PEMERIKSAAN TERHADAP :
K-3 RAMPAS, FIRE EXTINGUISER, SAFETY LINE, SAFETY NET. APD, P3K
INPUT
PROSEDUR K 3
Quality Supervisor
DIPERBAKI
Pelaksana / Ass. Pel.
Pengawas K3
PENAWASAN
RUTIN
NO
PEMASANGAN :
TASK
- RAMBU-RAMBU K 3
- PEMADAM KEBAKARAN
- PAGAR PENGAMAN
PERIKSA :
- LOKASI
- KEKUATAN
YES
DISETUJUI
- JARING PENGAMAN - KEAMANAN
Pengawas K3 Pengawas K3
Pelaksana / Ass. Pelaksana
OUTPUT LAPORAN HARIAN
Pengawas K3
IMPLEMENTATION PROCEDURE
K-3
K 3 TERHADAP SISTEM OIL PIPE
INPUT
PROSEDUR K 3
OIL PIPE SYSTEM
Qualit
y
Superv
isor
DIPERBAKI
NO
DIPERIKSA
YES
BERSAMA
Pengawas K3
Mechanical Work
TASK
RENCANA GAMBAR SISTEM
OIL PIPE :
DRAIN INSTALLATION
PIPE EXISTING & LIFTING
INSTALLATION OIL PIPE
Mechanic
al Work
INSTALLATION OIL PIPE
SESUAI
GAMBAR RENCANA
Mechanical Work
Mechanical Work
PELAKSANAAN
PEKERJAAN
OUTPUT
INSTALLATION PIPE
BAIK
- LAPORAN HARIAN
Pengawas K3 Mechanical
Work
PROSEDUR PELAKSANAAN
K3
A. DATA TEKNIS :
1. NAMA PROYEK
2. JUMLAH TITIK PONDASI
3. DIAMETER BORED PILE
4. KEDALAMAN BORE PILE
:
:
:
:
5. MUTU BETON
6. MUTU BESI UNTUK SPIRAL
7. MUTU BESI UNTUK TULANGAN POKOK
8. VOLUME BETON PEK. TTK BORED PILE
9. BERAT KERANJANG
:
:
:
:
:
B. PERALATAN YANG DIGUNAKAN :
1. SERVICE CRANE
2. KELLY
3. AUGER MACHINE
4. DIESEL GENSET
5. PIPE CASING DIA. 0.8 M, LENGTH = 16 M
6. CLEANING BUCKET
7. PIPE TREMIE
8. THEODLITE
9. READY MIX (TRUCK MIXER)
10. TREMIE PIPE CONE
C. SQUENCE OF WORKS :
A. PEKERJAAN PERSIAPAN
1. UKUR DAN TENTUKAN POSISI TITIK – TITIK BORE PILE DI SITE
2. BUAT PABRIKASI KERANJANG BESI BORE PILE
3. BUAT SHEDULE PENGECORAN BORED PILE DAN TERUS
DIKENDALIKAN
4. BUAT FORMAT UNTUK MONITORING REPORT BORE PILE
B. PEKERJAAN BORED PILE
1. SET ALAT PADA POSISI TITIK YANG AKAN DI BOR
2. BILA KONDISI LAPISAN TANAH BAIK
- BOR SAMPAI KEDALAMAN 6 m SAJA
DAN PASANG CASING 6 m
TEMPORARY FULL CASING
5 – 6 M
3. BILA KONDISI LAPISAN TANAH JELEK
- GUNAKAN FULL CASING UNTUK
MENCEGAH KELONGSORAN TANAH
PADA SAAT PROSES BORING
- MASUKKAN FULL CASING KEDALAM
LUBANG BOR SEBELUM PROSES
PENGEBORAN DIMULAI DENGAN ALAT
BANTU VIBRO HAMMER
GENSET
METHODE KERJA PONDASI BORED PILE
METHODE KERJA PONDASI BORED PILE
4. KEMUDIAN DILANJUTKAN DENGAN PROSES PENGEBORAN SAMPAI
KEDALAMAN YANG DIKEHENDAKI
5. CHECK APAKAH KEDALAMAN YANG DIKEHENDAKI SUDAH TERCAPAI
ELEV. – 6.00
TEMPORARY
CASING 6 M
6. BERSIHKAN LUMPUR PADA DASAR LUBANG BOR DENGAN
BUCKET CLEANING
7. SELAMA PROSES BERLANGSUNG, CATAT :
- KEDALAMAN MUKA AIR TANAH
- JENIS LAPISAN TANAH BERIKUT DEDALAMAN DAN KETEBALAN
DARI LAPISAN TANAH
8. BUAT LAPORAN HARIAN BORE PILE
ELEV. – 6.00
TEMPORARY FULL CASING
(BILA DIPERLUKAN)
CLEANING BUCKET
METHODE KERJA PONDASI BORED PILE
D. CONCRETE WORK
1. PESAN BETON K - 400., SLUMP 18 +/- 2 CM, KE BATCHING
PLAN
2. PASANG KERANJANG BESI
ELEV. – 6.00
TEMPORARY FULL CASING
DIA. 80 cm L=16 M
KERANJANG PEMBESIAN KERANJANG PEMBESIAN
PIPA TREMI
TEMPORARY FULL CASING
DIA. 80 cm L=16 M
3. PASANG PIPA TREMI BILA TERDAPAT MUKA AIR TANAH DALAM LUBANG BOR
4. JIKA TIDAK ADA AIR TANAH PENGGUNAAN PIPATREMIC TIDAK MUTLAK
DIPERLUKAN (CUKUP PAKAI CORONG)
METHODE KERJA PONDASI BORED PILE
5. PROSES PENGECORAN PONDASI BORE PILE
SELAMA PROSES BERLANGSUNG, CHECK ADAKAH VOLUME
TEORITIC PER LUBANG SUDAH SESUAI DENGAN VOLUME BETON
YANG DIKIRIM / DICOR KEDALAM LUBANG
6.
7.
SEGERA SETELAH PENGECORAN SLESAI, TARIKTEMPORARY CASING DARI
LUBANG BOR
PEKERJAAN BOR SELESAI
TEMPORARY FULL CASING
KERANJANG BESI
PIPA TREMI
TEMPORARY FULL
CASING
DASAR
EXISTING
METHODE OF BORED PILE FOUNDATION
1.25
M
13 M
BORE PILE
DIA. 80cm
OVER POUR WILL
BE CUT OFF
SAND FILLING
STRUKTUR PONDASI BORED PILE
A. METHODE URUTAN BORED PILE AND COR
8. BILA BATAS PENGECORAN AKHIR PONDASI BORE PILE TERLETAK
DIKEDALAMAN TERTENTU DARI MUKA TANAH
- ISI VOLUME LUBANG TERSEBUT DENGAN PASIR
DENGAN DASAR PERTIMBANGAN K 3
FLOW
CHART
METHOD
OF
BORED
PILE
WORK
METHODE PEKERJAAN BORED PILE
A. SEBELUM PENGEBORAN DIBUAT
TEST-PIT TERLEBIH DAHULU DAN
SEGALA SESUATU
PEKERJAAN SURVEY
B. PENGEBORAN DIBUAT DALAM 2
(DUA) TAHAPAN YANG BERBEDA
YAITU :
- ZONE A
- ZONE B
MENGGUNAKAN 1 (SATU) UNIT
ALAT BOR DAN 1 (SATU) UNIT
SERVICE CRANE
C. PEMBUATAN (RANJANG) PEMBESIAN
DISESUAIKAN LOKASI STOCK PILE
D. CAPASITAS PRODUKSI KURANG
LEBIH 2 – 3 TITIK/HARI
START
UITZET
BONGKAR ASPAL/
RIGID. PAV
STEL BESI
(RANJANG)
CASSING + VERTICALITY
+ MASUK BESI RANJANG
PENGEBORAN
GALIAN
1.50 – 2.00
M
SETTING ALAT
TUTUP KEMBALI
BEKAS LUBANG
FINISH
COR
METHODE PEKERJAAN BENTONITE
A. DATA TEKNIS SEBAGAI
BERIKUT :
- DIA. 60 cm
- L = 11 – 18 m
- 1 m3 = 60 kg SEMUA BENTONITE +
300 kg SEMEN
B. PENENTUAN TITIK BOR
C. PENGEBORAN SESUAIKAN PEIL
KEDALAMAN YANG
DITENTUKAN
D. COR YAITU :
-TUANGKAN SEMUA SEMEN
BENTONITE (SESUAI MIX
DESIGN) KEDALAM BUCKET COR /
CONCRETE PUMP KEMUDIAN
LUAPANNYA DIALIRKAN KE
TANK BENTONITE
- SETELAH SEMEN BENTONITE
MASUKKAN KEDALAM LUBANG
SAMPAI MELUAP DAN FRESH
SEHINGGA DIDAPATKAN
KAPASTIAN BAHWA LUBANG
TELAH FULL SELANJUTNYA
SEGERA PIPA TREMIE DAN CASING
DICABUT ARTINYA BAHWA
PEMBUATAN BENTONITE PILE
TELAH SELESAI
METHODE PEKERJAAN JEMBATAN
( TOP DOWN )
A. BONGKAR ASPAL / RIGIT PAV DAN GALIAN TANAH
DAN PEMOTONGAN KEPALA BORED PILE
B. PENGUKURAN UNTUK MENENTUKAN PEIL DAN
BUAT / PASANG BEKISTING YAITU TERDIRI :
- PEMADATAN TANAH
- PAS. LANTAI KERJA
- PAS. MULTIPLEX 12 mm
(BILA TIDAK TERGALI MAKA MENGGUNAKAN
BEKISTING BATACO)
C. STEL PEMBESIAN SESUAI GBR / BISTAT
D. PENGECORAN YAITU SETELAH PEMBERSIHAN
DAN PENENTUAN PEIL
BORED PILE
MULTIPLEX 12 mm
LT. KERJA
COR CAPPING BEAM
COR (PLAT JEMBATAN
METHODE PEMANCANGAN SHEET PILE
A. PEMANCANGAN DIBUAT DALAM 2 TAHAP BERSAMAAN
YAITU SISI KIRI DAN KANAN (LIHAT GAMBAR)
DENGAN MENGGUNKAN 2 ALAT YAITU MASING-MASING
1 UNIT DRIVE PILING DAN 1 UNIT SERVICE CRANE
PENGIRIMAN DARI WORK SHOP DISESUAIKAN
DENGAN HASIL PEMANCANGAN DILAPANGAN
(KARENA STOCK PILE TERBATAS)
B. SEBELUM PANCANG LEBIH DAHULU DIBUAT
TEST-PIT DAN GUIDE BEAM SEPANJANG
RETAINNING WALL SEBAGAI REFERENSI
(HARUS KOKOH / KUAT) UNTUK CEK
TERHADAP VERTIKAL / HORIZONTAL
C. CAPASITAS PRODUKSI KURANG LEBIH 4 – 5 TITIK/HARI
DAN HARUS ADA DATA KALENDERING
START
UITZET
BONGKAR ASPAL/
RIGID. PAV
KEDALAMAN
SHEET PILE
SHEET PILE UP
PASANG GUIDE BEAM
GALIAN
1.50 – 2.00
M
SETTING ALAT
TUTUP KEMBALI
BEKAS LUBANG
FINISH
PEMANCANGAN
FLOW CHART PEKERJAAN
START
PERSIAPAN
KOORDINASI DENGAN INSTANSI TERKAIT
JARINGAN/PIPA/GAS/DLL
/
PELEBARAN JALAN PADA
TROTOAR / PENEBANGAN
PEMINDAHAN
POHON
CAPPING BEAM
PEKERJAAN SHEET PILE
GALIAN
1.50 – 2.00
M
TRAFIC MANAGEMENT
FINISH
TRAFIC MANAGEMENT
PEKERJAAN BORED PILE
PEIR / ABUTMENT JEMBATAN
SLAB & OPRIT JEMBATAN
YA / TIDAK
YA TIDAK
FLOW CHART PEKERJAAN
START
PERSIAPAN
KOORDINASI DENGAN INSTANSI TERKAIT
JARINGAN/PIPA/GAS/DLL
/
PELEBARAN JALAN PADA
TROTOAR / PENEBANGAN
PEMINDAHAN
POHON
CAPPING BEAM
PEKERJAAN SHEET PILE
GALIAN
1.50 – 2.00
M
TRAFIC MANAGEMENT
FINISH
TRAFIC MANAGEMENT
PEKERJAAN BORED PILE
PEIR / ABUTMENT JEMBATAN
SLAB & OPRIT JEMBATAN
YA / TIDAK
YA TIDAK

Method Statement HSE & Bor Pail Project.pptx

  • 1.
    PEMERIKSAAN TERHADAP : K-3RAMPAS, FIRE EXTINGUISER, SAFETY LINE, SAFETY NET. APD, P3K INPUT PROSEDUR K 3 Quality Supervisor DIPERBAKI Pelaksana / Ass. Pel. Pengawas K3 PENAWASAN RUTIN NO PEMASANGAN : TASK - RAMBU-RAMBU K 3 - PEMADAM KEBAKARAN - PAGAR PENGAMAN PERIKSA : - LOKASI - KEKUATAN YES DISETUJUI - JARING PENGAMAN - KEAMANAN Pengawas K3 Pengawas K3 Pelaksana / Ass. Pelaksana OUTPUT LAPORAN HARIAN Pengawas K3 IMPLEMENTATION PROCEDURE K-3
  • 2.
    K 3 TERHADAPSISTEM OIL PIPE INPUT PROSEDUR K 3 OIL PIPE SYSTEM Qualit y Superv isor DIPERBAKI NO DIPERIKSA YES BERSAMA Pengawas K3 Mechanical Work TASK RENCANA GAMBAR SISTEM OIL PIPE : DRAIN INSTALLATION PIPE EXISTING & LIFTING INSTALLATION OIL PIPE Mechanic al Work INSTALLATION OIL PIPE SESUAI GAMBAR RENCANA Mechanical Work Mechanical Work PELAKSANAAN PEKERJAAN OUTPUT INSTALLATION PIPE BAIK - LAPORAN HARIAN Pengawas K3 Mechanical Work PROSEDUR PELAKSANAAN K3
  • 3.
    A. DATA TEKNIS: 1. NAMA PROYEK 2. JUMLAH TITIK PONDASI 3. DIAMETER BORED PILE 4. KEDALAMAN BORE PILE : : : : 5. MUTU BETON 6. MUTU BESI UNTUK SPIRAL 7. MUTU BESI UNTUK TULANGAN POKOK 8. VOLUME BETON PEK. TTK BORED PILE 9. BERAT KERANJANG : : : : : B. PERALATAN YANG DIGUNAKAN : 1. SERVICE CRANE 2. KELLY 3. AUGER MACHINE 4. DIESEL GENSET 5. PIPE CASING DIA. 0.8 M, LENGTH = 16 M 6. CLEANING BUCKET 7. PIPE TREMIE 8. THEODLITE 9. READY MIX (TRUCK MIXER) 10. TREMIE PIPE CONE C. SQUENCE OF WORKS : A. PEKERJAAN PERSIAPAN 1. UKUR DAN TENTUKAN POSISI TITIK – TITIK BORE PILE DI SITE 2. BUAT PABRIKASI KERANJANG BESI BORE PILE 3. BUAT SHEDULE PENGECORAN BORED PILE DAN TERUS DIKENDALIKAN 4. BUAT FORMAT UNTUK MONITORING REPORT BORE PILE B. PEKERJAAN BORED PILE 1. SET ALAT PADA POSISI TITIK YANG AKAN DI BOR 2. BILA KONDISI LAPISAN TANAH BAIK - BOR SAMPAI KEDALAMAN 6 m SAJA DAN PASANG CASING 6 m TEMPORARY FULL CASING 5 – 6 M 3. BILA KONDISI LAPISAN TANAH JELEK - GUNAKAN FULL CASING UNTUK MENCEGAH KELONGSORAN TANAH PADA SAAT PROSES BORING - MASUKKAN FULL CASING KEDALAM LUBANG BOR SEBELUM PROSES PENGEBORAN DIMULAI DENGAN ALAT BANTU VIBRO HAMMER GENSET METHODE KERJA PONDASI BORED PILE
  • 4.
    METHODE KERJA PONDASIBORED PILE 4. KEMUDIAN DILANJUTKAN DENGAN PROSES PENGEBORAN SAMPAI KEDALAMAN YANG DIKEHENDAKI 5. CHECK APAKAH KEDALAMAN YANG DIKEHENDAKI SUDAH TERCAPAI ELEV. – 6.00 TEMPORARY CASING 6 M 6. BERSIHKAN LUMPUR PADA DASAR LUBANG BOR DENGAN BUCKET CLEANING 7. SELAMA PROSES BERLANGSUNG, CATAT : - KEDALAMAN MUKA AIR TANAH - JENIS LAPISAN TANAH BERIKUT DEDALAMAN DAN KETEBALAN DARI LAPISAN TANAH 8. BUAT LAPORAN HARIAN BORE PILE ELEV. – 6.00 TEMPORARY FULL CASING (BILA DIPERLUKAN) CLEANING BUCKET
  • 5.
    METHODE KERJA PONDASIBORED PILE D. CONCRETE WORK 1. PESAN BETON K - 400., SLUMP 18 +/- 2 CM, KE BATCHING PLAN 2. PASANG KERANJANG BESI ELEV. – 6.00 TEMPORARY FULL CASING DIA. 80 cm L=16 M KERANJANG PEMBESIAN KERANJANG PEMBESIAN PIPA TREMI TEMPORARY FULL CASING DIA. 80 cm L=16 M 3. PASANG PIPA TREMI BILA TERDAPAT MUKA AIR TANAH DALAM LUBANG BOR 4. JIKA TIDAK ADA AIR TANAH PENGGUNAAN PIPATREMIC TIDAK MUTLAK DIPERLUKAN (CUKUP PAKAI CORONG)
  • 6.
    METHODE KERJA PONDASIBORED PILE 5. PROSES PENGECORAN PONDASI BORE PILE SELAMA PROSES BERLANGSUNG, CHECK ADAKAH VOLUME TEORITIC PER LUBANG SUDAH SESUAI DENGAN VOLUME BETON YANG DIKIRIM / DICOR KEDALAM LUBANG 6. 7. SEGERA SETELAH PENGECORAN SLESAI, TARIKTEMPORARY CASING DARI LUBANG BOR PEKERJAAN BOR SELESAI TEMPORARY FULL CASING KERANJANG BESI PIPA TREMI TEMPORARY FULL CASING DASAR EXISTING
  • 7.
    METHODE OF BOREDPILE FOUNDATION 1.25 M 13 M BORE PILE DIA. 80cm OVER POUR WILL BE CUT OFF SAND FILLING STRUKTUR PONDASI BORED PILE A. METHODE URUTAN BORED PILE AND COR 8. BILA BATAS PENGECORAN AKHIR PONDASI BORE PILE TERLETAK DIKEDALAMAN TERTENTU DARI MUKA TANAH - ISI VOLUME LUBANG TERSEBUT DENGAN PASIR DENGAN DASAR PERTIMBANGAN K 3
  • 8.
  • 9.
    METHODE PEKERJAAN BOREDPILE A. SEBELUM PENGEBORAN DIBUAT TEST-PIT TERLEBIH DAHULU DAN SEGALA SESUATU PEKERJAAN SURVEY B. PENGEBORAN DIBUAT DALAM 2 (DUA) TAHAPAN YANG BERBEDA YAITU : - ZONE A - ZONE B MENGGUNAKAN 1 (SATU) UNIT ALAT BOR DAN 1 (SATU) UNIT SERVICE CRANE C. PEMBUATAN (RANJANG) PEMBESIAN DISESUAIKAN LOKASI STOCK PILE D. CAPASITAS PRODUKSI KURANG LEBIH 2 – 3 TITIK/HARI START UITZET BONGKAR ASPAL/ RIGID. PAV STEL BESI (RANJANG) CASSING + VERTICALITY + MASUK BESI RANJANG PENGEBORAN GALIAN 1.50 – 2.00 M SETTING ALAT TUTUP KEMBALI BEKAS LUBANG FINISH COR
  • 10.
    METHODE PEKERJAAN BENTONITE A.DATA TEKNIS SEBAGAI BERIKUT : - DIA. 60 cm - L = 11 – 18 m - 1 m3 = 60 kg SEMUA BENTONITE + 300 kg SEMEN B. PENENTUAN TITIK BOR C. PENGEBORAN SESUAIKAN PEIL KEDALAMAN YANG DITENTUKAN D. COR YAITU : -TUANGKAN SEMUA SEMEN BENTONITE (SESUAI MIX DESIGN) KEDALAM BUCKET COR / CONCRETE PUMP KEMUDIAN LUAPANNYA DIALIRKAN KE TANK BENTONITE - SETELAH SEMEN BENTONITE MASUKKAN KEDALAM LUBANG SAMPAI MELUAP DAN FRESH SEHINGGA DIDAPATKAN KAPASTIAN BAHWA LUBANG TELAH FULL SELANJUTNYA SEGERA PIPA TREMIE DAN CASING DICABUT ARTINYA BAHWA PEMBUATAN BENTONITE PILE TELAH SELESAI
  • 11.
    METHODE PEKERJAAN JEMBATAN (TOP DOWN ) A. BONGKAR ASPAL / RIGIT PAV DAN GALIAN TANAH DAN PEMOTONGAN KEPALA BORED PILE B. PENGUKURAN UNTUK MENENTUKAN PEIL DAN BUAT / PASANG BEKISTING YAITU TERDIRI : - PEMADATAN TANAH - PAS. LANTAI KERJA - PAS. MULTIPLEX 12 mm (BILA TIDAK TERGALI MAKA MENGGUNAKAN BEKISTING BATACO) C. STEL PEMBESIAN SESUAI GBR / BISTAT D. PENGECORAN YAITU SETELAH PEMBERSIHAN DAN PENENTUAN PEIL BORED PILE MULTIPLEX 12 mm LT. KERJA COR CAPPING BEAM COR (PLAT JEMBATAN
  • 12.
    METHODE PEMANCANGAN SHEETPILE A. PEMANCANGAN DIBUAT DALAM 2 TAHAP BERSAMAAN YAITU SISI KIRI DAN KANAN (LIHAT GAMBAR) DENGAN MENGGUNKAN 2 ALAT YAITU MASING-MASING 1 UNIT DRIVE PILING DAN 1 UNIT SERVICE CRANE PENGIRIMAN DARI WORK SHOP DISESUAIKAN DENGAN HASIL PEMANCANGAN DILAPANGAN (KARENA STOCK PILE TERBATAS) B. SEBELUM PANCANG LEBIH DAHULU DIBUAT TEST-PIT DAN GUIDE BEAM SEPANJANG RETAINNING WALL SEBAGAI REFERENSI (HARUS KOKOH / KUAT) UNTUK CEK TERHADAP VERTIKAL / HORIZONTAL C. CAPASITAS PRODUKSI KURANG LEBIH 4 – 5 TITIK/HARI DAN HARUS ADA DATA KALENDERING START UITZET BONGKAR ASPAL/ RIGID. PAV KEDALAMAN SHEET PILE SHEET PILE UP PASANG GUIDE BEAM GALIAN 1.50 – 2.00 M SETTING ALAT TUTUP KEMBALI BEKAS LUBANG FINISH PEMANCANGAN
  • 13.
    FLOW CHART PEKERJAAN START PERSIAPAN KOORDINASIDENGAN INSTANSI TERKAIT JARINGAN/PIPA/GAS/DLL / PELEBARAN JALAN PADA TROTOAR / PENEBANGAN PEMINDAHAN POHON CAPPING BEAM PEKERJAAN SHEET PILE GALIAN 1.50 – 2.00 M TRAFIC MANAGEMENT FINISH TRAFIC MANAGEMENT PEKERJAAN BORED PILE PEIR / ABUTMENT JEMBATAN SLAB & OPRIT JEMBATAN YA / TIDAK YA TIDAK
  • 14.
    FLOW CHART PEKERJAAN START PERSIAPAN KOORDINASIDENGAN INSTANSI TERKAIT JARINGAN/PIPA/GAS/DLL / PELEBARAN JALAN PADA TROTOAR / PENEBANGAN PEMINDAHAN POHON CAPPING BEAM PEKERJAAN SHEET PILE GALIAN 1.50 – 2.00 M TRAFIC MANAGEMENT FINISH TRAFIC MANAGEMENT PEKERJAAN BORED PILE PEIR / ABUTMENT JEMBATAN SLAB & OPRIT JEMBATAN YA / TIDAK YA TIDAK