SlideShare a Scribd company logo
From:    Brandon Valdez                    To: David Ficklin - OnGoal
                                                                            Rory O’Connor – OnGoal
                             Office: Kansas City                            Lee Turner – OnGoal
                             Date:    5.12.2010                             Andy Heitmann – Turner
                                                                            Dave Dudzik - Turner
                             Re:      Wizards Stadium Project
                                      Update – Week of
                                      5.10.2010



 Current Activities this Week:

 Mass Excavation:
 Grading is ongoing in Area 3. Backfilling of on-grade
 is ongoing in Area 1.

 Site Utilities:
 Installation of the new electrical ductbank is ongoing.
                                                               Field Level Area 2 – A-Line and Field Wall
 Storm Sewer installation (Line 6000) is ongoing on            Footings ready for concrete placement.
 east side of France Family Drive.

 Foundations:
 Area 2 Field Level – Footing installation will be complete
 to Column Line 12 by the end of the day.

 Area 1 Mezzanine Level – Installation of Elevator Pit walls
 are complete.

 Area 4 Mezzanine Level – Installation of Drilled Piers
 are ongoing.                                                  Field Level Area 3 – Drilled Pier installation is
                                                               ongoing.
 Structural Steel Erection:
 Area 1 – Steel Erection in sequence 1-1 is nearly
 complete. Sequence 1-2 has started and is currently
 being erected in the Column Line 27/26 Bay.

 Decking is nearly complete in sequence 1-1 on
 Mezzanine and Concourse Levels.


                                                               France Family Drive – Storm Line 6000
                                                               installation is ongoing.
Building the Future
Underground Electrical:
 Secondary service ducts is complete from Electrical Room
 01.34.04 south past Column Line 25.

 Installation of secondary service ducts at Column Line D
 are ongoing.


 Projected Activities occurring next Week:
                                                                Concourse Level Area 1 – Decking installed
                                                                at Main Club.
 Mass Excavation:
 Grading at Truck Dock Area will continue.

 Site Utilities:
 Installation of the Storm Line 6000 on the East Side (France
 Family Drive) of the site will continue.

 Deep Underground Plumbing:
 Sanitary in Area 3 will begin.

 Foundations:                                                   Area 1 – Structural Steel Erection at West
 Area 2 Field Level – Placement of foundation walls east of     Building continues. B-Line Columns being
 Stage will begin.                                              set at Column Lines 26 and 27.

 Area 3 Field Level – Footing excavation will begin.

 Structural Steel Erection:
 Erection of Structural Steel in Sequence 1-2 will continue.




                                                                Field Level Area 1 – Shot looking north from
                                                                Concourse Level.




Building the Future
Additional Photos:




Field Level Area 2 – Foundations taking    Mezzanine Level Area 1 – VIP Entrance
shape at Stage.                            taking shape.




Field Level Area 1 – Shot of the Stadium   Concourse Level Area 2 – E-Line Footings
Suite from Column Line 30 (Field Level).   installed to Column Line 20.




Area 1 – Shot looking North West showing   Concourse Level Area 2 – Electrical ductbank
West Building Structural Steel.            installation is ongoing.




Building the Future

More Related Content

Viewers also liked

Disaster Recovery with OnState and Google Apps
Disaster Recovery with OnState and Google AppsDisaster Recovery with OnState and Google Apps
Disaster Recovery with OnState and Google Apps
OnState Communications
 
PhD defense Koen Deschacht
PhD defense Koen DeschachtPhD defense Koen Deschacht
PhD defense Koen Deschacht
guest1add48f
 
OnState Spring '10 Updates
OnState Spring '10 UpdatesOnState Spring '10 Updates
OnState Spring '10 Updates
OnState Communications
 
Superbes photos
Superbes photosSuperbes photos
Superbes photos
Joyeux Nain
 
Gartenkunst chine
Gartenkunst chineGartenkunst chine
Gartenkunst chineJoyeux Nain
 
Misogyne ou clairvoyant
Misogyne ou clairvoyantMisogyne ou clairvoyant
Misogyne ou clairvoyant
Joyeux Nain
 
La France en 2060
La France en 2060La France en 2060
La France en 2060
Joyeux Nain
 
Paris et les métiers d'antan
Paris et les métiers d'antanParis et les métiers d'antan
Paris et les métiers d'antanJoyeux Nain
 

Viewers also liked (8)

Disaster Recovery with OnState and Google Apps
Disaster Recovery with OnState and Google AppsDisaster Recovery with OnState and Google Apps
Disaster Recovery with OnState and Google Apps
 
PhD defense Koen Deschacht
PhD defense Koen DeschachtPhD defense Koen Deschacht
PhD defense Koen Deschacht
 
OnState Spring '10 Updates
OnState Spring '10 UpdatesOnState Spring '10 Updates
OnState Spring '10 Updates
 
Superbes photos
Superbes photosSuperbes photos
Superbes photos
 
Gartenkunst chine
Gartenkunst chineGartenkunst chine
Gartenkunst chine
 
Misogyne ou clairvoyant
Misogyne ou clairvoyantMisogyne ou clairvoyant
Misogyne ou clairvoyant
 
La France en 2060
La France en 2060La France en 2060
La France en 2060
 
Paris et les métiers d'antan
Paris et les métiers d'antanParis et les métiers d'antan
Paris et les métiers d'antan
 

Similar to Memo wizards 05-12-2010

Construction Update 07-28-2010
Construction Update 07-28-2010Construction Update 07-28-2010
Construction Update 07-28-2010
Kansas City Wizards
 
Construction Update 7-6-2010
Construction Update 7-6-2010Construction Update 7-6-2010
Construction Update 7-6-2010
Kansas City Wizards
 
KC Soccer Stadium
KC Soccer Stadium KC Soccer Stadium
KC Soccer Stadium
Kansas City Wizards
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
Kansas City Wizards
 
Memo wizards 08-25-2010
Memo wizards 08-25-2010Memo wizards 08-25-2010
Memo wizards 08-25-2010
Kansas City Wizards
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
Kansas City Wizards
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
Fairfax County
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
Honolulu Civil Beat
 

Similar to Memo wizards 05-12-2010 (8)

Construction Update 07-28-2010
Construction Update 07-28-2010Construction Update 07-28-2010
Construction Update 07-28-2010
 
Construction Update 7-6-2010
Construction Update 7-6-2010Construction Update 7-6-2010
Construction Update 7-6-2010
 
KC Soccer Stadium
KC Soccer Stadium KC Soccer Stadium
KC Soccer Stadium
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
 
Memo wizards 08-25-2010
Memo wizards 08-25-2010Memo wizards 08-25-2010
Memo wizards 08-25-2010
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 

Memo wizards 05-12-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 5.12.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 5.10.2010 Current Activities this Week: Mass Excavation: Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1. Site Utilities: Installation of the new electrical ductbank is ongoing. Field Level Area 2 – A-Line and Field Wall Storm Sewer installation (Line 6000) is ongoing on Footings ready for concrete placement. east side of France Family Drive. Foundations: Area 2 Field Level – Footing installation will be complete to Column Line 12 by the end of the day. Area 1 Mezzanine Level – Installation of Elevator Pit walls are complete. Area 4 Mezzanine Level – Installation of Drilled Piers are ongoing. Field Level Area 3 – Drilled Pier installation is ongoing. Structural Steel Erection: Area 1 – Steel Erection in sequence 1-1 is nearly complete. Sequence 1-2 has started and is currently being erected in the Column Line 27/26 Bay. Decking is nearly complete in sequence 1-1 on Mezzanine and Concourse Levels. France Family Drive – Storm Line 6000 installation is ongoing. Building the Future
  • 2. Underground Electrical: Secondary service ducts is complete from Electrical Room 01.34.04 south past Column Line 25. Installation of secondary service ducts at Column Line D are ongoing. Projected Activities occurring next Week: Concourse Level Area 1 – Decking installed at Main Club. Mass Excavation: Grading at Truck Dock Area will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Deep Underground Plumbing: Sanitary in Area 3 will begin. Foundations: Area 1 – Structural Steel Erection at West Area 2 Field Level – Placement of foundation walls east of Building continues. B-Line Columns being Stage will begin. set at Column Lines 26 and 27. Area 3 Field Level – Footing excavation will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 1-2 will continue. Field Level Area 1 – Shot looking north from Concourse Level. Building the Future
  • 3. Additional Photos: Field Level Area 2 – Foundations taking Mezzanine Level Area 1 – VIP Entrance shape at Stage. taking shape. Field Level Area 1 – Shot of the Stadium Concourse Level Area 2 – E-Line Footings Suite from Column Line 30 (Field Level). installed to Column Line 20. Area 1 – Shot looking North West showing Concourse Level Area 2 – Electrical ductbank West Building Structural Steel. installation is ongoing. Building the Future