Minutes of the meeting held at coal block on 6.04.2012:
Present: Mr H Choudhury (MHFPL)
Mr T K Balaji (UL)
Mr B K Goyal (UL)
Mr Ankur Agarwal (KAPL)
Mr Amit Mehra (KAPL)
Mr Adarsh Jain (KAPL)
Mr Parag Saxena (KAPL)
Mr S N Jha (ECL)
Mr Basant Kumar (ESL)
Mr Chetan Todi (KCPL)
Mr Shiv Chandar Singh (KCPL’s Sub-contractor)
1. Mr Choudhury raised the point why threats were given to PMC staff by contractor after
every running bill is submitted for the last 2 months. Mr Chetan said that if it has happened
then it was and he will make sure that it will not be repeated in future .
2. Issue of extra items was raised by Ankur Agarwal and it was decided that only Chimney for
the generators and cables for transformer up to panel room and cable for DG to panel room
is required be considered . Regarding landscaping it was decided that grass and basic
landscaping will be provided by KCPL and balance will be managed by the MHFPL. Regarding
external lighting it was decided that it has to be provided by MHFPL and KCPL will do the
installation alone ie; labour charges will not be paid . With this the issue of extra items has
been closed and accepted by all. All other items are included in the scope of the contractor
which was accepted by Mr Chetan. Mr B K Goyal suggested that 20% which had been kept in
abeyance out of KCPL’s payment be added back as they have agreed to all work and the
same old payment schedule be adopted hence forth for passing /payment of their future
bill. Mr Choudhury and Mr Chetan both agreed to the same.
3. Mr Chetan said that they can complete the work within 3 months. It was decided that KCPL
will present a road map of activities for completion of the project within 3 months time, for
this they require time upto 11.04.2012.
4. Mr Adarsh Jain raised the point that KCPL has not provided unions in the water down comer
lines. Mr S N Jha and Basant objected that Adarsh Jain should have told them to do so while
the line installation was done at that time itself and should have prevented them . Now
telling them to provide unions in every floor will involve additional labour cost . Mr Adarsh
has resisted saying that it was told to them in the beginning itself but their staff refuses to
listen. It was finally decided that KCPL will provide the required union connections to every
floor without claiming any extra amount.
5. Mr Adarsh said that plumbing work is only 50% complete as of today and unless the
plumbing labour is doubled ,work cannot be completed within 3 months. He said that they
had only 8 skilled persons in the plumbing front.
6. Regarding Electrical work, Mr Chetan said that since they were facing fund constraints due
to delayed payments from MHFPL, they were unable to purchase the required cables etc
and that’s why there is delay in the work. Mr Choudhury said that only Rs 40 lacs of the old
payment was balance in KCPL’s account and all other payments had been cleared, so where
was the problem. Mr Chetan referred about the recent bill of dt 3rd
April which is pending
.However Mr Chetan agreed that by 16th
April`12 this work will also be started and
completed by 15th
May`12.
7. Most of the materials, in the scope of supply of MHFPL, have been supplied i.e. Ceramic
tiles, Vetrified Tiles, Granite, Sanitary ware, C.P fittings, Electrical boxes, switches and plates.
Mr S N Jha and Mr Chetan raised the point of supply of Kota stone, for which Mr BKG has
told them to complete the work of fitting of all the materials supplied and Kota stone, HVAC,
and Light fittings will follow.
8. Mr Chetan raised the point that he may be allotted further work for which Mr Choudhury
and Mr B K G have told him clearly that work can only be allotted after the existing work is
completed in all respects.
9. Mr Choudhury informed Mr Chetan that incase work is not completed in 3 months then any
payment made to the PMC beyond 3 months (till June 2012))will be recovered from their
bill. Mr Chetan said that no evaluation of delay has been done so far, for which Mr
Choudhury said that he is only talking about the further 3 months and not the past. Mr
Choudhary has once again stressed Mr Chetan to prepare a realistic road map of the
activities for completion of the project and to send before 11.04.2012, which was agreed by
Mr Chetan .

More Related Content

Featured

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
Marius Sescu
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
Expeed Software
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
Pixeldarts
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
marketingartwork
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
Skeleton Technologies
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
Neil Kimberley
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
contently
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
Albert Qian
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
Search Engine Journal
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
SpeakerHub
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
Tessa Mero
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Lily Ray
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
Rajiv Jayarajah, MAppComm, ACC
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
Christy Abraham Joy
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
Vit Horky
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
MindGenius
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
RachelPearson36
 

Featured (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Mom with kcpl dt 6.4.12

  • 1. Minutes of the meeting held at coal block on 6.04.2012: Present: Mr H Choudhury (MHFPL) Mr T K Balaji (UL) Mr B K Goyal (UL) Mr Ankur Agarwal (KAPL) Mr Amit Mehra (KAPL) Mr Adarsh Jain (KAPL) Mr Parag Saxena (KAPL) Mr S N Jha (ECL) Mr Basant Kumar (ESL) Mr Chetan Todi (KCPL) Mr Shiv Chandar Singh (KCPL’s Sub-contractor) 1. Mr Choudhury raised the point why threats were given to PMC staff by contractor after every running bill is submitted for the last 2 months. Mr Chetan said that if it has happened then it was and he will make sure that it will not be repeated in future . 2. Issue of extra items was raised by Ankur Agarwal and it was decided that only Chimney for the generators and cables for transformer up to panel room and cable for DG to panel room is required be considered . Regarding landscaping it was decided that grass and basic landscaping will be provided by KCPL and balance will be managed by the MHFPL. Regarding external lighting it was decided that it has to be provided by MHFPL and KCPL will do the installation alone ie; labour charges will not be paid . With this the issue of extra items has been closed and accepted by all. All other items are included in the scope of the contractor which was accepted by Mr Chetan. Mr B K Goyal suggested that 20% which had been kept in abeyance out of KCPL’s payment be added back as they have agreed to all work and the same old payment schedule be adopted hence forth for passing /payment of their future bill. Mr Choudhury and Mr Chetan both agreed to the same. 3. Mr Chetan said that they can complete the work within 3 months. It was decided that KCPL will present a road map of activities for completion of the project within 3 months time, for this they require time upto 11.04.2012. 4. Mr Adarsh Jain raised the point that KCPL has not provided unions in the water down comer lines. Mr S N Jha and Basant objected that Adarsh Jain should have told them to do so while the line installation was done at that time itself and should have prevented them . Now telling them to provide unions in every floor will involve additional labour cost . Mr Adarsh has resisted saying that it was told to them in the beginning itself but their staff refuses to listen. It was finally decided that KCPL will provide the required union connections to every floor without claiming any extra amount. 5. Mr Adarsh said that plumbing work is only 50% complete as of today and unless the plumbing labour is doubled ,work cannot be completed within 3 months. He said that they had only 8 skilled persons in the plumbing front. 6. Regarding Electrical work, Mr Chetan said that since they were facing fund constraints due to delayed payments from MHFPL, they were unable to purchase the required cables etc and that’s why there is delay in the work. Mr Choudhury said that only Rs 40 lacs of the old payment was balance in KCPL’s account and all other payments had been cleared, so where was the problem. Mr Chetan referred about the recent bill of dt 3rd April which is pending
  • 2. .However Mr Chetan agreed that by 16th April`12 this work will also be started and completed by 15th May`12. 7. Most of the materials, in the scope of supply of MHFPL, have been supplied i.e. Ceramic tiles, Vetrified Tiles, Granite, Sanitary ware, C.P fittings, Electrical boxes, switches and plates. Mr S N Jha and Mr Chetan raised the point of supply of Kota stone, for which Mr BKG has told them to complete the work of fitting of all the materials supplied and Kota stone, HVAC, and Light fittings will follow. 8. Mr Chetan raised the point that he may be allotted further work for which Mr Choudhury and Mr B K G have told him clearly that work can only be allotted after the existing work is completed in all respects. 9. Mr Choudhury informed Mr Chetan that incase work is not completed in 3 months then any payment made to the PMC beyond 3 months (till June 2012))will be recovered from their bill. Mr Chetan said that no evaluation of delay has been done so far, for which Mr Choudhury said that he is only talking about the further 3 months and not the past. Mr Choudhary has once again stressed Mr Chetan to prepare a realistic road map of the activities for completion of the project and to send before 11.04.2012, which was agreed by Mr Chetan .