This work order assigns Sri BiswajitPattnaik to lay OFC cable along the Raibidhar route of the BRM-KHJ6F cable. The work includes digging trenches of varying depths on soft soil, asphalted soil and concrete surfaces; laying protective and RCC pipes; splicing and pulling/blowing the 24 F OFC cable; and planting route indicators. The work must be completed within 20 days and will be supervised by Sri S.K. Sahu, the site engineer.