Load Flow Studies
All STG Plans of Discos
Transmission Plan of NTDC
Generation Plan of NTDC
Verify Generators Scope
Verify Grid Stations (Bus Bars and Transformers) Scope
Verify Transmission Line Scope
Verify Capacitors Scope
Verify New Grid Stations Scope along with Transmission Lines
Verify New Consumer Grid Stations Scope along with Transmission Lines
Latest Power Market Survey Load Forecast (Grid Maximum/Peak and LESCO
Maximum/Peak)
Diversity Factor
Month Factor
Load Distribution proportional to Transformer MVA Capacity
MW is now available
To Calculate MVAR, Power Factor is Required
Power Factor for Existing Grid Stations (Realistic)
Power Factor for New Grid Stations (Average, Nearby, Dominating, Assumptions ... etc)
Power Factor for Extensions (Average of rest)
Power Factor for Consumer Grid Stations
Consumer Grid Station (Load is Fixed and Non-Scalable) So no Diversity is applied on
Consumer Grid Stations
Scale Grid Station Wise (Proportional Transformer Wise) Load Peak to Disco Peak
Load Shifting/Movement (New Grid Stations, Extensions and Augmentations)
Generators Parameters
Transformers Parameters
Transmission Lines Parameters
Load Parameters
Variables (Vterminal/Scheduled of Generators, Taps of HV side of Transformers, Capacitors)
Measured Parameters
Bus Voltages
Swing Bus Pgen and Qgen
Qgen of Generators as compared to Qmax and should be positive
Loading of Branches (Transformers, Transmission Lines, Generators)
--
Regards,
Hammad Arif
00923334291423

Lfs

  • 1.
    Hammad Arif <hammad.account@gmail.com> LoadFlow Studies Abstract - 1 Hammad Arif <hammad.account@gmail.com> Tue, Apr 30, 2013 at 2:04 PM To: Hammad Arif <hammad.account@gmail.com>, hammad.account@yahoo.com, hammad.arif@hotmail.com, hammad.arif@aol.com Load Flow Studies All STG Plans of Discos Transmission Plan of NTDC Generation Plan of NTDC Verify Generators Scope Verify Grid Stations (Bus Bars and Transformers) Scope Verify Transmission Line Scope Verify Capacitors Scope Verify New Grid Stations Scope along with Transmission Lines Verify New Consumer Grid Stations Scope along with Transmission Lines Latest Power Market Survey Load Forecast (Grid Maximum/Peak and LESCO Maximum/Peak) Diversity Factor Month Factor Load Distribution proportional to Transformer MVA Capacity MW is now available To Calculate MVAR, Power Factor is Required Power Factor for Existing Grid Stations (Realistic) Power Factor for New Grid Stations (Average, Nearby, Dominating, Assumptions ... etc) Power Factor for Extensions (Average of rest) Power Factor for Consumer Grid Stations Consumer Grid Station (Load is Fixed and Non-Scalable) So no Diversity is applied on Consumer Grid Stations Scale Grid Station Wise (Proportional Transformer Wise) Load Peak to Disco Peak Load Shifting/Movement (New Grid Stations, Extensions and Augmentations) Generators Parameters Transformers Parameters Transmission Lines Parameters Load Parameters Variables (Vterminal/Scheduled of Generators, Taps of HV side of Transformers, Capacitors) Measured Parameters Bus Voltages Swing Bus Pgen and Qgen Qgen of Generators as compared to Qmax and should be positive Loading of Branches (Transformers, Transmission Lines, Generators)