1. The meeting discussed issues around threats made to staff after bill submissions, scope of extra work items, and payments being held from the contractor. 2. It was decided that chimneys, cables, and basic landscaping were included in scope, while external lighting was not. Payments held from the contractor would be restored. 3. The contractor agreed to complete the work within 3 months and would provide a project completion plan by April 11th.