AXIOS GROUP LTD
BRIDON ROPES
LOLER
AWARENESS
AXIOS GROUP LTD
BRIDON ROPES
 ACTS
 REGULATIONS
 CODES OF PRACTICES
 BRITISH STANDARDS
 GUIDANCE NOTES
 HEALTH AND SAFETY AT WORK ACT
 OTHER STANDARDS
AXIOS GROUP LTD
BRIDON ROPES
 The Provision and Use of Work Equipment Regulations 1998
(PUWER). Applies to all lifting equipment
 The Lifting Operations and Lifting Equipment Regulations 1998
(LOLER). Applies over and above PUWER in dealing with specific
risks/hazards.
 British Standard 7121 - Parts 1, 2 and 11 (Eleven) - (1989) (Applies to
crane operations)
 Health and Safety at Work Act 1974 (Amended 1988)
Offshore & Onshore Regulations:
AXIOS GROUP LTD
BRIDON ROPES
PROVISION AND USE
OF WORK EQUIPMENT
REGULATIONS
SI 1998/2306
PUWER
AXIOS GROUP LTD
BRIDON ROPES
Statutory Instruments No: SI 1998/2307
THE LIFTING OPERATIONS & LIFTING EQUIPMENT
REGULATIONS 1998 (LOLER)
Interpretation
In these Regulations, unless the context otherwise requires:
“The 1994 ACT” means the Health & Safety at Work etc. Act
1974.
Citation and Commencement
These Regulations may be cited as the Lifting Operations and Lifting
Equipment Regulations SI 1998/2307, - came into force on 5th
December 1998. All equipment used for lifting or lowering, including
second-hand, leased or new equipment MUST COMPLY with these
Regulations
AXIOS GROUP LTD
BRIDON ROPES
 “The 1992 Regulations” means the Supply of
Machinery (Safety) Regulations 1992.
Statutory Instruments - Interpretation
(continued)
 “EC Declaration of Conformity” means a
declaration which complies with Regulation 22
of the 1992 Regulations.
AXIOS GROUP LTD
BRIDON ROPES
“Accessory for Lifting”
means work equipment
for attaching loads to
machinery for lifting.
Statutory Instruments - Interpretation
(continued)
AXIOS GROUP LTD
BRIDON ROPES
LOLER
LIFTING OPERATIONS &
LIFTING EQUIPMENT
REGULATIONS
SI 1998/2307
AXIOS GROUP LTD
BRIDON ROPES
WHAT IS: AN APPROVED CODE OF PRACTICE (ACOP) ?
 ACOP material gives practical guidance on how to
comply with the law.
 If you follow the advice in an ACOP you will be doing
enough to ensure compliance with the law on the
matters that it covers.
 ACOP has special legal status. If you are prosecuted
for a breach of HS law, and it is proved that you did
not follow the relevant ACOP, you will need to show
that you have complied with the law in some other
way or a court will find you at fault.
AXIOS GROUP LTD
BRIDON ROPES
LOLER (continued)
Many operations offshore involve a number of contracting
companies, and these Regulations will no doubt result in
considerable debate in the future, and it is not possible to be
clear and concise at this point.
In any investigation following a serious incident, the HSE
will no doubt wish to consider which company, or companies
had primary involvement.
This already happened under the SI 1019 legislation
and is not a major change of direction
AXIOS GROUP LTD
BRIDON ROPES
WHAT IS: “ GUIDANCE” ?
 Guidance material describes practical means of complying
with the Regulations.
 It does not have special status in law, but is seen as best
practice.
 Following guidance is not compulsory and you are free to
take other action.
 However, if you follow the ‘guidance’ given by LOLER and
PUWER you will normally be doing enough to comply with
the law.
AXIOS GROUP LTD
BRIDON ROPES
LIFTING OPERATIONS AND LIFTING
EQUIPMENT REGULATIONS (LOLER)
LOLER places primary responsibility on the
employers.
The employer has a duty to ensure that lifting
equipment provided for use by his employees
complies with the Regulations
AXIOS GROUP LTD
BRIDON ROPES
LOLER (continued)
These regulations also include reference to Regulations 4, 8
& 9 of the Provision of Work Equipment Regulations
(PUWER) which consider the suitability of lifting equipment,
Information and Instructions, Reg 8 and Training, to the
people that use it, Reg 9.
Essentially, the employer must ensure that the equipment is
constructed so as to be suitable for the purpose intended, and
further, that the employer must carefully consider the
environment conditions and any additional risks posed by
the use of that equipment.
AXIOS GROUP LTD
BRIDON ROPES
WHEN THE CRANE TIPPED OVER THE HOOK BLOCK HIT AND KILLED A PEDESTRIAN
AXIOS GROUP LTD
BRIDON ROPES
WHEN THE CRANE TIPPED - A MAN WAS FATALLY TRAPPED BENEATH THE LOAD
AXIOS GROUP LTD
BRIDON ROPES
Every employer shall ensure that every lifting operation
involving lifting equipment is :
a) Properly planned by a competent person;
b) Appropriately supervised; and
c) Carried out in a safe manner
Lifting Operations - means an operation concerned with
the lifting or lowering of a load.
ORGANISATION & LIFTING OPERATIONS
AXIOS GROUP LTD
BRIDON ROPES
ORGANISATION & LIFTING OPERATIONS
• Was the lift planned ?
• Where written procedures for the lifting operation ?
• Did a representative of the crane hire Company agree to the
(clearly inadequate) site arrangement ?
• Was a qualified engineer present to advise the crane operator?
• Was the crane operator adequately trained on the crane ?
The unsatisfactory answers to these questions led to prosecution
The HSE asked the following :
AXIOS GROUP LTD
BRIDON ROPES
MEANS
OF
ACCESS
Areas which are further considered include :
LOLER (continued)
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
Further considered areas include:
SLIPS
TRIPS
FALLS
AXIOS GROUP LTD
BRIDON ROPES
Other areas considered include:
AXIOS GROUP LTD
BRIDON ROPES
EFFECTS
OF HIGH
WIND
And further areas considered include:
Although mentioned here, these factors are further
considered under Regulation 8 of LOLER
AXIOS GROUP LTD
BRIDON ROPES
Every employer shall ensure that every lifting operation
involving lifting equipment is :
a) Properly planned by a competent person;
b) Appropriately supervised; and
c) Carried out in a safe manner
Lifting Operations - means an operation concerned with
the lifting or lowering of a load.
ORGANISATION AND LIFTING OPERATIONS
AXIOS GROUP LTD
BRIDON ROPES
Operating / Control Procedures
The duty holder should ensure a safe system of work..
ROUTINE NON-ROUTINE
Written procedures should be provided for use of equipment in both types of
operation.
AXIOS GROUP LTD
BRIDON ROPES
Operating / Control Procedures
An example of a routine duty is the offloading/back loading
of a container from a supply vessels.
Examples of non-routine lifting operations include:-
1) Operations during the repair or modification of plant and
on the installation. See also Regulation 22 of the 1992
Regulations (shown later).
2) Work carried out on the lifting appliance itself.
AXIOS GROUP LTD
BRIDON ROPES
 Every employer shall take appropriate measures to ensure that
work equipment is so constructed, or adapted that, so far as is
reasonably practicable, maintenance operations which involve a
risk to health or safety can be carried out while the work
equipment is shut down.
 Maintenance operations can be carried out without exposing the
person carrying them out to a risk to his health or safety, or
appropriate measures can be taken for the protection of any
person carrying out maintenance operations which involve a risk
to his health or safety.
REGULATION 22 OF THE 1992 REGULATION
Maintenance Operations
AXIOS GROUP LTD
BRIDON ROPES
LIFTING
OPERATIONS
FLOW CHART
( handout )
AXIOS GROUP LTD
BRIDON ROPES
Written procedures should identify the controls provided and authorised
by the duty holder
These should include:
1) The planning of the lifting operation [ TRIC Card/Lifting
Operations Plan - handouts ].
2) The results of any risk assessment on the operations and
equipment.
3) The issue and authorisation of work permits as required.
[See : Task Risk Assessment No 50 - handout ]
Operating / Control Procedures
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
LIFTING PLANS - Definitions
Routine Lifts
 The vast majority of offshore lifts (includes platform
crane lifts).
 They are covered by competence, risk assessments
and procedures.
A Toolbox talk or a TRIC is normally sufficient BUT -
BEWARE - If conditions change you must re-assess
the HAZARD.
AXIOS GROUP LTD
BRIDON ROPES
LIFTING PLANS - Definitions
Non-routine:
Are lifts that require:
 A Lifting Plan
 A Permit to Work
 Special Controls
 Risk Assessment
AXIOS GROUP LTD
BRIDON ROPES
SIMPLE COMPLICATED COMPLEX
NON-ROUTINE
Varying degrees of control require Non-routine lifts
to be further sub-divided
Handouts (Organisation of Lifting Ops)
AXIOS GROUP LTD
BRIDON ROPES
LIFTING PLANS - Definitions
Non-routine SIMPLE
 An existing procedure, or a simple lifting plan drawn
up by the Competent Person. Risk assessed by
Toolbox Talk/TRIC.
 Lift carried out by Competent Person
 Vertical lifts using one piece of lifting equipment,
eg a winch, a chain block, a crane, etc.
AXIOS GROUP LTD
BRIDON ROPES
LIFTING PLANS - Definitions
Non-routine COMPLICATED
 Lifting plan drawn up by Supervisors/Competent
person. Risk assessment using Permit to Work.
 Work carried out by Competent Person (Rigger).
 Examples:
Awkward load - Work in Hazardous Area -
Special rig required - Need to use uncertified lifting
points.
AXIOS GROUP LTD
BRIDON ROPES
LIFTING PLANS - Definitions
Non-routine COMPLEX
 Lifting plan drawn up by Engineer/Supervisors but
could be specialised Lifting Engineer. Risk assessed
using Permit to Work or separate Risk Assessment.
 Work closely supervised, carried out by Competent
Person (Rigger), Abseilers, Lift Specialist.
 Examples: Engineering work packs using external
assistance (divers, a floating crane, abseilers) or a
BIG JOB.
AXIOS GROUP LTD
BRIDON ROPES
LIFT TYPE - ASSESSMENT MATRIX
TABLE 1
Lift
Load
Light Lift
Up to 1 Tonne
Moderate lift
between 1 tonne and
3 Tonne
Heavy lift between
3 Tonne and 12.5
Tonne
Exceptional lift in
excess of 12 Tonne
Certified Lift Point
(LP) Directly
overhead
Low Low Low Medium
Certified Lift Point
Unobstructed Cross
Haul
Low Low Medium High
Certified Lift Point
Obstructed Cross
Haul
Low Medium High High
Structural steel
directly overhead
unobstructed
Medium Medium High High
Structural steel
Cross Haul
unobstructed
Medium Medium High High
Structural steel
Cross Haul
Obstructed
Medium High High High
TABLE 2
Load balanced Low Low Medium Medium
Load Unbalanced
Low Medium High High
Awkward Load Low High High High
AXIOS GROUP LTD
BRIDON ROPES
‘Low’ is the only condition of the load/lift indicated by the
Matrix the lift can be:
(a) undertaken by a person who is adequately trained and
authorised by a third party, or
(b) A person who has sufficient experience to be acceptable to
the Controlling Authority.
(OPENG. MAINT, MME, Terminal Maint Eng, or SAEM, or
Stores and Transport Officer)
LOW
AXIOS GROUP LTD
BRIDON ROPES
RISK ASSESSMENT
Where ‘Medium’ is the predominant load/lift condition the
lift should be undertaken by a Qualified Rigger or
nominated Engineer.
If a Qualified Rigger or Engineer is not available a written
lifting operation method statement must be generated – with
technical appraisal.
MEDIUM
AXIOS GROUP LTD
BRIDON ROPES
RISK ASSESSMENT
Where ‘High’ is the predominant load/lift condition a
specific written lifting operation method statement
must be generated and supported by technical
appraisal and approval.
HIGH
AXIOS GROUP LTD
BRIDON ROPES
WHO IS A ‘COMPETENT PERSON’
Not much advice in LOLER
but………..
AXIOS GROUP LTD
BRIDON ROPES
Competency: Is the ability to perform activities within an
occupation or function to the standards
expected in employment.
Competent Person is generally considered to be one who
has sufficient training, experience, knowledge
and other qualities for the task in hand.
The Offshore Mechanical Handling Equipment Committee
(OHMEC) has a workgroup looking at “Enterprise of
Competence” for operator’s of lifting Equipment
WHO IS A ‘COMPETENT PERSON’ ?
AXIOS GROUP LTD
BRIDON ROPES
COMPETENCE REQUIREMENTS
 These may vary depending on the task,
For example: Hooking on a container - to
working out Load Dynamics.
 It is Important that individuals should be aware of
their competence limitations.
 If in doubt - ask your supervisor.
AXIOS GROUP LTD
BRIDON ROPES
COMPETENCE REQUIREMENTS
 Now requires formal training, for example:
OPITO / National Standards / NVQs - as well as
experience on the job.
 Experience (for example 15 years as a Rigger) is
now no longer enough by itself - everyone needs to
be working towards training qualifications.
 Maintaining competence - refresher training or
on-the-job assessment.
AXIOS GROUP LTD
BRIDON ROPES
Am I competent to
complete a Lifting Plan ?
Do I have the knowledge and experience ?
Have I received the necessary training ?
Have I successfully completed units of
Competence ?
AXIOS GROUP LTD
BRIDON ROPES
REMEMBER…..
When in doubt SAFETY takes priority.
STOP what you are doing and REASSESS
No job is so important that we cannot
afford the time to do it SAFELY
AXIOS GROUP LTD
BRIDON ROPES
4) The following checks are carried out:
4a All equipment is suitably examined prior to use
4b Pre-start checks provided by the equipment supplier
(See next slide) or the competent person.
4c Loose equipment has a valid Certificate of Conformity
4d All equipment is in a good state of repair before being
stored.
Operating / Control Procedures
(continued)
AXIOS GROUP LTD
BRIDON ROPES
All new equipment must
be accompanied by
Operating and
Maintenance Instructions
THESE MUST BE MADE
AVAILABLE TO THE END USER
AXIOS GROUP LTD
BRIDON ROPES
5) All personnel involved with mechanical handling operations, are
trained to levels of competence appropriate to their tasks and
responsibilities.
6) That no person works under a suspended load, or that any load
passes over personnel.
7) There is a system for the effective reporting and recording of
any incident arising from the operational use and/or, failure of
the lifting mechanical handling equipment.
Operating / Control Procedures
(continued)
AXIOS GROUP LTD
BRIDON ROPES
8) A clear and effective communications system is available and
under-stood by all personnel involved with the lifting
operation. A competent person is identified to co-ordinate and
control all aspects of the lifting operation.
9) A shift change over log should be in place which correctly
informs the incoming shift of states of the lifting operation
and/or the lifting appliance.
10) Personal protective equipment such as helmet, boots, clothing
etc, is issued appropriate to the operational task.
11) The work place is provided with adequate lighting and
effective unobstructed access ways and escape routes.
Operating / Control Procedures
(continued)
AXIOS GROUP LTD
BRIDON ROPES
Risk Assessment
• Routine lifting operations do not require a
Risk Assessment.
• A Risk Assessment should only be carried
out if hazards are identified with any lifting
operation.
• Ask yourself………...
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
 It is nothing more than a careful examination of
what, in your work, could cause harm to people.
 You weigh-up whether you have taken enough
precautions - or should you take more action to
prevent harm.
WHAT IS RISK ASSESSMENT ?
AXIOS GROUP LTD
BRIDON ROPES
The best risk assessments are made ‘at the right level’. Staff nearest to the problems
are the best placed to identify them.
“Nobody gets hurt sitting at a desk on the beach !”
Risk assessments should not be over complicated - Suitable and sufficient - not
perfection.
“Experience is a severe teacher:- It
tests first and gives lessons afterwards”
RISK ASSESSMENT
AXIOS GROUP LTD
BRIDON ROPES
 Understanding the objectives of the job.
 Understanding the risks and how they will be
controlled
 Everyone knowing their roles - and the roles of
others involved
 The work gets done correctly and SAFELY
GOOD RISK ASSESSMENT MEANS:
AXIOS GROUP LTD
BRIDON ROPES
QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN
ASSESSMENT
(1) Is there documentation (planned by a competent person)
for the lifting operation, or is it a routine job?
(2) Are personnel familiar with the work area and equipment
(obstructions hazards) and fully trained to carry out that
lifting operation?
(3) Is a permit required, if so is it valid ? Has any other work
activity in the same vicinity been identified? Is restricted
access needed, and are all isolations in place, if applicable?
AXIOS GROUP LTD
BRIDON ROPES
QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN
ASSESSMENT
• Pre-use inspections.
• Correct installation of equipment.
• Over the C of G?
(4) Is the lifting equipment
suitable for that operation
and is it the correct SWL?
AXIOS GROUP LTD
BRIDON ROPES
QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN
ASSESSMENT
(5) Is the weight of the load known, or does the weight
have to be calculated? ( Selection of lifting
equipment will depend upon the weight of the load and
environmental conditions )
(6) Has the route the load is going to travel been checked
for hazards - such as - personnel, unprotected
occupied offices or accommodation, vulnerable plant,
e.g. live gas lines, turbine exhausts or gas cooler
banks ?
AXIOS GROUP LTD
BRIDON ROPES
QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN
ASSESSMENT
(7) Has an area been prepared to land the load?
The load should not be landed in
any area other than those
designated for load bearing.
3-way link
AXIOS GROUP LTD
BRIDON ROPES
Hazard Assessment
(By base
dispatchers)
• Assess cargo transit requirements with
respect to method of conveyance.
• Check platform offloading capabilities with
respect to weight of cargo.
• Can platform offload safely with equipment
provided ?
AXIOS GROUP LTD
BRIDON ROPES
Risk assessment by
Vessel Master (at
base)
• Is the cargo suitably packed and secured for the
conditions that might be encountered ?
• Is the cargo suitably positioned on the deck with
respect to offloading ?
AXIOS GROUP LTD
BRIDON ROPES
Communication
(offshore)
Three-way job discussion (Risk Assessment) between:
Vessel Master - OIM - Crane Operator considering all
risks involved with proposed lift.
If any one of the three considers the lift a high risk, it
must not go ahead in its present form.
AXIOS GROUP LTD
BRIDON ROPES
Strength and Stability
A fairly self-evident requirement that
the lifting equipment must be identified
as adequate for the task intended and
be selected to provide an acceptable
factor of safety.
AXIOS GROUP LTD
BRIDON ROPES
 In addition to the equipment itself, the
suspension point e.g. padeye or
structural beam must also be considered
for suitability to the task.
 The lifting equipment must be regularly
inspected by a competent person.
Strength and Stability
AXIOS GROUP LTD
BRIDON ROPES
Strength and Stability
 The regulations also seek to differentiate between
padeyes which can be construed as part of the load
and therefore subject to PUWER and padeyes
which are permanent items on the platform and
subject to LOLER.
 It is not considered good use of time to argue the
difference as both need to be inspected, one
through PUWER on the basis of risk assessment
and one in accordance with Reg 9 of LOLER.
AXIOS GROUP LTD
BRIDON ROPES
THE SAFETY OF PERSONNEL IS THE
MOST VITAL FACTOR.
Strength and Stability
Uncertified Lifting Points must be assessed by a
Competent Person who will consider:
• Beam size, span fixings, existing loading.
• Weight/size of the object.
• Loads exerted during lift, especially lateral bending
capacity.
• Lifting equipment and accessories.
AXIOS GROUP LTD
BRIDON ROPES
Strength and Stability
Uncertified Lifting Points (continued)
CAUTION
Existing platform Instructions may not consider all
the factors involved.
 If in doubt refer to Structural Engineers who will carry
out the necessary calculations.
 In the first instance produce a sketch of requirements
and send it to the Engineering Department for
consideration.
AXIOS GROUP LTD
BRIDON ROPES
TYPICAL SKETCH
OF LIFT
REQUIREMENTS
AXIOS GROUP LTD
BRIDON ROPES
Strength and Stability
 The lifting equipment must have adequate stability
for the proposed use. This is mainly directed
towards onshore use with mobile cranes, however,
it may also apply offshore for any free standing
lifting arrangements.
 Cranes which are required to lift items out of the
water (e.g. Diving Vessels) must be suitably
derated to take account of the dynamic factors
involved in such operations.
AXIOS GROUP LTD
BRIDON ROPES
Strength and Stability
 Where the risk of overload exists, Rated Capacity
Indicators must be fitted.
Note This is the new term for safe load
indicators!
 Para (b) of the regulation refers to every part of
the load must be of adequate strength. This is
intended to include pallets which may be banded
to the load, and lids and doors which may be
attached to the load.
AXIOS GROUP LTD
BRIDON ROPES
POSITIONING AND INSTALLATION
Every employer shall ensure that lifting equipment is
positioned or installed in such a way as to reduce to as
low as is reasonably practicable the risk:
a) of the lifting equipment, or a load striking a
person, or
b) from a load, drifting, falling freely, or being
released unintentionally.
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
NEVER STAND UNDER A
LOAD !!
AXIOS GROUP LTD
BRIDON ROPES
LIFTING EQUIPMENT FOR LIFTING PERSONS
Every employer shall ensure that lifting equipment for lifting
persons:
a) Prevents, so far as is reasonably practicable, a person using it,
being crushed, trapped or struck or falling from the carrier.
b) Has suitable devices to prevent the risk of the carrier falling.
c) That a person trapped in any carrier is not exposed to danger
and can be freed.
AXIOS GROUP LTD
BRIDON ROPES
Lifting Equipment Used for Lifting Persons
(1) Work baskets should only be used
if there is no other way to access
the work site. The basket should
be approved for such operations,
and be suitably marked with the
maximum number of persons that
can be carried and the SWL.
Personnel Work Baskets
NOTE: The ‘Billy Pugh’ is no longer acceptable
for personnel transfer operations.
AXIOS GROUP LTD
BRIDON ROPES
Lifting Equipment Used for Lifting Persons
(2) Written procedures for all operations involving work
baskets should be produced. All personnel involved should
be competent and suitably trained. Safety harnesses
should be used, life vest/jacket for operations over the sea.
(3) Work baskets design should include, non-slip floors,
anchor points for safety harness and any tools or loose
equipment, and a back-up line which securely connects the
basket to the lifting appliance. The carrier should be
inspected by a competent person each time it is used.
(continued)
AXIOS GROUP LTD
BRIDON ROPES
THOROUGH EXAMINATION
WHAT IS A THOROUGH EXAMINATION ?
It is an examination carried out by a ‘Competent
Person’ looking carefully and critically - and where
necessary supplemented by other means such as
measurements and non-destructive testing…...
in order to detect damage or deterioration
AXIOS GROUP LTD
BRIDON ROPES
THOROUGH EXAMINATION
The extent of a Thorough Examination should be dependent on an assessment of the
risks - based on the type of lifting equipment - and other factors such as:
• Exposure to environmental conditions.
• Frequency of use
• How the equipment is used
• Effect of forces applied
• Material and construction of equipment.
AXIOS GROUP LTD
BRIDON ROPES
THOROUGH EXAMINATION
When is a Thorough Examination Conducted ?
(A) Before it is put into Service for the First time
(B) After installation or assembly where it’s safety
depends on installation or assembly conditions.
(C) Each time it undergoes exceptional circumstances
that are liable to jeopardise it’s safety.
(D) At suitable intervals as part of a written examination.
AXIOS GROUP LTD
BRIDON ROPES
When is a Thorough Examination Conducted ?
(E) Or in accordance with LOLER.
(i) Equipment for lifting persons and lifting
accessories -at least every 6 months.
(ii) Other lifting equipment - at least every
12 months.
THOROUGH EXAMINATION
AXIOS GROUP LTD
BRIDON ROPES
Is an In-service Inspection the same as
a Thorough Examination ?
THOROUGH EXAMINATION
NO !
In-service Inspections are a set of simple checkscarried out by authorised
persons to ensure that equipment is maintained such that it’s performance does
not deteriorate to the extent that it puts people at risk.
AXIOS GROUP LTD
BRIDON ROPES
Why is a Thorough Examination Conducted ?
THOROUGH EXAMINATION
1. Regulation 9 of LOLER requires it.
2. We must detect damage and deterioration
before it presents an unacceptable risk.
3. We must identify whether or not the equipment
can be:
- Operated
- Adjusted
- Maintained
AXIOS GROUP LTD
BRIDON ROPES
THOROUGH EXAMINATION
A person making a thorough examination for an employer shall:
a) Notify the employer forthwith of any defect in the
lifting equipment which in his opinion, is or could
become, a danger to persons
b) As soon as is practicable, make a report of the
thorough examination in writing, authenticated by
him, or on his behalf by signature, or equally secure
means and containing the information specified in
Schedule 1 of LOLER. (See handout examples)
AXIOS GROUP LTD
BRIDON ROPES
INFORMATION TO
BE CONTAINED IN
A REPORT OF A
THOROUGH
EXAMINATION
[See handout]
AXIOS GROUP LTD
BRIDON ROPES
INFORMATION TO
BE CONTAINED IN
A REPORT OF A
TEST AND
THOROUGH
EXAMINATION
[See handout]
AXIOS GROUP LTD
BRIDON ROPES
Example of a
Statement of
Conformity
AXIOS GROUP LTD
BRIDON ROPES
Example of a Certificate
of Proof Test and
Examination
Can be used as an
EC Declaration of
Incorporation
AXIOS GROUP LTD
BRIDON ROPES
DECLARATION of CONFORMITY (DOC)
Requirements of the CE marking and a Declaration of Conformity
Any complete lifting equipment which can be used in the form in
which it is supplied.
• Chain Block complete - CE mark and DOC.
• Chain block without chain - Declaration of Incorporation.
• Assemble chain to block - issues DOC and adds CE mark.
AXIOS GROUP LTD
BRIDON ROPES
LIFTING ACCESSORIES ?
The classic example is a shackle.
• If it is on the market as a lifting accessory - CE marked and have
a DOC.
• When supplied as part of lifting equipment, such as a lifting
beam, it is captive and cannot be used separately.
• Recommended that all shackles and eyebolts for lifting purposes
should be CE marked and have a DOC.
DECLARATION of CONFORMITY
AXIOS GROUP LTD
BRIDON ROPES
Who does the Declaration of Conformity go to ?
The regulations do not state what the responsible person does
with the declaration and there is no duty on him to pass it to
anyone. Its principle function is as a formal means of claiming
that the machinery complies with all the Essential Health and
Safety Requirements
DECLARATION of CONFORMITY
AXIOS GROUP LTD
BRIDON ROPES
REPORTS AND DEFECTS
 A Competent Persons’ report is a vital aid to the safe
management of lifting equipment.
 Where a competent person detects a defect which needs
to be made good within a timescale he must submit the
report promptly to allow action to be taken within the
required period.
 Normally the competent person should submit his report
within 28 days of the thorough examination.
AXIOS GROUP LTD
BRIDON ROPES
REPORTS AND DEFECTS
 A Competent Person who fails to report a
defect, simply because it was rectified on the
spot, is disguising a potentially dangerous
situation.
 Defects which are habitually not detected, or
rectified until the Competent Person’s
thorough examination report are an indicator
of Management System inadequacies.
AXIOS GROUP LTD
BRIDON ROPES
REPORTS AND DEFECTS
WHICH REPORTS SHOULD BE KEPT ?
 EC Declaration of Conformity
 Certification of Proof Load Test and Examination.
 Thorough Examination Reports
 Defect Reports
AXIOS GROUP LTD
BRIDON ROPES
REPORTS AND DEFECTS
HOW LONG SHOULD REPORTS BE KEPT ?
(1) Lifting Equipment - Keep until next report or for
2 years.
(2) Lifting accessories - 2 years
Reports may be kept for longer periods if the information
they contain assists in identifying repeated defects, wear
trends, etc.
Periodic review of this information should be part of the
Management System for controlling lifting equipment.
AXIOS GROUP LTD
BRIDON ROPES
REPORTS AND DEFECTS
WHERE SHOULD REPORTS BE KEPT ?
 Onboard the installation - or,
 At some other location such that the information
can be readily accessed when required.
 Held at a common location
AXIOS GROUP LTD
BRIDON ROPES
• The regulations use several terms including maximum
working load Working Load Limit (WLL) and nominal
load.
• In the UK, for the foreseeable future, the user will still be
required to state a Safe Working Load (SWL). (Usually it
is the same as the WLL. )
• The paperwork can use both terms.
LOAD CAPACITY MARKINGS
AXIOS GROUP LTD
BRIDON ROPES
OFFSHORE CONTAINERS
AXIOS GROUP LTD
BRIDON ROPES
CONTAINER DATA PLATE
The data plate shall be headed:
OFFSHORE CONTAINER DATA PLATE - EN 12079
The plate shall contain the following information:
Fabricator’s serial number
Maximum gross mass in Kilograms, at the design sling angle
Tare mass in Kilograms
Payload in kilograms and intermediate deck payload (if applicable)
Certificate number
Design temperature
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
AXIOS GROUP LTD
BRIDON ROPES
CONTENTS OF THE STATEMENT OF CONFORMITY
All containers to be used offshore shall be issued with a certificate
of conformity containing the following information:
– Container fabrication No.
– The certificate No.
– Description of the container including:
External dimensions  Number of lifting points  Name of
fabricator  Month/year of fabrication  Maximum gross mass in
kgs  Tare mass in kgs  Payload in kgs  Reference to the as-built
dossier  Total gross mass in kgs applicable to the ‘all points lifting test’
- and the actual method of test
– Angle of lifting set legs (from vertical)
– shackle bolt diameter
AXIOS GROUP LTD
BRIDON ROPES
 Conformity to other requirements and/or codes
 A statement that the container described has been
designed, fabricated and tested in accordance with
EN 12079
 Remarks
 Signature on behalf of the certifying body
CONTENTS OF A CONTAINER STATEMENT OF
CONFORMITY
AXIOS GROUP LTD
BRIDON ROPES
Adequate arrangements shall be made for the safe
transportation of a damaged container to the location
agreed with by the owner.
EUROPEAN STANDARD EN12079
(Containers) - (continued)
THE CONTAINER SHALL NOT BE USED AGAIN UNTIL IT
IS REPAIRED AND INSPECTED BY AN INSPECTION
BODY.
AXIOS GROUP LTD
BRIDON ROPES
CEN TC 280 Standard for Offshore Containers
Procedure No. 12 - Pre-trip Inspections: (continued)
The responsible person shall confirm , by signature and date
(eg on the shipping manifest) that inspection has been
carried out to his satisfaction.
Records of inspections shall be retained by
the user for a period of at least 60 days
AXIOS GROUP LTD
BRIDON ROPES
Contract Lift
The term “contract lift” refers to the situation where an
organisation enters into a contract with a third party, who
will undertake the lifting operation on their behalf, i.e. the
third party provides the lifting equipment (such as a
crane) and the operator. In these circumstances, the crane
owner has the duty to ensure that the crane is properly
maintained, inspected and safe to use and that lifting
operation is carried out safely.
AXIOS GROUP LTD
BRIDON ROPES
Crane on Hire BS 7121 Part
1
The user then has the duty to manage the lifting operation in
a safe manner, unless other arrangements are made, e.g.
under the terms of a contract.
When hiring a crane, the crane hire company should
produce physical evidence of the last inspection report for
the crane, and lifting equipment. After installation, the
user should ensure that the crane is inspected by a
competent person before being put into use. (Normally this
will be done by the hire company, particularly if they erect
the crane).
AXIOS GROUP LTD
BRIDON ROPES
END OF PRESENTATION

LOLER awareness presentation for beginners.ppt

  • 1.
    AXIOS GROUP LTD BRIDONROPES LOLER AWARENESS
  • 2.
    AXIOS GROUP LTD BRIDONROPES  ACTS  REGULATIONS  CODES OF PRACTICES  BRITISH STANDARDS  GUIDANCE NOTES  HEALTH AND SAFETY AT WORK ACT  OTHER STANDARDS
  • 3.
    AXIOS GROUP LTD BRIDONROPES  The Provision and Use of Work Equipment Regulations 1998 (PUWER). Applies to all lifting equipment  The Lifting Operations and Lifting Equipment Regulations 1998 (LOLER). Applies over and above PUWER in dealing with specific risks/hazards.  British Standard 7121 - Parts 1, 2 and 11 (Eleven) - (1989) (Applies to crane operations)  Health and Safety at Work Act 1974 (Amended 1988) Offshore & Onshore Regulations:
  • 4.
    AXIOS GROUP LTD BRIDONROPES PROVISION AND USE OF WORK EQUIPMENT REGULATIONS SI 1998/2306 PUWER
  • 5.
    AXIOS GROUP LTD BRIDONROPES Statutory Instruments No: SI 1998/2307 THE LIFTING OPERATIONS & LIFTING EQUIPMENT REGULATIONS 1998 (LOLER) Interpretation In these Regulations, unless the context otherwise requires: “The 1994 ACT” means the Health & Safety at Work etc. Act 1974. Citation and Commencement These Regulations may be cited as the Lifting Operations and Lifting Equipment Regulations SI 1998/2307, - came into force on 5th December 1998. All equipment used for lifting or lowering, including second-hand, leased or new equipment MUST COMPLY with these Regulations
  • 6.
    AXIOS GROUP LTD BRIDONROPES  “The 1992 Regulations” means the Supply of Machinery (Safety) Regulations 1992. Statutory Instruments - Interpretation (continued)  “EC Declaration of Conformity” means a declaration which complies with Regulation 22 of the 1992 Regulations.
  • 7.
    AXIOS GROUP LTD BRIDONROPES “Accessory for Lifting” means work equipment for attaching loads to machinery for lifting. Statutory Instruments - Interpretation (continued)
  • 8.
    AXIOS GROUP LTD BRIDONROPES LOLER LIFTING OPERATIONS & LIFTING EQUIPMENT REGULATIONS SI 1998/2307
  • 9.
    AXIOS GROUP LTD BRIDONROPES WHAT IS: AN APPROVED CODE OF PRACTICE (ACOP) ?  ACOP material gives practical guidance on how to comply with the law.  If you follow the advice in an ACOP you will be doing enough to ensure compliance with the law on the matters that it covers.  ACOP has special legal status. If you are prosecuted for a breach of HS law, and it is proved that you did not follow the relevant ACOP, you will need to show that you have complied with the law in some other way or a court will find you at fault.
  • 10.
    AXIOS GROUP LTD BRIDONROPES LOLER (continued) Many operations offshore involve a number of contracting companies, and these Regulations will no doubt result in considerable debate in the future, and it is not possible to be clear and concise at this point. In any investigation following a serious incident, the HSE will no doubt wish to consider which company, or companies had primary involvement. This already happened under the SI 1019 legislation and is not a major change of direction
  • 11.
    AXIOS GROUP LTD BRIDONROPES WHAT IS: “ GUIDANCE” ?  Guidance material describes practical means of complying with the Regulations.  It does not have special status in law, but is seen as best practice.  Following guidance is not compulsory and you are free to take other action.  However, if you follow the ‘guidance’ given by LOLER and PUWER you will normally be doing enough to comply with the law.
  • 12.
    AXIOS GROUP LTD BRIDONROPES LIFTING OPERATIONS AND LIFTING EQUIPMENT REGULATIONS (LOLER) LOLER places primary responsibility on the employers. The employer has a duty to ensure that lifting equipment provided for use by his employees complies with the Regulations
  • 13.
    AXIOS GROUP LTD BRIDONROPES LOLER (continued) These regulations also include reference to Regulations 4, 8 & 9 of the Provision of Work Equipment Regulations (PUWER) which consider the suitability of lifting equipment, Information and Instructions, Reg 8 and Training, to the people that use it, Reg 9. Essentially, the employer must ensure that the equipment is constructed so as to be suitable for the purpose intended, and further, that the employer must carefully consider the environment conditions and any additional risks posed by the use of that equipment.
  • 14.
    AXIOS GROUP LTD BRIDONROPES WHEN THE CRANE TIPPED OVER THE HOOK BLOCK HIT AND KILLED A PEDESTRIAN
  • 15.
    AXIOS GROUP LTD BRIDONROPES WHEN THE CRANE TIPPED - A MAN WAS FATALLY TRAPPED BENEATH THE LOAD
  • 16.
    AXIOS GROUP LTD BRIDONROPES Every employer shall ensure that every lifting operation involving lifting equipment is : a) Properly planned by a competent person; b) Appropriately supervised; and c) Carried out in a safe manner Lifting Operations - means an operation concerned with the lifting or lowering of a load. ORGANISATION & LIFTING OPERATIONS
  • 17.
    AXIOS GROUP LTD BRIDONROPES ORGANISATION & LIFTING OPERATIONS • Was the lift planned ? • Where written procedures for the lifting operation ? • Did a representative of the crane hire Company agree to the (clearly inadequate) site arrangement ? • Was a qualified engineer present to advise the crane operator? • Was the crane operator adequately trained on the crane ? The unsatisfactory answers to these questions led to prosecution The HSE asked the following :
  • 18.
    AXIOS GROUP LTD BRIDONROPES MEANS OF ACCESS Areas which are further considered include : LOLER (continued)
  • 19.
  • 20.
    AXIOS GROUP LTD BRIDONROPES Further considered areas include: SLIPS TRIPS FALLS
  • 21.
    AXIOS GROUP LTD BRIDONROPES Other areas considered include:
  • 22.
    AXIOS GROUP LTD BRIDONROPES EFFECTS OF HIGH WIND And further areas considered include: Although mentioned here, these factors are further considered under Regulation 8 of LOLER
  • 23.
    AXIOS GROUP LTD BRIDONROPES Every employer shall ensure that every lifting operation involving lifting equipment is : a) Properly planned by a competent person; b) Appropriately supervised; and c) Carried out in a safe manner Lifting Operations - means an operation concerned with the lifting or lowering of a load. ORGANISATION AND LIFTING OPERATIONS
  • 24.
    AXIOS GROUP LTD BRIDONROPES Operating / Control Procedures The duty holder should ensure a safe system of work.. ROUTINE NON-ROUTINE Written procedures should be provided for use of equipment in both types of operation.
  • 25.
    AXIOS GROUP LTD BRIDONROPES Operating / Control Procedures An example of a routine duty is the offloading/back loading of a container from a supply vessels. Examples of non-routine lifting operations include:- 1) Operations during the repair or modification of plant and on the installation. See also Regulation 22 of the 1992 Regulations (shown later). 2) Work carried out on the lifting appliance itself.
  • 26.
    AXIOS GROUP LTD BRIDONROPES  Every employer shall take appropriate measures to ensure that work equipment is so constructed, or adapted that, so far as is reasonably practicable, maintenance operations which involve a risk to health or safety can be carried out while the work equipment is shut down.  Maintenance operations can be carried out without exposing the person carrying them out to a risk to his health or safety, or appropriate measures can be taken for the protection of any person carrying out maintenance operations which involve a risk to his health or safety. REGULATION 22 OF THE 1992 REGULATION Maintenance Operations
  • 27.
    AXIOS GROUP LTD BRIDONROPES LIFTING OPERATIONS FLOW CHART ( handout )
  • 28.
    AXIOS GROUP LTD BRIDONROPES Written procedures should identify the controls provided and authorised by the duty holder These should include: 1) The planning of the lifting operation [ TRIC Card/Lifting Operations Plan - handouts ]. 2) The results of any risk assessment on the operations and equipment. 3) The issue and authorisation of work permits as required. [See : Task Risk Assessment No 50 - handout ] Operating / Control Procedures
  • 29.
  • 30.
    AXIOS GROUP LTD BRIDONROPES LIFTING PLANS - Definitions Routine Lifts  The vast majority of offshore lifts (includes platform crane lifts).  They are covered by competence, risk assessments and procedures. A Toolbox talk or a TRIC is normally sufficient BUT - BEWARE - If conditions change you must re-assess the HAZARD.
  • 31.
    AXIOS GROUP LTD BRIDONROPES LIFTING PLANS - Definitions Non-routine: Are lifts that require:  A Lifting Plan  A Permit to Work  Special Controls  Risk Assessment
  • 32.
    AXIOS GROUP LTD BRIDONROPES SIMPLE COMPLICATED COMPLEX NON-ROUTINE Varying degrees of control require Non-routine lifts to be further sub-divided Handouts (Organisation of Lifting Ops)
  • 33.
    AXIOS GROUP LTD BRIDONROPES LIFTING PLANS - Definitions Non-routine SIMPLE  An existing procedure, or a simple lifting plan drawn up by the Competent Person. Risk assessed by Toolbox Talk/TRIC.  Lift carried out by Competent Person  Vertical lifts using one piece of lifting equipment, eg a winch, a chain block, a crane, etc.
  • 34.
    AXIOS GROUP LTD BRIDONROPES LIFTING PLANS - Definitions Non-routine COMPLICATED  Lifting plan drawn up by Supervisors/Competent person. Risk assessment using Permit to Work.  Work carried out by Competent Person (Rigger).  Examples: Awkward load - Work in Hazardous Area - Special rig required - Need to use uncertified lifting points.
  • 35.
    AXIOS GROUP LTD BRIDONROPES LIFTING PLANS - Definitions Non-routine COMPLEX  Lifting plan drawn up by Engineer/Supervisors but could be specialised Lifting Engineer. Risk assessed using Permit to Work or separate Risk Assessment.  Work closely supervised, carried out by Competent Person (Rigger), Abseilers, Lift Specialist.  Examples: Engineering work packs using external assistance (divers, a floating crane, abseilers) or a BIG JOB.
  • 36.
    AXIOS GROUP LTD BRIDONROPES LIFT TYPE - ASSESSMENT MATRIX TABLE 1 Lift Load Light Lift Up to 1 Tonne Moderate lift between 1 tonne and 3 Tonne Heavy lift between 3 Tonne and 12.5 Tonne Exceptional lift in excess of 12 Tonne Certified Lift Point (LP) Directly overhead Low Low Low Medium Certified Lift Point Unobstructed Cross Haul Low Low Medium High Certified Lift Point Obstructed Cross Haul Low Medium High High Structural steel directly overhead unobstructed Medium Medium High High Structural steel Cross Haul unobstructed Medium Medium High High Structural steel Cross Haul Obstructed Medium High High High TABLE 2 Load balanced Low Low Medium Medium Load Unbalanced Low Medium High High Awkward Load Low High High High
  • 37.
    AXIOS GROUP LTD BRIDONROPES ‘Low’ is the only condition of the load/lift indicated by the Matrix the lift can be: (a) undertaken by a person who is adequately trained and authorised by a third party, or (b) A person who has sufficient experience to be acceptable to the Controlling Authority. (OPENG. MAINT, MME, Terminal Maint Eng, or SAEM, or Stores and Transport Officer) LOW
  • 38.
    AXIOS GROUP LTD BRIDONROPES RISK ASSESSMENT Where ‘Medium’ is the predominant load/lift condition the lift should be undertaken by a Qualified Rigger or nominated Engineer. If a Qualified Rigger or Engineer is not available a written lifting operation method statement must be generated – with technical appraisal. MEDIUM
  • 39.
    AXIOS GROUP LTD BRIDONROPES RISK ASSESSMENT Where ‘High’ is the predominant load/lift condition a specific written lifting operation method statement must be generated and supported by technical appraisal and approval. HIGH
  • 40.
    AXIOS GROUP LTD BRIDONROPES WHO IS A ‘COMPETENT PERSON’ Not much advice in LOLER but………..
  • 41.
    AXIOS GROUP LTD BRIDONROPES Competency: Is the ability to perform activities within an occupation or function to the standards expected in employment. Competent Person is generally considered to be one who has sufficient training, experience, knowledge and other qualities for the task in hand. The Offshore Mechanical Handling Equipment Committee (OHMEC) has a workgroup looking at “Enterprise of Competence” for operator’s of lifting Equipment WHO IS A ‘COMPETENT PERSON’ ?
  • 42.
    AXIOS GROUP LTD BRIDONROPES COMPETENCE REQUIREMENTS  These may vary depending on the task, For example: Hooking on a container - to working out Load Dynamics.  It is Important that individuals should be aware of their competence limitations.  If in doubt - ask your supervisor.
  • 43.
    AXIOS GROUP LTD BRIDONROPES COMPETENCE REQUIREMENTS  Now requires formal training, for example: OPITO / National Standards / NVQs - as well as experience on the job.  Experience (for example 15 years as a Rigger) is now no longer enough by itself - everyone needs to be working towards training qualifications.  Maintaining competence - refresher training or on-the-job assessment.
  • 44.
    AXIOS GROUP LTD BRIDONROPES Am I competent to complete a Lifting Plan ? Do I have the knowledge and experience ? Have I received the necessary training ? Have I successfully completed units of Competence ?
  • 45.
    AXIOS GROUP LTD BRIDONROPES REMEMBER….. When in doubt SAFETY takes priority. STOP what you are doing and REASSESS No job is so important that we cannot afford the time to do it SAFELY
  • 46.
    AXIOS GROUP LTD BRIDONROPES 4) The following checks are carried out: 4a All equipment is suitably examined prior to use 4b Pre-start checks provided by the equipment supplier (See next slide) or the competent person. 4c Loose equipment has a valid Certificate of Conformity 4d All equipment is in a good state of repair before being stored. Operating / Control Procedures (continued)
  • 47.
    AXIOS GROUP LTD BRIDONROPES All new equipment must be accompanied by Operating and Maintenance Instructions THESE MUST BE MADE AVAILABLE TO THE END USER
  • 48.
    AXIOS GROUP LTD BRIDONROPES 5) All personnel involved with mechanical handling operations, are trained to levels of competence appropriate to their tasks and responsibilities. 6) That no person works under a suspended load, or that any load passes over personnel. 7) There is a system for the effective reporting and recording of any incident arising from the operational use and/or, failure of the lifting mechanical handling equipment. Operating / Control Procedures (continued)
  • 49.
    AXIOS GROUP LTD BRIDONROPES 8) A clear and effective communications system is available and under-stood by all personnel involved with the lifting operation. A competent person is identified to co-ordinate and control all aspects of the lifting operation. 9) A shift change over log should be in place which correctly informs the incoming shift of states of the lifting operation and/or the lifting appliance. 10) Personal protective equipment such as helmet, boots, clothing etc, is issued appropriate to the operational task. 11) The work place is provided with adequate lighting and effective unobstructed access ways and escape routes. Operating / Control Procedures (continued)
  • 50.
    AXIOS GROUP LTD BRIDONROPES Risk Assessment • Routine lifting operations do not require a Risk Assessment. • A Risk Assessment should only be carried out if hazards are identified with any lifting operation. • Ask yourself………...
  • 51.
  • 52.
    AXIOS GROUP LTD BRIDONROPES  It is nothing more than a careful examination of what, in your work, could cause harm to people.  You weigh-up whether you have taken enough precautions - or should you take more action to prevent harm. WHAT IS RISK ASSESSMENT ?
  • 53.
    AXIOS GROUP LTD BRIDONROPES The best risk assessments are made ‘at the right level’. Staff nearest to the problems are the best placed to identify them. “Nobody gets hurt sitting at a desk on the beach !” Risk assessments should not be over complicated - Suitable and sufficient - not perfection. “Experience is a severe teacher:- It tests first and gives lessons afterwards” RISK ASSESSMENT
  • 54.
    AXIOS GROUP LTD BRIDONROPES  Understanding the objectives of the job.  Understanding the risks and how they will be controlled  Everyone knowing their roles - and the roles of others involved  The work gets done correctly and SAFELY GOOD RISK ASSESSMENT MEANS:
  • 55.
    AXIOS GROUP LTD BRIDONROPES QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN ASSESSMENT (1) Is there documentation (planned by a competent person) for the lifting operation, or is it a routine job? (2) Are personnel familiar with the work area and equipment (obstructions hazards) and fully trained to carry out that lifting operation? (3) Is a permit required, if so is it valid ? Has any other work activity in the same vicinity been identified? Is restricted access needed, and are all isolations in place, if applicable?
  • 56.
    AXIOS GROUP LTD BRIDONROPES QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN ASSESSMENT • Pre-use inspections. • Correct installation of equipment. • Over the C of G? (4) Is the lifting equipment suitable for that operation and is it the correct SWL?
  • 57.
    AXIOS GROUP LTD BRIDONROPES QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN ASSESSMENT (5) Is the weight of the load known, or does the weight have to be calculated? ( Selection of lifting equipment will depend upon the weight of the load and environmental conditions ) (6) Has the route the load is going to travel been checked for hazards - such as - personnel, unprotected occupied offices or accommodation, vulnerable plant, e.g. live gas lines, turbine exhausts or gas cooler banks ?
  • 58.
    AXIOS GROUP LTD BRIDONROPES QUESTIONS THAT SHOULD BE ASKED WHEN CARRYING OUT AN ASSESSMENT (7) Has an area been prepared to land the load? The load should not be landed in any area other than those designated for load bearing. 3-way link
  • 59.
    AXIOS GROUP LTD BRIDONROPES Hazard Assessment (By base dispatchers) • Assess cargo transit requirements with respect to method of conveyance. • Check platform offloading capabilities with respect to weight of cargo. • Can platform offload safely with equipment provided ?
  • 60.
    AXIOS GROUP LTD BRIDONROPES Risk assessment by Vessel Master (at base) • Is the cargo suitably packed and secured for the conditions that might be encountered ? • Is the cargo suitably positioned on the deck with respect to offloading ?
  • 61.
    AXIOS GROUP LTD BRIDONROPES Communication (offshore) Three-way job discussion (Risk Assessment) between: Vessel Master - OIM - Crane Operator considering all risks involved with proposed lift. If any one of the three considers the lift a high risk, it must not go ahead in its present form.
  • 62.
    AXIOS GROUP LTD BRIDONROPES Strength and Stability A fairly self-evident requirement that the lifting equipment must be identified as adequate for the task intended and be selected to provide an acceptable factor of safety.
  • 63.
    AXIOS GROUP LTD BRIDONROPES  In addition to the equipment itself, the suspension point e.g. padeye or structural beam must also be considered for suitability to the task.  The lifting equipment must be regularly inspected by a competent person. Strength and Stability
  • 64.
    AXIOS GROUP LTD BRIDONROPES Strength and Stability  The regulations also seek to differentiate between padeyes which can be construed as part of the load and therefore subject to PUWER and padeyes which are permanent items on the platform and subject to LOLER.  It is not considered good use of time to argue the difference as both need to be inspected, one through PUWER on the basis of risk assessment and one in accordance with Reg 9 of LOLER.
  • 65.
    AXIOS GROUP LTD BRIDONROPES THE SAFETY OF PERSONNEL IS THE MOST VITAL FACTOR. Strength and Stability Uncertified Lifting Points must be assessed by a Competent Person who will consider: • Beam size, span fixings, existing loading. • Weight/size of the object. • Loads exerted during lift, especially lateral bending capacity. • Lifting equipment and accessories.
  • 66.
    AXIOS GROUP LTD BRIDONROPES Strength and Stability Uncertified Lifting Points (continued) CAUTION Existing platform Instructions may not consider all the factors involved.  If in doubt refer to Structural Engineers who will carry out the necessary calculations.  In the first instance produce a sketch of requirements and send it to the Engineering Department for consideration.
  • 67.
    AXIOS GROUP LTD BRIDONROPES TYPICAL SKETCH OF LIFT REQUIREMENTS
  • 68.
    AXIOS GROUP LTD BRIDONROPES Strength and Stability  The lifting equipment must have adequate stability for the proposed use. This is mainly directed towards onshore use with mobile cranes, however, it may also apply offshore for any free standing lifting arrangements.  Cranes which are required to lift items out of the water (e.g. Diving Vessels) must be suitably derated to take account of the dynamic factors involved in such operations.
  • 69.
    AXIOS GROUP LTD BRIDONROPES Strength and Stability  Where the risk of overload exists, Rated Capacity Indicators must be fitted. Note This is the new term for safe load indicators!  Para (b) of the regulation refers to every part of the load must be of adequate strength. This is intended to include pallets which may be banded to the load, and lids and doors which may be attached to the load.
  • 70.
    AXIOS GROUP LTD BRIDONROPES POSITIONING AND INSTALLATION Every employer shall ensure that lifting equipment is positioned or installed in such a way as to reduce to as low as is reasonably practicable the risk: a) of the lifting equipment, or a load striking a person, or b) from a load, drifting, falling freely, or being released unintentionally.
  • 71.
  • 72.
  • 73.
  • 74.
    AXIOS GROUP LTD BRIDONROPES NEVER STAND UNDER A LOAD !!
  • 75.
    AXIOS GROUP LTD BRIDONROPES LIFTING EQUIPMENT FOR LIFTING PERSONS Every employer shall ensure that lifting equipment for lifting persons: a) Prevents, so far as is reasonably practicable, a person using it, being crushed, trapped or struck or falling from the carrier. b) Has suitable devices to prevent the risk of the carrier falling. c) That a person trapped in any carrier is not exposed to danger and can be freed.
  • 76.
    AXIOS GROUP LTD BRIDONROPES Lifting Equipment Used for Lifting Persons (1) Work baskets should only be used if there is no other way to access the work site. The basket should be approved for such operations, and be suitably marked with the maximum number of persons that can be carried and the SWL. Personnel Work Baskets NOTE: The ‘Billy Pugh’ is no longer acceptable for personnel transfer operations.
  • 77.
    AXIOS GROUP LTD BRIDONROPES Lifting Equipment Used for Lifting Persons (2) Written procedures for all operations involving work baskets should be produced. All personnel involved should be competent and suitably trained. Safety harnesses should be used, life vest/jacket for operations over the sea. (3) Work baskets design should include, non-slip floors, anchor points for safety harness and any tools or loose equipment, and a back-up line which securely connects the basket to the lifting appliance. The carrier should be inspected by a competent person each time it is used. (continued)
  • 78.
    AXIOS GROUP LTD BRIDONROPES THOROUGH EXAMINATION WHAT IS A THOROUGH EXAMINATION ? It is an examination carried out by a ‘Competent Person’ looking carefully and critically - and where necessary supplemented by other means such as measurements and non-destructive testing…... in order to detect damage or deterioration
  • 79.
    AXIOS GROUP LTD BRIDONROPES THOROUGH EXAMINATION The extent of a Thorough Examination should be dependent on an assessment of the risks - based on the type of lifting equipment - and other factors such as: • Exposure to environmental conditions. • Frequency of use • How the equipment is used • Effect of forces applied • Material and construction of equipment.
  • 80.
    AXIOS GROUP LTD BRIDONROPES THOROUGH EXAMINATION When is a Thorough Examination Conducted ? (A) Before it is put into Service for the First time (B) After installation or assembly where it’s safety depends on installation or assembly conditions. (C) Each time it undergoes exceptional circumstances that are liable to jeopardise it’s safety. (D) At suitable intervals as part of a written examination.
  • 81.
    AXIOS GROUP LTD BRIDONROPES When is a Thorough Examination Conducted ? (E) Or in accordance with LOLER. (i) Equipment for lifting persons and lifting accessories -at least every 6 months. (ii) Other lifting equipment - at least every 12 months. THOROUGH EXAMINATION
  • 82.
    AXIOS GROUP LTD BRIDONROPES Is an In-service Inspection the same as a Thorough Examination ? THOROUGH EXAMINATION NO ! In-service Inspections are a set of simple checkscarried out by authorised persons to ensure that equipment is maintained such that it’s performance does not deteriorate to the extent that it puts people at risk.
  • 83.
    AXIOS GROUP LTD BRIDONROPES Why is a Thorough Examination Conducted ? THOROUGH EXAMINATION 1. Regulation 9 of LOLER requires it. 2. We must detect damage and deterioration before it presents an unacceptable risk. 3. We must identify whether or not the equipment can be: - Operated - Adjusted - Maintained
  • 84.
    AXIOS GROUP LTD BRIDONROPES THOROUGH EXAMINATION A person making a thorough examination for an employer shall: a) Notify the employer forthwith of any defect in the lifting equipment which in his opinion, is or could become, a danger to persons b) As soon as is practicable, make a report of the thorough examination in writing, authenticated by him, or on his behalf by signature, or equally secure means and containing the information specified in Schedule 1 of LOLER. (See handout examples)
  • 85.
    AXIOS GROUP LTD BRIDONROPES INFORMATION TO BE CONTAINED IN A REPORT OF A THOROUGH EXAMINATION [See handout]
  • 86.
    AXIOS GROUP LTD BRIDONROPES INFORMATION TO BE CONTAINED IN A REPORT OF A TEST AND THOROUGH EXAMINATION [See handout]
  • 87.
    AXIOS GROUP LTD BRIDONROPES Example of a Statement of Conformity
  • 88.
    AXIOS GROUP LTD BRIDONROPES Example of a Certificate of Proof Test and Examination Can be used as an EC Declaration of Incorporation
  • 89.
    AXIOS GROUP LTD BRIDONROPES DECLARATION of CONFORMITY (DOC) Requirements of the CE marking and a Declaration of Conformity Any complete lifting equipment which can be used in the form in which it is supplied. • Chain Block complete - CE mark and DOC. • Chain block without chain - Declaration of Incorporation. • Assemble chain to block - issues DOC and adds CE mark.
  • 90.
    AXIOS GROUP LTD BRIDONROPES LIFTING ACCESSORIES ? The classic example is a shackle. • If it is on the market as a lifting accessory - CE marked and have a DOC. • When supplied as part of lifting equipment, such as a lifting beam, it is captive and cannot be used separately. • Recommended that all shackles and eyebolts for lifting purposes should be CE marked and have a DOC. DECLARATION of CONFORMITY
  • 91.
    AXIOS GROUP LTD BRIDONROPES Who does the Declaration of Conformity go to ? The regulations do not state what the responsible person does with the declaration and there is no duty on him to pass it to anyone. Its principle function is as a formal means of claiming that the machinery complies with all the Essential Health and Safety Requirements DECLARATION of CONFORMITY
  • 92.
    AXIOS GROUP LTD BRIDONROPES REPORTS AND DEFECTS  A Competent Persons’ report is a vital aid to the safe management of lifting equipment.  Where a competent person detects a defect which needs to be made good within a timescale he must submit the report promptly to allow action to be taken within the required period.  Normally the competent person should submit his report within 28 days of the thorough examination.
  • 93.
    AXIOS GROUP LTD BRIDONROPES REPORTS AND DEFECTS  A Competent Person who fails to report a defect, simply because it was rectified on the spot, is disguising a potentially dangerous situation.  Defects which are habitually not detected, or rectified until the Competent Person’s thorough examination report are an indicator of Management System inadequacies.
  • 94.
    AXIOS GROUP LTD BRIDONROPES REPORTS AND DEFECTS WHICH REPORTS SHOULD BE KEPT ?  EC Declaration of Conformity  Certification of Proof Load Test and Examination.  Thorough Examination Reports  Defect Reports
  • 95.
    AXIOS GROUP LTD BRIDONROPES REPORTS AND DEFECTS HOW LONG SHOULD REPORTS BE KEPT ? (1) Lifting Equipment - Keep until next report or for 2 years. (2) Lifting accessories - 2 years Reports may be kept for longer periods if the information they contain assists in identifying repeated defects, wear trends, etc. Periodic review of this information should be part of the Management System for controlling lifting equipment.
  • 96.
    AXIOS GROUP LTD BRIDONROPES REPORTS AND DEFECTS WHERE SHOULD REPORTS BE KEPT ?  Onboard the installation - or,  At some other location such that the information can be readily accessed when required.  Held at a common location
  • 97.
    AXIOS GROUP LTD BRIDONROPES • The regulations use several terms including maximum working load Working Load Limit (WLL) and nominal load. • In the UK, for the foreseeable future, the user will still be required to state a Safe Working Load (SWL). (Usually it is the same as the WLL. ) • The paperwork can use both terms. LOAD CAPACITY MARKINGS
  • 98.
    AXIOS GROUP LTD BRIDONROPES OFFSHORE CONTAINERS
  • 99.
    AXIOS GROUP LTD BRIDONROPES CONTAINER DATA PLATE The data plate shall be headed: OFFSHORE CONTAINER DATA PLATE - EN 12079 The plate shall contain the following information: Fabricator’s serial number Maximum gross mass in Kilograms, at the design sling angle Tare mass in Kilograms Payload in kilograms and intermediate deck payload (if applicable) Certificate number Design temperature
  • 100.
  • 101.
  • 102.
  • 103.
    AXIOS GROUP LTD BRIDONROPES CONTENTS OF THE STATEMENT OF CONFORMITY All containers to be used offshore shall be issued with a certificate of conformity containing the following information: – Container fabrication No. – The certificate No. – Description of the container including: External dimensions  Number of lifting points  Name of fabricator  Month/year of fabrication  Maximum gross mass in kgs  Tare mass in kgs  Payload in kgs  Reference to the as-built dossier  Total gross mass in kgs applicable to the ‘all points lifting test’ - and the actual method of test – Angle of lifting set legs (from vertical) – shackle bolt diameter
  • 104.
    AXIOS GROUP LTD BRIDONROPES  Conformity to other requirements and/or codes  A statement that the container described has been designed, fabricated and tested in accordance with EN 12079  Remarks  Signature on behalf of the certifying body CONTENTS OF A CONTAINER STATEMENT OF CONFORMITY
  • 105.
    AXIOS GROUP LTD BRIDONROPES Adequate arrangements shall be made for the safe transportation of a damaged container to the location agreed with by the owner. EUROPEAN STANDARD EN12079 (Containers) - (continued) THE CONTAINER SHALL NOT BE USED AGAIN UNTIL IT IS REPAIRED AND INSPECTED BY AN INSPECTION BODY.
  • 106.
    AXIOS GROUP LTD BRIDONROPES CEN TC 280 Standard for Offshore Containers Procedure No. 12 - Pre-trip Inspections: (continued) The responsible person shall confirm , by signature and date (eg on the shipping manifest) that inspection has been carried out to his satisfaction. Records of inspections shall be retained by the user for a period of at least 60 days
  • 107.
    AXIOS GROUP LTD BRIDONROPES Contract Lift The term “contract lift” refers to the situation where an organisation enters into a contract with a third party, who will undertake the lifting operation on their behalf, i.e. the third party provides the lifting equipment (such as a crane) and the operator. In these circumstances, the crane owner has the duty to ensure that the crane is properly maintained, inspected and safe to use and that lifting operation is carried out safely.
  • 108.
    AXIOS GROUP LTD BRIDONROPES Crane on Hire BS 7121 Part 1 The user then has the duty to manage the lifting operation in a safe manner, unless other arrangements are made, e.g. under the terms of a contract. When hiring a crane, the crane hire company should produce physical evidence of the last inspection report for the crane, and lifting equipment. After installation, the user should ensure that the crane is inspected by a competent person before being put into use. (Normally this will be done by the hire company, particularly if they erect the crane).
  • 109.
    AXIOS GROUP LTD BRIDONROPES END OF PRESENTATION