SlideShare a Scribd company logo
1 of 15
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
1 | P a g e
Documentation for
Completion of Grease and Odor Control Project
On Collection Line Using:
CLIENT - Severn Trent/MUD 163
LOCATION - 8507 Hot Springs Collection line H1-H2-H3-H4-H5-H6-H7-and
Lift Station # 1 8411 Sunny Ridge Dr. Houston Tx. 77095
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
2 | P a g e
Shannon Birdwells - President of the Board MUD 163 November 25, 2015
Board members of MUD 163
Bill Richmond & Cyrus Damas – Severn Trent Services
32259 Morton Road
Brookshire Tx. 77423
Re: Results of 3 month Micro-Solve® testing.
Mr. Birdwells,
Thank you and the board for the opportunity to do this important testing.
About Micro-Solve®:
Micro-Solve® is NOT a bacteria, not enzyme or a “quick-fix” emulsifier. Micro-Solve® turns your
problematic build-up into a food source to feed the populations of naturally occurring microorganisms.
Micro-Solve® dramatically increases facultative bacteria sending cleaner, healthier wastewater to the
WWTP. Micro-Solve® does NOT allow grease to stick on floats, pumps or re-solidify downstream. As the
system gets cleaner, less and less Micro-Solve® is needed to maintain the area.
Project Duration: 3 months
Application date and dosage and total gallon used:
Thursday August 6th
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
Thursday August 13th
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
Thursday August 20th
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
Thursday August 27th
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
Thursday September 3rd
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
Thursday September17th
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
3 | P a g e
Thursday October 1st
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
Thursday October 15th
: 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs **Last
Application**
Total Gallons used: 40 gallons.
Expected Results:
 No chokes during application period.
 Expect to see grease that was stuck to the pipes, come loose and move its way downstream into
the lift station.
 Lower H2S gasses down stream.
 Better wastewater going to the treatment plant.
 Over time the amount of grease in the lift station will decrease and less vacuuming required.
Results:
- There were zero chokes during the application.
- We are 4 weeks after the last application. Have there been any chokes?
- The collection line inspection graphs show great results that offer HUGE benefits.
- H1 to H2: Before and after shows that the camera made it through the line and the line showed no
obstructions and no debri build-up.
- H2 to H3: (same)Before and after shows that the camera made it through the line and the line
showed no obstructions and no debri build-up.
- H3 to H4: Before and after shows that the camera made it through the line and the line showed no
obstructions and no debri build-up.
- H4 to H5 to H6 to H7 to the lift station: This graph work did not show build-up or obstructions
before Micro-Solve® application and still shows no build-up or obstructions.
- The lift station continues to have no grease balls or chucks. The grease is not collected around the
floats like it was before Micro-Solve® application. The grease is not collected around the lip of the
lift station like it was before the Micro-Solve® application.
- The lift station was being vacced out every 6 months. Today it has been over 6 months since it
was vacced and because it is still clean, due to Micro-Solve®, it will not have to be vacced out for
many more months to come.
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
4 | P a g e
In Texas, Micro-Solve® has been solving grease, sludge, and odor issues for over 17 years. Micro-Solve® is
a proactive, beneficial solution tool that increases the bioremediation process by making the grease
better able to be used as food and also aids in increasing the microorganism populations that already
exist in the wastewater collection system. Micro-Solve® is a proactive, positive, PM approach to taking
care of your collection system and benefiting the treatment process.
Micro-Solve® works. Cleaning and eliminating grease and sludge in the collection lines and lift stations
creates a lot of cost effective benefits.
We hope to start working together on other areas that may be of concern with grease, sludge and odor
issues.
Thank you for testing Micro-Solve®. Please see below.
Sincere regards,
Troy Scott Najar
Chief
512.775.5358
http://www.egsw.us
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
5 | P a g e
Before Micro-Solve® H1-H2
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
6 | P a g e
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
7 | P a g e
After Micro-Solve® H1 to H2
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
8 | P a g e
Before Micro-Solve® H2 to H3
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
9 | P a g e
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
10 | P a g e
After Micro-Solve® H2 to H3
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
11 | P a g e
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
12 | P a g e
Before Micro-Solve® H3 to H4
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
13 | P a g e
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
14 | P a g e
After Micro-Solve® H3 to H4
P.O. Box 40843 Austin, TX 78704 512-775-5358
http://www.EGSW.US
http://MicroSolve.us
15 | P a g e

More Related Content

What's hot

Personal Project Methodology Framework
Personal Project Methodology FrameworkPersonal Project Methodology Framework
Personal Project Methodology FrameworkOleksiy Yegoshyn
 
מצגת נוזלי הגוף
מצגת  נוזלי הגוףמצגת  נוזלי הגוף
מצגת נוזלי הגוףtal zohar
 
Pgcet mca 2013 question paper
Pgcet   mca 2013 question paperPgcet   mca 2013 question paper
Pgcet mca 2013 question paperEneutron
 
Daily derivative report money classic research
Daily derivative report money classic researchDaily derivative report money classic research
Daily derivative report money classic researchMoney Classic Research
 

What's hot (7)

Louis resume 2010
Louis resume 2010Louis resume 2010
Louis resume 2010
 
Personal Project Methodology Framework
Personal Project Methodology FrameworkPersonal Project Methodology Framework
Personal Project Methodology Framework
 
Forklift Tire and Chain Wear Charts
Forklift Tire and Chain Wear ChartsForklift Tire and Chain Wear Charts
Forklift Tire and Chain Wear Charts
 
מצגת נוזלי הגוף
מצגת  נוזלי הגוףמצגת  נוזלי הגוף
מצגת נוזלי הגוף
 
Daily derivative report
Daily derivative reportDaily derivative report
Daily derivative report
 
Pgcet mca 2013 question paper
Pgcet   mca 2013 question paperPgcet   mca 2013 question paper
Pgcet mca 2013 question paper
 
Daily derivative report money classic research
Daily derivative report money classic researchDaily derivative report money classic research
Daily derivative report money classic research
 

Similar to MUD 163 Micro-Solve final report 11 21 15

Assent webinar cm3_updates-aug19-2014-slideshare
Assent webinar cm3_updates-aug19-2014-slideshareAssent webinar cm3_updates-aug19-2014-slideshare
Assent webinar cm3_updates-aug19-2014-slidesharebrytani
 
Basics of Grease Sampling: Grease Thief Goes to KSA
Basics of Grease Sampling: Grease Thief Goes to KSABasics of Grease Sampling: Grease Thief Goes to KSA
Basics of Grease Sampling: Grease Thief Goes to KSARich Wurzbach
 
Qss Business Card 31609 A
Qss Business Card 31609 AQss Business Card 31609 A
Qss Business Card 31609 AQSS
 
Assent webinar cm3_updates-aug19-2014-slideshare3
Assent webinar cm3_updates-aug19-2014-slideshare3Assent webinar cm3_updates-aug19-2014-slideshare3
Assent webinar cm3_updates-aug19-2014-slideshare3brytani
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 
Architecture Portfolio Sample
Architecture Portfolio SampleArchitecture Portfolio Sample
Architecture Portfolio SampleRafaela Ahsan
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingLean6Sigma4all
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.Raheem Arif
 
FM Magazine - April & May 2016 - Slippery when wet
FM Magazine - April & May 2016 - Slippery when wetFM Magazine - April & May 2016 - Slippery when wet
FM Magazine - April & May 2016 - Slippery when wetPaul Angus
 

Similar to MUD 163 Micro-Solve final report 11 21 15 (20)

Lean - Tight Oil Design & Construction
Lean - Tight Oil Design & ConstructionLean - Tight Oil Design & Construction
Lean - Tight Oil Design & Construction
 
Assent webinar cm3_updates-aug19-2014-slideshare
Assent webinar cm3_updates-aug19-2014-slideshareAssent webinar cm3_updates-aug19-2014-slideshare
Assent webinar cm3_updates-aug19-2014-slideshare
 
Basics of Grease Sampling: Grease Thief Goes to KSA
Basics of Grease Sampling: Grease Thief Goes to KSABasics of Grease Sampling: Grease Thief Goes to KSA
Basics of Grease Sampling: Grease Thief Goes to KSA
 
Work Portfolio_2015
Work Portfolio_2015Work Portfolio_2015
Work Portfolio_2015
 
Work portfolio 2015
Work portfolio 2015Work portfolio 2015
Work portfolio 2015
 
Qss Business Card 31609 A
Qss Business Card 31609 AQss Business Card 31609 A
Qss Business Card 31609 A
 
Assent webinar cm3_updates-aug19-2014-slideshare3
Assent webinar cm3_updates-aug19-2014-slideshare3Assent webinar cm3_updates-aug19-2014-slideshare3
Assent webinar cm3_updates-aug19-2014-slideshare3
 
New Frontiers of Lean Practice
New Frontiers of Lean PracticeNew Frontiers of Lean Practice
New Frontiers of Lean Practice
 
2006_Mar_SMT
2006_Mar_SMT2006_Mar_SMT
2006_Mar_SMT
 
The Lean Strategic Challenge
The Lean Strategic Challenge  The Lean Strategic Challenge
The Lean Strategic Challenge
 
ABCCOM Profile1
ABCCOM Profile1ABCCOM Profile1
ABCCOM Profile1
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
Architecture Portfolio Sample
Architecture Portfolio SampleArchitecture Portfolio Sample
Architecture Portfolio Sample
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream Mapping
 
Project
ProjectProject
Project
 
The Beginners Guide to Lean
The Beginners Guide to LeanThe Beginners Guide to Lean
The Beginners Guide to Lean
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 
FM Magazine - April & May 2016 - Slippery when wet
FM Magazine - April & May 2016 - Slippery when wetFM Magazine - April & May 2016 - Slippery when wet
FM Magazine - April & May 2016 - Slippery when wet
 
Office_Lean_sample
Office_Lean_sampleOffice_Lean_sample
Office_Lean_sample
 
Office Lean Sample
Office Lean SampleOffice Lean Sample
Office Lean Sample
 

MUD 163 Micro-Solve final report 11 21 15

  • 1. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 1 | P a g e Documentation for Completion of Grease and Odor Control Project On Collection Line Using: CLIENT - Severn Trent/MUD 163 LOCATION - 8507 Hot Springs Collection line H1-H2-H3-H4-H5-H6-H7-and Lift Station # 1 8411 Sunny Ridge Dr. Houston Tx. 77095
  • 2. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 2 | P a g e Shannon Birdwells - President of the Board MUD 163 November 25, 2015 Board members of MUD 163 Bill Richmond & Cyrus Damas – Severn Trent Services 32259 Morton Road Brookshire Tx. 77423 Re: Results of 3 month Micro-Solve® testing. Mr. Birdwells, Thank you and the board for the opportunity to do this important testing. About Micro-Solve®: Micro-Solve® is NOT a bacteria, not enzyme or a “quick-fix” emulsifier. Micro-Solve® turns your problematic build-up into a food source to feed the populations of naturally occurring microorganisms. Micro-Solve® dramatically increases facultative bacteria sending cleaner, healthier wastewater to the WWTP. Micro-Solve® does NOT allow grease to stick on floats, pumps or re-solidify downstream. As the system gets cleaner, less and less Micro-Solve® is needed to maintain the area. Project Duration: 3 months Application date and dosage and total gallon used: Thursday August 6th : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs Thursday August 13th : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs Thursday August 20th : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs Thursday August 27th : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs Thursday September 3rd : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs Thursday September17th : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs
  • 3. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 3 | P a g e Thursday October 1st : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs Thursday October 15th : 5 gallons of Micro-Solve® into South Side man hole on 8507 Hot Springs **Last Application** Total Gallons used: 40 gallons. Expected Results:  No chokes during application period.  Expect to see grease that was stuck to the pipes, come loose and move its way downstream into the lift station.  Lower H2S gasses down stream.  Better wastewater going to the treatment plant.  Over time the amount of grease in the lift station will decrease and less vacuuming required. Results: - There were zero chokes during the application. - We are 4 weeks after the last application. Have there been any chokes? - The collection line inspection graphs show great results that offer HUGE benefits. - H1 to H2: Before and after shows that the camera made it through the line and the line showed no obstructions and no debri build-up. - H2 to H3: (same)Before and after shows that the camera made it through the line and the line showed no obstructions and no debri build-up. - H3 to H4: Before and after shows that the camera made it through the line and the line showed no obstructions and no debri build-up. - H4 to H5 to H6 to H7 to the lift station: This graph work did not show build-up or obstructions before Micro-Solve® application and still shows no build-up or obstructions. - The lift station continues to have no grease balls or chucks. The grease is not collected around the floats like it was before Micro-Solve® application. The grease is not collected around the lip of the lift station like it was before the Micro-Solve® application. - The lift station was being vacced out every 6 months. Today it has been over 6 months since it was vacced and because it is still clean, due to Micro-Solve®, it will not have to be vacced out for many more months to come.
  • 4. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 4 | P a g e In Texas, Micro-Solve® has been solving grease, sludge, and odor issues for over 17 years. Micro-Solve® is a proactive, beneficial solution tool that increases the bioremediation process by making the grease better able to be used as food and also aids in increasing the microorganism populations that already exist in the wastewater collection system. Micro-Solve® is a proactive, positive, PM approach to taking care of your collection system and benefiting the treatment process. Micro-Solve® works. Cleaning and eliminating grease and sludge in the collection lines and lift stations creates a lot of cost effective benefits. We hope to start working together on other areas that may be of concern with grease, sludge and odor issues. Thank you for testing Micro-Solve®. Please see below. Sincere regards, Troy Scott Najar Chief 512.775.5358 http://www.egsw.us
  • 5. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 5 | P a g e Before Micro-Solve® H1-H2
  • 6. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 6 | P a g e
  • 7. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 7 | P a g e After Micro-Solve® H1 to H2
  • 8. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 8 | P a g e Before Micro-Solve® H2 to H3
  • 9. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 9 | P a g e
  • 10. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 10 | P a g e After Micro-Solve® H2 to H3
  • 11. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 11 | P a g e
  • 12. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 12 | P a g e Before Micro-Solve® H3 to H4
  • 13. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 13 | P a g e
  • 14. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 14 | P a g e After Micro-Solve® H3 to H4
  • 15. P.O. Box 40843 Austin, TX 78704 512-775-5358 http://www.EGSW.US http://MicroSolve.us 15 | P a g e