Details (1).pptx
Basavaprabhuprabhu2
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
Pravin Gaurav
 
Multi story building construction anshul
Multi story building construction anshulMulti story building construction anshul
Multi story building construction anshul
Anshul Shakya
 
Work check list
Work check listWork check list
tender6-7_040616.pdf
tender6-7_040616.pdftender6-7_040616.pdf
tender6-7_040616.pdf
KSLDESIGN
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
KriShna Sharma
 
Ferro cement by Dr.Vinay Kumar B M
Ferro cement by Dr.Vinay Kumar B MFerro cement by Dr.Vinay Kumar B M
Ferro cement by Dr.Vinay Kumar B M
VIDYA VIKAS INSTITUTE OF ENGINEERING AND TECHNOLOGY
 
Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)
Stephen Nzima
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
pradip dangar
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
chiranjeevulu chinthala
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
JaySinghchib1
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
y Sahaja
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
usamazahoor159
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
Mkh Nantu
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
IEI GSC
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
Akshay kumar
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
LingWei11
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 

Similar to Phase2 final.pptx (20)

Basic Details (1).pptx
Basic Details (1).pptxBasic Details (1).pptx
Basic Details (1).pptx
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Multi story building construction anshul
Multi story building construction anshulMulti story building construction anshul
Multi story building construction anshul
 
Work check list
Work check listWork check list
Work check list
 
tender6-7_040616.pdf
tender6-7_040616.pdftender6-7_040616.pdf
tender6-7_040616.pdf
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Ferro cement by Dr.Vinay Kumar B M
Ferro cement by Dr.Vinay Kumar B MFerro cement by Dr.Vinay Kumar B M
Ferro cement by Dr.Vinay Kumar B M
 
Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)Bo q for joint cuart hall block construction in pamir (3)
Bo q for joint cuart hall block construction in pamir (3)
 
Microtunel Construction / Secant Pile
Microtunel Construction / Secant PileMicrotunel Construction / Secant Pile
Microtunel Construction / Secant Pile
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Proportions of concrete
Proportions of concreteProportions of concrete
Proportions of concrete
 

More from Gopalakrishnan N

SCC Mix Design.pptx
SCC Mix Design.pptxSCC Mix Design.pptx
SCC Mix Design.pptx
Gopalakrishnan N
 
Mix Design - SCC.pptx
Mix Design - SCC.pptxMix Design - SCC.pptx
Mix Design - SCC.pptx
Gopalakrishnan N
 
Tower Cranes 1.pptx
Tower Cranes 1.pptxTower Cranes 1.pptx
Tower Cranes 1.pptx
Gopalakrishnan N
 
Mechanization in rebar fabrication.pptx
Mechanization in rebar fabrication.pptxMechanization in rebar fabrication.pptx
Mechanization in rebar fabrication.pptx
Gopalakrishnan N
 
9786447.ppt
9786447.ppt9786447.ppt
9786447.ppt
Gopalakrishnan N
 
PAVAN SEMINAR 001.pptx
PAVAN SEMINAR 001.pptxPAVAN SEMINAR 001.pptx
PAVAN SEMINAR 001.pptx
Gopalakrishnan N
 
Rent, Buy, Lease.pptx
Rent, Buy, Lease.pptxRent, Buy, Lease.pptx
Rent, Buy, Lease.pptx
Gopalakrishnan N
 
Water act
Water actWater act
Water act
Gopalakrishnan N
 

More from Gopalakrishnan N (8)

SCC Mix Design.pptx
SCC Mix Design.pptxSCC Mix Design.pptx
SCC Mix Design.pptx
 
Mix Design - SCC.pptx
Mix Design - SCC.pptxMix Design - SCC.pptx
Mix Design - SCC.pptx
 
Tower Cranes 1.pptx
Tower Cranes 1.pptxTower Cranes 1.pptx
Tower Cranes 1.pptx
 
Mechanization in rebar fabrication.pptx
Mechanization in rebar fabrication.pptxMechanization in rebar fabrication.pptx
Mechanization in rebar fabrication.pptx
 
9786447.ppt
9786447.ppt9786447.ppt
9786447.ppt
 
PAVAN SEMINAR 001.pptx
PAVAN SEMINAR 001.pptxPAVAN SEMINAR 001.pptx
PAVAN SEMINAR 001.pptx
 
Rent, Buy, Lease.pptx
Rent, Buy, Lease.pptxRent, Buy, Lease.pptx
Rent, Buy, Lease.pptx
 
Water act
Water actWater act
Water act
 

Recently uploaded

digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 

Recently uploaded (20)

digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 

Phase2 final.pptx

  • 1. INTERNSHIP Phase –2 Review Presentation By Under the Guidence of Mr.Gopalakrishnan N Department of Civil Engineering ASST. PROFESSOR 1 Name Roll Number Mohammed Faizan ahmed 20191CIV9006 Section 8CIV02
  • 2. 2 1. Raft foundation 2. Column 3. Construction of beam and sand 4. Cement 5. Sands and aggregates 6. Materials 7. Time line Content :
  • 3. Raft Foundation: 3 Specification; Area of Raft :506.17 m • Thickness of Raft :550mm • Grade of Concrete :M25(1:1:2) • Grade of Steel :Fe500D • Bottom reinforcement :20mm @110mmc/c (both ways) • Top reinforcement :20mm @110mmc/c (both ways) • Clear Cover :50mm Lap Length : 40
  • 4. 4
  • 5. COLUMN : • Layout of columns: Check the location of columns from the datum location. If any deficiency take place within permissible limits, made adjustments accordingly, otherwise reconstruction of column is done. Filling of starters: Starters make the actual positions for const of column made of mortar or lean concrete. Thickness varies from 4-6mm. Make the base to shuttering. 5
  • 6. 6 • Reinforcement of Columns: Reinforcement is done as per given in drawings. Check should be made to the splice length. As the lateral ties spacing varies along the length of column hence spacing should be properly maintained. Shuttering of columns; Shuttering is either made of wooden or steel(Preferably steel). Vertically of shuttering could be checked by using plumb bob and thread. Cover block must be provided for better finishing of column.
  • 7.
  • 8. Construction of beam and slab: • Formwork of beam and slab : Form work of main beam is first laid on the column, then secondary beam shuttering is placed. After it, slab formwork is laid. Shuttering is supported by tubular scaffolding which can be adjusted later on . 8
  • 9. 9
  • 10. 10 • Reinforcement of slabs : Firstly reinforcement of beam is done as per given in drawings. Care should be taken for curtailed bar and maintain the spacing of sttruips. Then steel of slab is laid down to the required spacing. Top bar and sunken portion should be properly checked. Levelling of beam and slab: After the reinforcement the level of beam and slab are checked a) Marking with the paint on the column bar at equal level mean of water pipe b) Joint the all point by means of thread then with the help of tape check the level of beam and slab. If required adjustment by mean of jack in scaffoldings.
  • 11. 11
  • 12. CEMENT : OPC ( Ordinary Portland cement ) • Used in construction of foundation, column, beam and slab • Company name is Shree ultera cement PPC ( Pozzolona Portland cement ) Used in finishing work like plastering pointing and brick work Company name is Shree ultera cement 12
  • 13. 13
  • 14. Sands and aggregates : Sands : • Classified as coarse sands and fine sands • Having sizes varies from ….to….mm • Obtained from Pathankot river • Rate of one cubic meter is 750/- to 920/- • Having effect of bulking if batching by volume. 14
  • 15. • Aggregates : • Classified as two sizes 10mm and 20mm • Obtained from Pathankot crusher • Rate of one cubic meter is 780/- to 850/- 15
  • 16. 16
  • 17. Materials : • Cement • Coarse sand Battens • Fine sand • 10mm aggregates • 20mm aggregates • Steel • Brick • Admixture • chips 17
  • 18. 18 TIME LINE Commencement of project - 01 September 2022 Commencement of foundation and basement – January 17 2023 Expected completion of foundation and basement – April 30 2013 Expected Completion of project - December 2026