 Current Activities this Week:

 Mass Excavation:
 Backfilling of on-grade seating is ongoing in Area 2
 and Area 3.

 Site Utilities:
 Storm Sewer installation (Line 1000) is ongoing along      Concourse Level Area 2 – Underground
 Village West Parkway.                                      plumbing rough-in for the Concourse
                                                            Buildings is ongoing.
 Storm Line Installation (Line 600 and Sanitary Sewer
 Line E installation is ongoing on east side of France
 Family Dive is ongoing.

 Foundations:
 Area 3 Field Level – Isolated footing installation is
 Ongoing and is currently to Column Line 6.

 Area 4 Mezzanine Level – Excavation for D-Line footing
 Is ongoing and is currently to Column Line 40.             Field Level Area 1 – Vapor barrier
                                                            installation from column line 32-29 is placed
 Concrete Flatwork:                                         in preparation for slab-on-grade placement.
 Area 1 – Mezzanine slab-on deck is complete, Main
 Concourse structural slab is complete, Suite Level slab
 on deck is complete, Press Level slab on deck is
 complete. Preparation for 1st pour of Field Level Area 1
 slab-on-grade is ongoing.




                                                            Area 1 – Precast concrete treads and riser
                                                            installation is nearly complete between
                                                            column lines 32-24.
Building the Future
Structural Steel Erection:
 Area 1 –Detailing and decking in sequence 1-3 is ongoing.
 Erection of Steel Sequence 2-1 has started.

 Area 1 – Roof deck installation for entire West Building is
 nearly complete.

 Underground MEP:
 Electrical Secondary Distribution is ongoing in Area 3.         Area 1 –Canopy Trusses are being delivered
                                                                 and staged in the infield.
 MEP Rough-in:
 Area 1 – Shallow electrical and plumbing rough-in has
 started at Field Level in preparation for 1st slab-on-grade
 pour.

 Metal Stud Framing:
 Area 1 Suite Level – Metal stud framing for Suites has
 started.

 Projected Activities occurring next Week:
                                                                 Area 1 – Shot of the West Building from the
 Mass Excavation:                                                southeast.
 Backfilling of on-grade seating areas will continue in Area
 3.

 Site Utilities:
 Installation of the Storm Line 6000 on the East Side (France
 Family Drive) of the site will continue. Storm Line 1000
 will continue. Installation of Sanitary Line E will continue.

 Deep Underground MEP:
 Deep Sanitary and Electrical Distribution installation
 in Area 3 will continue.
                                                                 Roof Level Area 1 – Roof decking is nearly
 Foundations:                                                    complete.
 Area 3 Field Level – Foundation installation will continue.

 Area 4 Mezzanine Level – Foundation Wall installation will
 continue.




Building the Future
Concrete Flatwork:
 Area 1 Field Level – Concrete placement for slab-on-grade
 will begin.

 Structural Steel Erection:
 Erection of Structural Steel in Sequence 2-1 will
 continue.

 Delivery of Roof Trusses for sequence 1-7 will continue        Area 2 – Shot looking south of Terrace Area
 throughout the week.                                           taking shape.

 Structural Precast:
 Erection of the precast tubs in Area 1 will begin.

 Underground MEP:
 Deep Sanitary installation will continue in Area 3.

 Electrical Secondary will continue in Area 3.

 MEP Rough-in:
 Plumbing and Electrical rough-in for Area 1 Field Level slab
 on grade will continue.                                        Field Level Area 3 – Foundation installation
                                                                is ongoing.
 Metal Stud Framing:
 Area 1 Suite Level – Metal stud framing for Suites will
 continue.

 Area 1 Press Level – Metal stud framing for Suites will
 begin.




Building the Future
Additional Photos:




Field Level Area 1 – Shot of Player’s field   Field Level Area 3 – Field wall footing
entry.                                        concrete placed at column line 4.




Suite Level Area 1 – Metal stud framing for   Area 1 – Subgrade preparation for on-grade
suites has begun.                             seating risers has started.




Suite Level Area 1 – Duct straps being
installed in preparation for ductwork         Roof Level Area 1 – Shot of steel framing for
installation.                                 Freight Elevator “High Hat”.




Building the Future

More Related Content

Viewers also liked

Conseil Municipal du 18 juillet 2012 - le compte-rendu
Conseil Municipal du 18 juillet 2012 - le compte-renduConseil Municipal du 18 juillet 2012 - le compte-rendu
Conseil Municipal du 18 juillet 2012 - le compte-rendu
Communication Clermont
 
Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...
Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...
Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...
Communication Clermont
 
Conseil Municipal du 12 mars 2012 - le compte-rendu
Conseil Municipal du 12 mars 2012 - le compte-renduConseil Municipal du 12 mars 2012 - le compte-rendu
Conseil Municipal du 12 mars 2012 - le compte-rendu
Communication Clermont
 
Conseil Municipal du 13 avril 2011 - le compte-rendu
Conseil Municipal du 13 avril 2011 - le compte-renduConseil Municipal du 13 avril 2011 - le compte-rendu
Conseil Municipal du 13 avril 2011 - le compte-rendu
Communication Clermont
 
Conseil Municipal du 03 février 2011 - le compte-rendu
Conseil Municipal du 03 février 2011 - le compte-renduConseil Municipal du 03 février 2011 - le compte-rendu
Conseil Municipal du 03 février 2011 - le compte-rendu
Communication Clermont
 
Conseil Municipal du 12 juin 2012 - le compte-rendu
Conseil Municipal du 12 juin 2012 - le compte-renduConseil Municipal du 12 juin 2012 - le compte-rendu
Conseil Municipal du 12 juin 2012 - le compte-rendu
Communication Clermont
 
Ville de Clermont - Compte-rendu - CM du 6 mars 2013
Ville de Clermont - Compte-rendu - CM du 6 mars 2013Ville de Clermont - Compte-rendu - CM du 6 mars 2013
Ville de Clermont - Compte-rendu - CM du 6 mars 2013
Communication Clermont
 
Sur la Brêche - Hors-Série Noël 2011
Sur la Brêche - Hors-Série Noël 2011Sur la Brêche - Hors-Série Noël 2011
Sur la Brêche - Hors-Série Noël 2011
Communication Clermont
 
Ville de Clermont - Sur la Brèche - Printemps 2011
Ville de Clermont - Sur la Brèche - Printemps 2011Ville de Clermont - Sur la Brèche - Printemps 2011
Ville de Clermont - Sur la Brèche - Printemps 2011
Communication Clermont
 

Viewers also liked (9)

Conseil Municipal du 18 juillet 2012 - le compte-rendu
Conseil Municipal du 18 juillet 2012 - le compte-renduConseil Municipal du 18 juillet 2012 - le compte-rendu
Conseil Municipal du 18 juillet 2012 - le compte-rendu
 
Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...
Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...
Bibliothèque de Clermont Oise : Blablabook - Comité de lecture - Sélection Ar...
 
Conseil Municipal du 12 mars 2012 - le compte-rendu
Conseil Municipal du 12 mars 2012 - le compte-renduConseil Municipal du 12 mars 2012 - le compte-rendu
Conseil Municipal du 12 mars 2012 - le compte-rendu
 
Conseil Municipal du 13 avril 2011 - le compte-rendu
Conseil Municipal du 13 avril 2011 - le compte-renduConseil Municipal du 13 avril 2011 - le compte-rendu
Conseil Municipal du 13 avril 2011 - le compte-rendu
 
Conseil Municipal du 03 février 2011 - le compte-rendu
Conseil Municipal du 03 février 2011 - le compte-renduConseil Municipal du 03 février 2011 - le compte-rendu
Conseil Municipal du 03 février 2011 - le compte-rendu
 
Conseil Municipal du 12 juin 2012 - le compte-rendu
Conseil Municipal du 12 juin 2012 - le compte-renduConseil Municipal du 12 juin 2012 - le compte-rendu
Conseil Municipal du 12 juin 2012 - le compte-rendu
 
Ville de Clermont - Compte-rendu - CM du 6 mars 2013
Ville de Clermont - Compte-rendu - CM du 6 mars 2013Ville de Clermont - Compte-rendu - CM du 6 mars 2013
Ville de Clermont - Compte-rendu - CM du 6 mars 2013
 
Sur la Brêche - Hors-Série Noël 2011
Sur la Brêche - Hors-Série Noël 2011Sur la Brêche - Hors-Série Noël 2011
Sur la Brêche - Hors-Série Noël 2011
 
Ville de Clermont - Sur la Brèche - Printemps 2011
Ville de Clermont - Sur la Brèche - Printemps 2011Ville de Clermont - Sur la Brèche - Printemps 2011
Ville de Clermont - Sur la Brèche - Printemps 2011
 

Similar to Construction Update 7-6-2010

Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
Kansas City Wizards
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
Kansas City Wizards
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
Kansas City Wizards
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
Fairfax County
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportHonolulu Civil Beat
 
Feb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress ReportFeb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress ReportHonolulu Civil Beat
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportHonolulu Civil Beat
 

Similar to Construction Update 7-6-2010 (8)

Construction Update 5-12-2010
Construction Update 5-12-2010Construction Update 5-12-2010
Construction Update 5-12-2010
 
Construction Update 4-14-2010
Construction Update 4-14-2010Construction Update 4-14-2010
Construction Update 4-14-2010
 
Construction Update 4-7-2010
Construction Update 4-7-2010Construction Update 4-7-2010
Construction Update 4-7-2010
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily Report
 
Feb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress ReportFeb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress Report
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress Report
 

Recently uploaded

Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Recruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media MasterclassRecruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media Masterclass
LuanWise
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
Corey Perlman, Social Media Speaker and Consultant
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
FelixPerez547899
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
Norma Mushkat Gaffin
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
HARSHITHV26
 
Auditing study material for b.com final year students
Auditing study material for b.com final year  studentsAuditing study material for b.com final year  students
Auditing study material for b.com final year students
narasimhamurthyh4
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
Adam Smith
 

Recently uploaded (20)

Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Recruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media MasterclassRecruiting in the Digital Age: A Social Media Masterclass
Recruiting in the Digital Age: A Social Media Masterclass
 
Authentically Social Presented by Corey Perlman
Authentically Social Presented by Corey PerlmanAuthentically Social Presented by Corey Perlman
Authentically Social Presented by Corey Perlman
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
Mastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnapMastering B2B Payments Webinar from BlueSnap
Mastering B2B Payments Webinar from BlueSnap
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Set off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptxSet off and carry forward of losses and assessment of individuals.pptx
Set off and carry forward of losses and assessment of individuals.pptx
 
Auditing study material for b.com final year students
Auditing study material for b.com final year  studentsAuditing study material for b.com final year  students
Auditing study material for b.com final year students
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 
The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...The Influence of Marketing Strategy and Market Competition on Business Perfor...
The Influence of Marketing Strategy and Market Competition on Business Perfor...
 

Construction Update 7-6-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 6.30.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 6.28.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer installation (Line 1000) is ongoing along Concourse Level Area 2 – Underground Village West Parkway. plumbing rough-in for the Concourse Buildings is ongoing. Storm Line Installation (Line 600 and Sanitary Sewer Line E installation is ongoing on east side of France Family Dive is ongoing. Foundations: Area 3 Field Level – Isolated footing installation is Ongoing and is currently to Column Line 6. Area 4 Mezzanine Level – Excavation for D-Line footing Is ongoing and is currently to Column Line 40. Field Level Area 1 – Vapor barrier installation from column line 32-29 is placed Concrete Flatwork: in preparation for slab-on-grade placement. Area 1 – Mezzanine slab-on deck is complete, Main Concourse structural slab is complete, Suite Level slab on deck is complete, Press Level slab on deck is complete. Preparation for 1st pour of Field Level Area 1 slab-on-grade is ongoing. Area 1 – Precast concrete treads and riser installation is nearly complete between column lines 32-24. Building the Future
  • 2. Structural Steel Erection: Area 1 –Detailing and decking in sequence 1-3 is ongoing. Erection of Steel Sequence 2-1 has started. Area 1 – Roof deck installation for entire West Building is nearly complete. Underground MEP: Electrical Secondary Distribution is ongoing in Area 3. Area 1 –Canopy Trusses are being delivered and staged in the infield. MEP Rough-in: Area 1 – Shallow electrical and plumbing rough-in has started at Field Level in preparation for 1st slab-on-grade pour. Metal Stud Framing: Area 1 Suite Level – Metal stud framing for Suites has started. Projected Activities occurring next Week: Area 1 – Shot of the West Building from the Mass Excavation: southeast. Backfilling of on-grade seating areas will continue in Area 3. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Storm Line 1000 will continue. Installation of Sanitary Line E will continue. Deep Underground MEP: Deep Sanitary and Electrical Distribution installation in Area 3 will continue. Roof Level Area 1 – Roof decking is nearly Foundations: complete. Area 3 Field Level – Foundation installation will continue. Area 4 Mezzanine Level – Foundation Wall installation will continue. Building the Future
  • 3. Concrete Flatwork: Area 1 Field Level – Concrete placement for slab-on-grade will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 2-1 will continue. Delivery of Roof Trusses for sequence 1-7 will continue Area 2 – Shot looking south of Terrace Area throughout the week. taking shape. Structural Precast: Erection of the precast tubs in Area 1 will begin. Underground MEP: Deep Sanitary installation will continue in Area 3. Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 1 Field Level slab on grade will continue. Field Level Area 3 – Foundation installation is ongoing. Metal Stud Framing: Area 1 Suite Level – Metal stud framing for Suites will continue. Area 1 Press Level – Metal stud framing for Suites will begin. Building the Future
  • 4. Additional Photos: Field Level Area 1 – Shot of Player’s field Field Level Area 3 – Field wall footing entry. concrete placed at column line 4. Suite Level Area 1 – Metal stud framing for Area 1 – Subgrade preparation for on-grade suites has begun. seating risers has started. Suite Level Area 1 – Duct straps being installed in preparation for ductwork Roof Level Area 1 – Shot of steel framing for installation. Freight Elevator “High Hat”. Building the Future