The document provides a weekly update on progress for the Wizards Stadium Project for the week of May 10, 2010. Current activities included mass excavation and grading, installation of site utilities like electrical ductbanks and storm sewers, ongoing foundation work including footings and drilled piers, and structural steel erection in various areas. Projected activities for the following week included continuing mass excavation, site utility installation, starting deep underground plumbing, and further foundation and structural steel work. Additional photos documented the ongoing construction progress.