Weekly Construction Update 05-19-2010

823 views

Published on

KC Soccer Stadium construction update from Turner Construction.

Published in: Sports
  • Be the first to comment

  • Be the first to like this

Weekly Construction Update 05-19-2010

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 5.19.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 5.17.2010 Current Activities this Week: Mass Excavation: Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1. Site Utilities: Installation of the new electrical ductbank is complete. Field Level Area 1 – Wizards Team Bench Storm Sewer installation (Line 6000) is ongoing on concrete is placed. east side of France Family Drive. Foundations: Area 3 Field Level – Footing installation is ongoing and is Complete to Column Line 6. Area 4 Mezzanine Level – Installation of Drilled Piers are ongoing. Structural Steel Erection: Field Level Area 1 – South Field Wall Area 1 – Steel Erection in sequence 1-2 is nearly installation is ongoing. complete to Column Line 23 Decking is nearly complete in sequence 1-1 on Mezzanine and Concourse Levels. Installation of studs and edge plates have started. Decking on Suite Level has started. Area 2 – Electrical Ductbank relocation is complete. Building the Future
  2. 2. Underground Electrical: Secondary service ducts is complete from Electrical Room 01.34.04 south past Column Line 25. Installation of secondary service ducts at Column Line D Is installed to Column Line 24. Projected Activities occurring next Week: Concourse Level Area 1 – Decking, studs and edge plating installed at Main Club. Mass Excavation: Grading at Truck Dock Area will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Deep Underground Plumbing: Sanitary in Area 3 will continue. Area 1 – Structural Steel Erection at West Foundations: Building to Suite Level 1 Floor is nearly Area 2 Field Level – Placement of foundation walls east of complete to 23-Line. Stage will continue. Area 3 Field Level – Footing placement will continue and wall installation will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 1-4 will begin. Decking installation on Suite Level of Sequence 1-1 will continue. Field Level Area 1 – Shot looking north from Concourse Level. Building the Future
  3. 3. Additional Photos: Field Level Area 1 – Concrete encasement of Field Level Area 3 – Wall reinforcing mats Structural Steel columns. installed at SE vomitory and A-Line wall. Field Level Area 2 – A-Line reinforcing in Field Level Area 1 – Hydrotherapy pit base place from Column Lines 14-12. concrete being installed. Mezzanine Level Area 1 – Decking, studs and edge plating nearly complete at VIP Field Level Area 1 – Shot looking NW at Entrance. Wizards Team Bench Area. Building the Future

×