This document describes a court case from 2014 regarding defects found in a property purchased by the plaintiffs. The plaintiffs allege that the previous owners, the second defendants, breached warranties by carrying out unauthorized work before obtaining permits and by failing to build the house in compliance with building consents. The plaintiffs are seeking damages to cover the substantial costs of remedial work needed to rectify various defects with the property, including risks from falling debris, drainage issues, an unfit retaining wall, and weathertightness problems with the house.
The Owners, Strata Plan No. VIS3578 v. Canan Investment Group Ltd., 2009 BCSC 39Rolf Warburton
This document summarizes a court case between the owners of a condominium building known as "The Metropolitan" and various parties involved in the construction of the building, including the developer, general contractor, and subcontractors. The condominium owners are claiming damages related to leaks and defects in the building envelope, including issues with the stucco cladding system. The document provides background on inspections and reports done during and after construction that identified deficiencies in the thickness of the stucco, installation of the vapor barrier and lath, and other issues. It also discusses efforts by the condominium owners to have repairs made through warranty claims.
Messenger & Anor v Stanaway Real Estate Limited & OrsPeter Bates
This judgment concerns a claim by James and June Messenger against Stanaway Real Estate for negligence regarding the failed sale of their property in 2006. The Messengers claim $2.77 million in losses. Stanaway joined the Messengers' son Gary, his real estate company Realty NZ, and law firm Simpson Western as third parties. The judgment examines the facts around the failed sale, the duties of each party, and whether their actions caused the Messengers' losses. It also considers defenses of contributory negligence.
This short document promotes creating presentations using Haiku Deck, a tool for making slideshows. It encourages the reader to get started making their own Haiku Deck presentation and sharing it on SlideShare. In just one sentence, it pitches the idea of using Haiku Deck to easily create engaging slideshow presentations.
This document presents a rare case report of a 30-year-old woman diagnosed with Takayasu arteritis who presented with both aneurysmal dilation and stenosis of the right common carotid artery. Imaging revealed aneurysmal dilation of the right innominate and proximal right common carotid arteries as well as a 75% focal stenosis in the right common carotid artery distal to the dilation. Treatment with prednisone resulted in improvement of symptoms and normalization of inflammation markers. The concurrent presence of aneurysmal dilation and stenosis from Takayasu arteritis in the same vessel is an exceptionally rare finding.
Las tecnologías de la información y la comunicación (TIC) son herramientas que permiten la creación, almacenamiento, gestión y comunicación de información. Estas tecnologías incluyen internet, computadoras, teléfonos inteligentes y otros dispositivos digitales que facilitan la conectividad y el acceso a la información de manera rápida y eficiente. Las TIC han revolucionado la forma en que las personas se comunican, aprenden y trabajan en el siglo XXI.
This document provides a summary of Denice LaCombe's work history and qualifications. She has over 30 years of nursing experience, including 20 years working in intensive care units. Her most recent role is as a staff RN in the intensive care unit at Dignity Health since 2012. Prior to that, she held various critical care leadership roles such as Director of Critical Care Services and Charge Nurse. She has a Bachelor's Degree in Nursing and licenses including BLS and ACLS.
This document outlines a case brought before the Weathertight Homes Tribunal regarding a property purchased by David and Karen Strickland in Kaukapakapa. Within months of moving in, the Stricklands experienced leaks around the joinery, through walls, and around internal gutters. Experts advised the house needs to be demolished and rebuilt due to significant defects. The Stricklands are claiming costs of $892,200 for rebuild, $15,000 in consequential damages, and $25,000 in general damages from several parties involved in the original construction of the house, including the builder Andre Gaensicke, his brother Karl, the architect Ian Sharplin, Auckland Council, the roofing
North Shields Juniors AFC History Presentation. Katie Scarth
This document provides a history of North Shields Juniors AFC, a youth football club founded in 1996. It details the club's growth from 3 teams and 45 players to 43 teams and 650 players in 2014/15. It highlights milestones like forming girls teams in 2002, registering as a charity in 2006, and building a new pitch in 2014. The club has also supported international development by donating kits to South Africa. The history shows the club's continuing efforts to develop and support youth football.
The Owners, Strata Plan No. VIS3578 v. Canan Investment Group Ltd., 2009 BCSC 39Rolf Warburton
This document summarizes a court case between the owners of a condominium building known as "The Metropolitan" and various parties involved in the construction of the building, including the developer, general contractor, and subcontractors. The condominium owners are claiming damages related to leaks and defects in the building envelope, including issues with the stucco cladding system. The document provides background on inspections and reports done during and after construction that identified deficiencies in the thickness of the stucco, installation of the vapor barrier and lath, and other issues. It also discusses efforts by the condominium owners to have repairs made through warranty claims.
Messenger & Anor v Stanaway Real Estate Limited & OrsPeter Bates
This judgment concerns a claim by James and June Messenger against Stanaway Real Estate for negligence regarding the failed sale of their property in 2006. The Messengers claim $2.77 million in losses. Stanaway joined the Messengers' son Gary, his real estate company Realty NZ, and law firm Simpson Western as third parties. The judgment examines the facts around the failed sale, the duties of each party, and whether their actions caused the Messengers' losses. It also considers defenses of contributory negligence.
This short document promotes creating presentations using Haiku Deck, a tool for making slideshows. It encourages the reader to get started making their own Haiku Deck presentation and sharing it on SlideShare. In just one sentence, it pitches the idea of using Haiku Deck to easily create engaging slideshow presentations.
This document presents a rare case report of a 30-year-old woman diagnosed with Takayasu arteritis who presented with both aneurysmal dilation and stenosis of the right common carotid artery. Imaging revealed aneurysmal dilation of the right innominate and proximal right common carotid arteries as well as a 75% focal stenosis in the right common carotid artery distal to the dilation. Treatment with prednisone resulted in improvement of symptoms and normalization of inflammation markers. The concurrent presence of aneurysmal dilation and stenosis from Takayasu arteritis in the same vessel is an exceptionally rare finding.
Las tecnologías de la información y la comunicación (TIC) son herramientas que permiten la creación, almacenamiento, gestión y comunicación de información. Estas tecnologías incluyen internet, computadoras, teléfonos inteligentes y otros dispositivos digitales que facilitan la conectividad y el acceso a la información de manera rápida y eficiente. Las TIC han revolucionado la forma en que las personas se comunican, aprenden y trabajan en el siglo XXI.
This document provides a summary of Denice LaCombe's work history and qualifications. She has over 30 years of nursing experience, including 20 years working in intensive care units. Her most recent role is as a staff RN in the intensive care unit at Dignity Health since 2012. Prior to that, she held various critical care leadership roles such as Director of Critical Care Services and Charge Nurse. She has a Bachelor's Degree in Nursing and licenses including BLS and ACLS.
This document outlines a case brought before the Weathertight Homes Tribunal regarding a property purchased by David and Karen Strickland in Kaukapakapa. Within months of moving in, the Stricklands experienced leaks around the joinery, through walls, and around internal gutters. Experts advised the house needs to be demolished and rebuilt due to significant defects. The Stricklands are claiming costs of $892,200 for rebuild, $15,000 in consequential damages, and $25,000 in general damages from several parties involved in the original construction of the house, including the builder Andre Gaensicke, his brother Karl, the architect Ian Sharplin, Auckland Council, the roofing
North Shields Juniors AFC History Presentation. Katie Scarth
This document provides a history of North Shields Juniors AFC, a youth football club founded in 1996. It details the club's growth from 3 teams and 45 players to 43 teams and 650 players in 2014/15. It highlights milestones like forming girls teams in 2002, registering as a charity in 2006, and building a new pitch in 2014. The club has also supported international development by donating kits to South Africa. The history shows the club's continuing efforts to develop and support youth football.
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109Alec Rendell [NBPR-2]
This document summarizes a District Court appeal from a decision of the Consumer, Trader and Tenancy Tribunal regarding a building dispute. The Tribunal found that there was an agreement for the plaintiff to pay $36,000 upon completion of the slab, but the District Court found there was no evidence to support this finding. The District Court allowed the appeal, set aside the Tribunal's orders, and remitted the matter to the Tribunal for a rehearing in accordance with the District Court's reasons.
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162Alec Rendell [NBPR-2]
The document summarizes a dispute between homeowners (the applicants) and a flooring company (the respondent) over defective parquet flooring installed in the applicants' home. It provides background on the case, summarizes the key reports and evidence submitted by both parties, and details the differing conclusions reached as to the cause of the flooring defects. The respondent argued that moisture issues due to improper sealing of external doors by the applicants caused the defects, while reports submitted by the applicants concluded installation errors by the respondent were to blame. The tribunal found both parties presented insufficient evidence and had difficulty determining the cause of the defects.
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590Alec Rendell [NBPR-2]
The document summarizes a court case between James Fordham and Dewsash Pty Ltd regarding a disputed home building contract. Key points:
- Fordham sued Dewsash for damages related to issues with the home's slab. Dewsash counter-sued for unpaid invoices.
- The original tribunal ruled partially in favor of both parties. Fordham appealed and the court found errors in the tribunal's reasoning. It remanded the case back to the tribunal.
- At the new tribunal hearing, issues considered included whether Dewsash breached the contract terms, if the contract was validly terminated, and what damages were owed.
- The tribunal found Dewsash
March 2015 presentation to ASBC on slab heave and damagesAndrew Downie
This presentation looks at the history of awards of damages for demolition and reinstatement of property, including Bellgrove v Eldrige (1954) 90 CLR 613, Ruxley Electronics and Constructions Limited v Forsyth [1996] AC 344 and Tabcorp Holdings Limited v Bowen Investments Pty Ltd (2009) 236 CLR 272.
The presentation then discusses the two recent cases of Softley v Metricon Homes Pty Ltd [2014] VCAT 1502 and Hooper v Metricon Homes Pty Ltd [2014] VCAT 277 in which the Tribunal made an award of damages for demolition and reinstatement, rather than rectification, where the slab was found to be unstable.
This document summarizes a judgment from the Land and Environment Court of New South Wales regarding an application by Windy Dropdown Pty Ltd to modify a development consent granted by Warringah Council. The judgment discusses whether the court has the power to approve modifications to development consent retrospectively, when development has already been carried out that does not comply with the original consent. The judge ultimately finds that section 96 of the Environmental Planning and Assessment Act allows for retrospective modification of development consent in some circumstances.
This document summarizes a court case between Mr. and Ms. McKenzie and a building contractor, Mr. Dean, regarding defects in the construction of the McKenzie's home. The Tribunal ordered Mr. Dean to pay the McKenzies $55,416 to cover damages agreed upon by both parties and additional damages assessed by the Tribunal for other defects. Key defects included inadequate reinforcement in walls, defective concrete footings, non-compliant downpipe spacing, and failure to install eaves at the specified 600mm depth. The Tribunal found evidence provided by structural engineers supported many of the McKenzie's claims.
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...nourhaghighi
The following is DRAFT of the Major Nourhaghighi's Winning Factum before the highest court in Ontario
in which Major Nourhaghighi won a case against
the most experience Law Firm, Deacon, Spears, Fedson, & Montizambert LLP,
specialist in the Ontario Condominium Act
with $1500.00 award of Costs to Major Nourhaghighi
Court File No: M 32976
COURT OF APPEAL FOR ONTARIO
BETWEEN:
MAJOR KEYVAN NOURHAGHIGHI
Applicant (Responding Party)
-and-
CABER MANAGEMENT SERVICES INC. JOHN BEDFORD, JOHN MORIELLI,
LISA BLAIR; METRO TORONTO CONDOMINIUM CORPORATION NO. 935
Respondents (Moving Parties)
This content deals with an important judgment titled "Baini Prasad (D) Thr. LRs. vs. Durga Devi” pronounced on 2nd Feb 2023. In this judgment, the Supreme Court has held that an encroacher cannot be termed as a 'transferee' to seek the benefit of Section 51 of the Transfer of Property Act (Transfer of Property Case (2023)). To know more about it, please watch this content fully...
Property Law
Baini Prasad (D) Thr. LRs. vs. Durga Devi
https://main.sci.gov.in/supremecourt/2008/13404/13404_2008_5_1501_41434_Judgement_02-Feb-2023.pdf
The content is created by Michael Anand. I (BA., BL) who is the owner of this YouTube Channel titled "Aanand Law Reporter". He has 5 years of experience in Content Management at MLJ (Madras Law Journal) and LLJ (Labour Law Journal) which belong to Lexis Nexis and 2 years of experience at Thomson Reuters...
Thanks for going through this content. I request you to like, share, comment on it, and don't forget to subscribe to our channel...
1) Jeffrey Blackwell appealed a partial summary judgment granted in favor of CSF Properties 2, LLC on his negligence claim related to injuries sustained from a fall off the front porch of a rented property.
2) The trial court's judgment did not resolve Blackwell's separate claim of negligence per se, leaving issues still pending for determination.
3) As the judgment was not final and did not dispose of the entire judicial unit, the appellate court lacks jurisdiction and dismissed the appeal.
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceFrancis Ho
The document summarizes three UK construction law cases from 2013:
1) John Grimes Partnership v Gubbins - The Court of Appeal held an engineer liable for damages caused by project delays, including losses from a decline in property values.
2) Parkwood Leisure v Laing O'Rourke - A collateral warranty was deemed a "construction contract" subject to adjudication due to language stating works were still to be completed.
3) Urban I v Ayres - The Court of Appeal found project delays did not entitle buyers to terminate as they were not deprived of the whole contract benefit, overturning a trial decision.
2018 Year in Review: Recent Midwest Legal Decisions Impacting Real Estate and...Quarles & Brady
In 2018, the Midwest (defined as Illinois, Indiana, Iowa, Michigan, Minnesota, Missouri, Ohio, and Wisconsin) saw a number of statutory changes and court decisions that reshaped and framed a number of key issues every developer, design professional, owner, lender, contractor, and real estate and construction lawyer must know. Quarles & Brady lawyers will discuss and take questions regarding recent decisions impacting real estate and construction law.
This document summarizes a court case from the District Court of Queensland regarding an appeal of a magistrate's decision to dismiss an application for leave to proceed with an action. The plaintiff had done building work for the defendants in 1997-98 but was unpaid. The court found that the plaintiff's explanation for the delay in the case was satisfactory. Additionally, the limitation period for the claim had not yet expired. Therefore, the court set aside the magistrate's decision to dismiss the application and granted the plaintiff leave to proceed with the action.
This document is a city council agenda memorandum requesting approval for a proposed new single-family home and accessory structure at 260 Retama in Alamo Heights, Texas. It provides background on the property and previous approvals. Details of the proposed new structures are given, including dimensions, materials, and compliance with lot coverage and floor area ratio requirements. The Architectural Review Board reviewed the design and unanimously recommended approval, finding it compatible with the neighborhood. City staff are requesting the city council also approve the proposed design.
OH 7th District Court of Appeals Decision in Hupp v. Beck Energy CorpMarcellus Drilling News
The Seventh District Court of Appeals in Ohio overturned a lower court ruling and ruled in favor of Beck Energy Corp and XTO Energy, a major victory for the drillers and major defeat for the landowners in Monroe and Belmont counties who say their land never got drilled and they wanted to re-sign with another company.
The document provides summaries of several Massachusetts case law decisions related to planning and zoning. The key cases discussed include:
- Collings v. Planning Board of Stow: The planning board could not require an applicant to convey land to the town as a condition of subdivision approval without just compensation.
- Kenner v. Zoning Board of Appeals of Chatham: Abutters did not have standing to challenge a project based solely on impacts to their private ocean views, as the zoning law addressed impacts to the neighborhood visual character.
- Marhefka v. Zoning Board of Appeals of Sutton: Abutters had standing to challenge a project that would increase density and violate zoning provisions related to maintaining a
This document summarizes a Queensland Civil and Administrative Tribunal decision regarding a dispute over compensation owed by a tenant, Cassandra Meehan, to her landlord, Stella Property Group Pty Ltd. The Tribunal found that Ms. Meehan owed $33.81 for unpaid water rates, as the property was deemed water efficient. She was also found liable for $330.19 in rent owed until she returned the property keys on November 17th, as she did not fully vacate the property or complete required cleaning and repairs on the agreed upon handover date of November 6th.
The newsletter provides information on recent events and updates in construction law adjudication. It summarizes that the annual London adjudication conference in August was a success, with the next major conference planned for Edinburgh in 2022. It also summarizes a recent Irish court case that enforced an adjudicator's decision and clarified that parties have an unfettered right to refer disputes to adjudication under Irish law. Upcoming events and conferences are also announced.
This document summarizes a case between a builder, Ultra Developments Pty Ltd, and a homeowner, Alison Bennett. The builder was contracted to perform renovations on the homeowner's property but the project was halted in July 2011. The builder is claiming unpaid fees of $158,507.41 while the homeowner has filed a cross-claim alleging defective workmanship and misleading representations by the builder that led to overcapitalization of the property. The tribunal must determine payment amounts owed, if any defects exist, and whether the contract was wrongfully terminated.
This newsletter summarizes upcoming adjudication and arbitration conferences in Edinburgh, London, and Cape Town. It also provides details on enforcing an adjudicator's decision in Northern Ireland. The key enforcement steps include issuing a writ of summons in the Queen's Bench Division of the High Court of Justice in Northern Ireland and applying for summary judgment. Recent Northern Irish court decisions generally support the enforcement of adjudicator's decisions in line with promoting cash flow in the construction industry.
This case establishes that the demolition of most buildings will now require planning permission. It overturns exemptions that previously allowed demolition of buildings other than dwellings without permission. As a result, developers will need to apply for prior approval from local authorities for demolitions beyond just dwellings. They may also need to conduct environmental impact assessments if demolitions could significantly affect the environment. The Court of Appeal ruling upholds a challenge by heritage group SAVE that argued demolitions should be considered a form of development requiring permission or assessment. This is a significant judgment that will impact how local authorities regulate demolitions going forward.
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109Alec Rendell [NBPR-2]
This document summarizes a District Court appeal from a decision of the Consumer, Trader and Tenancy Tribunal regarding a building dispute. The Tribunal found that there was an agreement for the plaintiff to pay $36,000 upon completion of the slab, but the District Court found there was no evidence to support this finding. The District Court allowed the appeal, set aside the Tribunal's orders, and remitted the matter to the Tribunal for a rehearing in accordance with the District Court's reasons.
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162Alec Rendell [NBPR-2]
The document summarizes a dispute between homeowners (the applicants) and a flooring company (the respondent) over defective parquet flooring installed in the applicants' home. It provides background on the case, summarizes the key reports and evidence submitted by both parties, and details the differing conclusions reached as to the cause of the flooring defects. The respondent argued that moisture issues due to improper sealing of external doors by the applicants caused the defects, while reports submitted by the applicants concluded installation errors by the respondent were to blame. The tribunal found both parties presented insufficient evidence and had difficulty determining the cause of the defects.
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590Alec Rendell [NBPR-2]
The document summarizes a court case between James Fordham and Dewsash Pty Ltd regarding a disputed home building contract. Key points:
- Fordham sued Dewsash for damages related to issues with the home's slab. Dewsash counter-sued for unpaid invoices.
- The original tribunal ruled partially in favor of both parties. Fordham appealed and the court found errors in the tribunal's reasoning. It remanded the case back to the tribunal.
- At the new tribunal hearing, issues considered included whether Dewsash breached the contract terms, if the contract was validly terminated, and what damages were owed.
- The tribunal found Dewsash
March 2015 presentation to ASBC on slab heave and damagesAndrew Downie
This presentation looks at the history of awards of damages for demolition and reinstatement of property, including Bellgrove v Eldrige (1954) 90 CLR 613, Ruxley Electronics and Constructions Limited v Forsyth [1996] AC 344 and Tabcorp Holdings Limited v Bowen Investments Pty Ltd (2009) 236 CLR 272.
The presentation then discusses the two recent cases of Softley v Metricon Homes Pty Ltd [2014] VCAT 1502 and Hooper v Metricon Homes Pty Ltd [2014] VCAT 277 in which the Tribunal made an award of damages for demolition and reinstatement, rather than rectification, where the slab was found to be unstable.
This document summarizes a judgment from the Land and Environment Court of New South Wales regarding an application by Windy Dropdown Pty Ltd to modify a development consent granted by Warringah Council. The judgment discusses whether the court has the power to approve modifications to development consent retrospectively, when development has already been carried out that does not comply with the original consent. The judge ultimately finds that section 96 of the Environmental Planning and Assessment Act allows for retrospective modification of development consent in some circumstances.
This document summarizes a court case between Mr. and Ms. McKenzie and a building contractor, Mr. Dean, regarding defects in the construction of the McKenzie's home. The Tribunal ordered Mr. Dean to pay the McKenzies $55,416 to cover damages agreed upon by both parties and additional damages assessed by the Tribunal for other defects. Key defects included inadequate reinforcement in walls, defective concrete footings, non-compliant downpipe spacing, and failure to install eaves at the specified 600mm depth. The Tribunal found evidence provided by structural engineers supported many of the McKenzie's claims.
The Lord of Law: Major Nourhaghighi's Factum before the Court of Appeal for O...nourhaghighi
The following is DRAFT of the Major Nourhaghighi's Winning Factum before the highest court in Ontario
in which Major Nourhaghighi won a case against
the most experience Law Firm, Deacon, Spears, Fedson, & Montizambert LLP,
specialist in the Ontario Condominium Act
with $1500.00 award of Costs to Major Nourhaghighi
Court File No: M 32976
COURT OF APPEAL FOR ONTARIO
BETWEEN:
MAJOR KEYVAN NOURHAGHIGHI
Applicant (Responding Party)
-and-
CABER MANAGEMENT SERVICES INC. JOHN BEDFORD, JOHN MORIELLI,
LISA BLAIR; METRO TORONTO CONDOMINIUM CORPORATION NO. 935
Respondents (Moving Parties)
This content deals with an important judgment titled "Baini Prasad (D) Thr. LRs. vs. Durga Devi” pronounced on 2nd Feb 2023. In this judgment, the Supreme Court has held that an encroacher cannot be termed as a 'transferee' to seek the benefit of Section 51 of the Transfer of Property Act (Transfer of Property Case (2023)). To know more about it, please watch this content fully...
Property Law
Baini Prasad (D) Thr. LRs. vs. Durga Devi
https://main.sci.gov.in/supremecourt/2008/13404/13404_2008_5_1501_41434_Judgement_02-Feb-2023.pdf
The content is created by Michael Anand. I (BA., BL) who is the owner of this YouTube Channel titled "Aanand Law Reporter". He has 5 years of experience in Content Management at MLJ (Madras Law Journal) and LLJ (Labour Law Journal) which belong to Lexis Nexis and 2 years of experience at Thomson Reuters...
Thanks for going through this content. I request you to like, share, comment on it, and don't forget to subscribe to our channel...
1) Jeffrey Blackwell appealed a partial summary judgment granted in favor of CSF Properties 2, LLC on his negligence claim related to injuries sustained from a fall off the front porch of a rented property.
2) The trial court's judgment did not resolve Blackwell's separate claim of negligence per se, leaving issues still pending for determination.
3) As the judgment was not final and did not dispose of the entire judicial unit, the appellate court lacks jurisdiction and dismissed the appeal.
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceFrancis Ho
The document summarizes three UK construction law cases from 2013:
1) John Grimes Partnership v Gubbins - The Court of Appeal held an engineer liable for damages caused by project delays, including losses from a decline in property values.
2) Parkwood Leisure v Laing O'Rourke - A collateral warranty was deemed a "construction contract" subject to adjudication due to language stating works were still to be completed.
3) Urban I v Ayres - The Court of Appeal found project delays did not entitle buyers to terminate as they were not deprived of the whole contract benefit, overturning a trial decision.
2018 Year in Review: Recent Midwest Legal Decisions Impacting Real Estate and...Quarles & Brady
In 2018, the Midwest (defined as Illinois, Indiana, Iowa, Michigan, Minnesota, Missouri, Ohio, and Wisconsin) saw a number of statutory changes and court decisions that reshaped and framed a number of key issues every developer, design professional, owner, lender, contractor, and real estate and construction lawyer must know. Quarles & Brady lawyers will discuss and take questions regarding recent decisions impacting real estate and construction law.
This document summarizes a court case from the District Court of Queensland regarding an appeal of a magistrate's decision to dismiss an application for leave to proceed with an action. The plaintiff had done building work for the defendants in 1997-98 but was unpaid. The court found that the plaintiff's explanation for the delay in the case was satisfactory. Additionally, the limitation period for the claim had not yet expired. Therefore, the court set aside the magistrate's decision to dismiss the application and granted the plaintiff leave to proceed with the action.
This document is a city council agenda memorandum requesting approval for a proposed new single-family home and accessory structure at 260 Retama in Alamo Heights, Texas. It provides background on the property and previous approvals. Details of the proposed new structures are given, including dimensions, materials, and compliance with lot coverage and floor area ratio requirements. The Architectural Review Board reviewed the design and unanimously recommended approval, finding it compatible with the neighborhood. City staff are requesting the city council also approve the proposed design.
OH 7th District Court of Appeals Decision in Hupp v. Beck Energy CorpMarcellus Drilling News
The Seventh District Court of Appeals in Ohio overturned a lower court ruling and ruled in favor of Beck Energy Corp and XTO Energy, a major victory for the drillers and major defeat for the landowners in Monroe and Belmont counties who say their land never got drilled and they wanted to re-sign with another company.
The document provides summaries of several Massachusetts case law decisions related to planning and zoning. The key cases discussed include:
- Collings v. Planning Board of Stow: The planning board could not require an applicant to convey land to the town as a condition of subdivision approval without just compensation.
- Kenner v. Zoning Board of Appeals of Chatham: Abutters did not have standing to challenge a project based solely on impacts to their private ocean views, as the zoning law addressed impacts to the neighborhood visual character.
- Marhefka v. Zoning Board of Appeals of Sutton: Abutters had standing to challenge a project that would increase density and violate zoning provisions related to maintaining a
This document summarizes a Queensland Civil and Administrative Tribunal decision regarding a dispute over compensation owed by a tenant, Cassandra Meehan, to her landlord, Stella Property Group Pty Ltd. The Tribunal found that Ms. Meehan owed $33.81 for unpaid water rates, as the property was deemed water efficient. She was also found liable for $330.19 in rent owed until she returned the property keys on November 17th, as she did not fully vacate the property or complete required cleaning and repairs on the agreed upon handover date of November 6th.
The newsletter provides information on recent events and updates in construction law adjudication. It summarizes that the annual London adjudication conference in August was a success, with the next major conference planned for Edinburgh in 2022. It also summarizes a recent Irish court case that enforced an adjudicator's decision and clarified that parties have an unfettered right to refer disputes to adjudication under Irish law. Upcoming events and conferences are also announced.
This document summarizes a case between a builder, Ultra Developments Pty Ltd, and a homeowner, Alison Bennett. The builder was contracted to perform renovations on the homeowner's property but the project was halted in July 2011. The builder is claiming unpaid fees of $158,507.41 while the homeowner has filed a cross-claim alleging defective workmanship and misleading representations by the builder that led to overcapitalization of the property. The tribunal must determine payment amounts owed, if any defects exist, and whether the contract was wrongfully terminated.
This newsletter summarizes upcoming adjudication and arbitration conferences in Edinburgh, London, and Cape Town. It also provides details on enforcing an adjudicator's decision in Northern Ireland. The key enforcement steps include issuing a writ of summons in the Queen's Bench Division of the High Court of Justice in Northern Ireland and applying for summary judgment. Recent Northern Irish court decisions generally support the enforcement of adjudicator's decisions in line with promoting cash flow in the construction industry.
This case establishes that the demolition of most buildings will now require planning permission. It overturns exemptions that previously allowed demolition of buildings other than dwellings without permission. As a result, developers will need to apply for prior approval from local authorities for demolitions beyond just dwellings. They may also need to conduct environmental impact assessments if demolitions could significantly affect the environment. The Court of Appeal ruling upholds a challenge by heritage group SAVE that argued demolitions should be considered a form of development requiring permission or assessment. This is a significant judgment that will impact how local authorities regulate demolitions going forward.
1. JERARD v PAXTON PAXTON [2014] NZHC 2493 [10 October 2014]
IN THE HIGH COURT OF NEW ZEALAND
AUCKLAND REGISTRY
CIV-2011-404-7422
[2014] NZHC 2493
BETWEEN KENNETH JAMES JERARD and LINDA
IRENE LEADER
Plaintiffs
AUCKLAND COUNCIL
First Defendant
AND BRYCE WARRAN PAXTON and
AMANDA SARAH PAXTON
Second Defendants
BROWN BROTHERS BUILDERS
LIMITED
First Third Party
IAN HUTCHINSON CONSULTANTS
LIMITED
Second Third Party
BRETT CONWAY BROWN
Third Third Party
MATTHEW TICKLE
Fourth Third Party
POLE SPECIALISTS LIMITED
Fifth Third Party
DEAN HENSHAW
Sixth Third Party
SHORE PLUMBING LIMITED
Seventh Third Party
Hearing: 6-9 October 2014
Appearances: T J Rainey, D A Cowan and J Heard for plaintiffs
No appearance for second defendants
Judgment: 10 October 2014
2. JUDGMENT OF LANG J
This judgment was delivered by me on 10 October 2014 at 3 pm,
pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date……………
3. [1] This proceeding concerns a property situated at 12 Fairhaven Walk, Arkles
Bay (“the property”). The plaintiffs, Mr Jerard and Ms Leader, are the present
owners of the property. They purchased the property in December 2005 from the
second defendants, Mr and Mrs Paxton.
[2] The plaintiffs commenced this proceeding in order to recover from the
defendants the cost of rectifying defects they have discovered in relation to the
property. They now seek judgment against the second defendants by way of formal
proof.
[3] The plaintiffs originally sued Mr and Mrs Paxton in both negligence and for
breach of contract, but ultimately restricted their claim to the latter. They allege that
Mr and Mrs Paxton breached the warranties relating to building work contained in
the agreement for sale and purchase that both parties signed when the plaintiffs
agreed to purchase the property. Mr and Mrs Paxton defended the plaintiffs’ claim
up until July 2013, but thereafter took no steps to serve evidence in support of their
defence or in support of their claims against the third parties. They did not appear
when the trial commenced on 6 October 2014.
[4] On the second day of the hearing, counsel for the remaining parties advised
the Court they had reached an unconditional settlement that will involve the
plaintiffs receiving the sum of $260,000 from those parties. For that reason the trial
proceeded by way of formal proof against the second defendants alone.
[5] When the trial began, the plaintiffs sought damages based on the cost of
rendering the property code compliant. They contended that remedial works to the
land would be likely to cost approximately $657,000, and that remedial works to the
house will probably cost approximately $250,000. The plaintiffs also sought
consequential losses totalling $42,514.69, and general damages for stress and
inconvenience in the sum of $25,000.
[6] When the plaintiffs closed their case, they sought damages calculated on the
basis of the extent to which their property has diminished in value by virtue of the
4. defects that have been identified. They sought damages in the sum of $550,000 on
this basis, reduced by $260,000 to reflect the payment they are to receive from the
other parties to this proceeding. They abandoned their claim for consequential
losses, but maintained their claim for general damages in the sum of $25,000.
The plaintiffs' claim
[7] The plaintiffs sue Mr and Mrs Paxton for breach of the following warranties
contained in cl 6.2(5) of the agreement for sale and purchase that they signed when
they agreed to purchase the property from them:
Where the vendor has done or caused or permitted to be done on the
property any works for which a permit or building consent was required by
law:
(a) The required permit or consent was obtained; and
(b) The works were completed in compliance with that permit or consent;
and
(c) Where appropriate, a code compliance certificate was issued for those
works; and
(d) All obligations imposed under the Building Act 1991 were fully
complied with.
[8] The evidence establishes conclusively that Mr and Mrs Paxton were the
persons who caused the house to be built on the property, and that the construction of
the house required a building consent. As a result, there can be no dispute that the
plaintiffs are entitled to the protection of the warranty contained in cl 6.2(5) of the
agreement for sale and purchase.
[9] The plaintiffs accept that Mr and Mrs Paxton obtained both a resource
consent and building permit from the Rodney District Council (the Council) in
respect of works to be carried out on the property. They maintain, however, that
these could not and did not cover preparatory work that the plaintiffs had already
carried out on the property before they had obtained either a resource consent or a
building consent. They therefore contend that Mr and Mrs Paxton breached the
warranty contained in cl 6.2(5)(a).
5. [10] The plaintiffs also accept that the Council subsequently issued a code
compliance certificate in respect of the work carried out in relation to the
construction of the house. The code compliance certificate was subsequently set
aside, however, after the plaintiffs obtained a determination from the Chief
Executive of the Department of Building and Housing that the Council did not have
reasonable grounds to be satisfied that the work carried out under the building
consent complied with the New Zealand Building Code.1
Following that decision,
the Council served a notice on the plaintiffs requiring them to rectify the defects
identified in the Chief Executive’s determination. The Council has agreed not to
enforce that notice pending determination of the present proceeding.
[11] As counsel for the plaintiffs recognised in his closing submissions, the fact
that the code compliance certificate was subsequently set aside does not mean that
Mr and Mrs Paxton are in breach of the warranty contained in cl 6.2(5)(c). That
warranty related to the state of affairs that existed when the parties signed the
agreement for sale and purchase. As at that date there had been no challenge to the
validity of the code compliance certificate. There is therefore no basis for the
plaintiffs to allege that Mr and Mrs Paxton breached the warranty contained in cl
6.2(5)(c).
[12] For reasons I shall shortly explain,2
it is not necessary in the circumstances of
the present case for the plaintiffs to rely upon an alleged breach of cl 6.2(5)(d). The
second defendants’ liability can be determined by consideration of whether in terms
of cl 6.2(5)(a) Mr and Mrs Paxton carried out work on the site before obtaining the
necessary consents, and whether in terms of cl 6.2(5)(b) they built the house in
compliance with the building consent.
The alleged defects
[13] The section on which Mr and Mrs Paxton built the house slopes steeply from
top to bottom, and was originally covered densely with large trees and thick bush.
Mr and Mrs Paxton began the construction works by felling a large number of trees.
They then created a small building platform by digging into the hillside. They
1
Determination 2010/116, 26 November 2010.
2
At [20].
6. disposed of spoil from the excavation works by tipping it over fallen trees to the
eastern side of the building platform. This area was later gravelled, and currently
forms an unsealed driveway that travels along the eastern side of the house to the
rear of the building platform.
[14] Mr and Mrs Paxton then built a house on the platform supported by poles. At
the rear of the house is a small back yard bounded by a steep rock face that was
exposed by the excavation works. The land above the rock face remains covered in a
mixture of very large trees and dense bush.
[15] The alleged defects that have given rise to the plaintiffs' claim can be
summarised as follows:
(a) although the rock face at the rear of the house is stable, the absence of
any retaining wall means that the house is exposed to the risk of being
damaged by debris that may wash down the hillside above the house
during extreme weather events;
(b) the construction of the house involved the diversion of natural water
flows so that in times of heavy rainfall, water now runs under the
house and through the uncompacted fill under the driveway on the
eastern side of the house. This places the integrity of both the house
and the driveway at risk;
(c) a retaining wall that runs along the edge of the driveway on the
eastern side of the property is not structurally fit for purpose and does
not have a safety rail or barrier; and
(d) the house suffers from weathertightness defects that have permitted
water ingress and resulting damage to the structure of the house.
The remedial work
[16] The expert evidence called by the plaintiffs establishes that the identified
defects will require extensive remedial work. This will include:
7. (a) construction of a substantial retaining wall at the rear of the house to
protect the house from being damaged by debris that may be washed
down the hillside;
(b) removal of the uncompacted fill under the driveway on the eastern
side of the house and replacement with compacted fill of suitable
quality;
(c) installation of appropriate drainage to ensure that the house and
driveway are not placed at risk in times of extremely heavy rainfall;
(d) replacement of the retaining wall on the eastern side of the property
with a retaining wall that is fit for purpose and has an adequate
barrier;
(e) removal of existing cladding from the house and replacement of all
damaged internal timber structures; and
(f) replacement of the entire cladding of the house and re-installation of
all affected joinery using appropriate flashings.
[17] The plaintiffs have obtained quotations from contractors having the ability to
carry out the necessary remedial work. These were based on calculations produced
by the plaintiffs' quantity surveyor. The quotations establish that the work necessary
to rectify the defects outside and around the house will cost $657,797, whilst the
work necessary to rectify the weathertightness defects in the dwelling will cost
$262,453.
Liability
[18] The plaintiffs point out that the preparatory work that Mr and Mrs Paxton
carried out on the building platform was not the subject of a building permit at the
time it was undertaken. I accept this submission, and consider it constituted a clear
breach of the warranty in cl 6.2(5)(a). In order to rectify that issue now, the plaintiffs
8. will be required to build a substantial retaining wall and install appropriate drainage
works.
[19] The plaintiffs’ claim for breach of warranty under cl 6.2(5)(b) relies on the
fact that the building consent contained an express provision requiring all building
work carried out under the consent to comply with the provisions of the Building
Code 1992.3
It is therefore not necessary for me to consider whether failure to
comply with the requirements of the Building Code also amounted to a breach of the
warranty in cl 6.2(5)(d) of the agreement for sale and purchase. Under that clause
the vendor warrants that all building work complies with the obligations imposed by
the Building Act 1991. The issue potentially arises in the present case because at the
time Mr and Mrs Paxton built the house s 7 of the Building Act 1991 required all
building work to comply with the Building Code. Whether failure to comply with
this statutory obligation also constitutes a breach of the warranty in cl 6.2(5)(d) has
been the subject of conflicting decisions in this Court.4
[20] The issue as to whether Mr and Mrs Paxton built the house in a manner that
complied with the requirements imposed by the Building Code has already largely
been determined in their favour by the determination issued by the Chief Executive
of the Department of Building and Housing. The Chief Executive determined that
the site stability and structure did not comply with Clause B1 of the Building Code,
and that the drainage on the property was not adequate to direct water from overland
flow paths away from the dwelling. This meant that the building work did not
comply with Clauses B2, E1 and E2 of the Building Code. Furthermore, the fact that
the retaining wall on the eastern boundary of the property did not have a safety
barrier meant that it did not comply with Clause F4 of the Building Code. In the
absence of any fresh evidence demonstrating that these conclusions were wrong, this
Court has no basis to revisit them. Each of the identified defects would constitute a
breach of the warranty contained in cl 6.2(5)(b).
3
The Building Code is set out in the First Schedule to the Building Regulations 1992.
4
Compare the approach taken by Ronald Young J in Van Huijsduijnen v Woodley [2012] NZHC
2685 at [32]-[34] with that taken by Asher J in Saffioti v Ward [2013] NZHC 2831, (2013) 14
NZCPR 792 at [36]-[43].
9. [21] Mr and Mrs Paxton also rely in this context upon the expert evidence given
by Mr Patrick Shorten, Dr Sean Finnegan and Mr Barry Gill.
Mr Shorten’s evidence
[22] Mr Shorten is a Chartered Professional Engineer with 36 years experience as
a geotechnical engineer and engineering geologist. Through his firm Fraser Thomas
Ltd, Mr Shorten has provided the plaintiffs with expert advice regarding the
geotechnical issues arising out of the manner in which Mr and Mrs Paxton
constructed the house. His evidence is to the effect that:
(a) the retaining wall on the eastern side of the property does not meet the
structural requirements of the Building Code for several reasons.
These stem largely from the fact that insufficient analysis was carried
out in relation to ground strength and conditions beneath the proposed
path of the retaining wall. He considers that poles having a much
larger diameter ought to have been used to prop up the wall, and that a
safety barrier will need to be installed on top of the wall;
(b) the cut to the steep bank at the rear of the house fails to meet the
requirements of Clause B2 of the Building Code, which requires
building elements to be sufficiently durable to ensure that buildings
satisfy their functional requirements throughout their usable lives. It
requires structural elements to perform for 50 years if they provide
structural stability to a building; and
(c) the failure to make adequate provision for water flows meant that the
work failed to comply with Clause E1 of the Building Code, which
requires that surface water from storm events having a two per cent
probability of occurring annually shall not enter buildings.
Dr Finnegan’s evidence
[23] Dr Finnegan is a senior Environmental Engineer and a director of Fraser
Thomas Ltd. He has specialist skills and expertise in several fields, including
10. hydrology and issues relating to stormwater. He has provided the plaintiffs with
expert advice regarding the issues arising out of the diversion of the natural water
flows at the time Mr and Mrs Paxton built the house and the proposal that new
retaining walls be built at the rear and along the eastern side of the property.
[24] Dr Finnegan says that the present forms of drainage at the property breach the
requirements of Clause E1 of the Building Code in several respects. The objective
of this clause is to safeguard property from damage from surface water and to protect
the outfalls of drainage systems. Furthermore, the fact that water is able to flow
beneath the house means that the land may become saturated and will cause further
instability to the uncompacted fill on the site. This is in breach of Clauses E2 and B1
of the Building Code. Other aspects of the present drainage system breach the
requirements of Clauses B1, B2 and E1 of the Building Code.
Mr Gill’s evidence
[25] Mr Gill is a registered building surveyor and has significant experience in
dealing with weathertightness issues. He has given detailed evidence regarding the
defects that have contributed to water ingress at the plaintiffs' property. The four
principal defects are the fact that several joinery units lack a weathertight seal and
there has been a failure to install the cavity cladding system in accordance with good
trade practice. In addition, the roof has not been installed in accordance with good
trade practice, and inadequate repairs have been carried out to a butynol membrane
covering a deck at the front of the property. All of these defects have permitted
water to enter the house and cause damage to the internal structure.
[26] Mr Gill says that the ingress of water through these defects means that the
house was not built in accordance with two particular requirements imposed by the
Building Code. These are Clauses B2 (relating to durability of construction work)
and E2 (relating to moisture).
[27] In his closing submissions counsel for the plaintiffs helpfully tendered a table
setting out in greater detail the individual defects that have been identified as being
in breach of relevant requirements imposed by the Building Code. The table is
annexed as an Appendix to this judgment.
11. Conclusion
[28] The evidence summarised above satisfies me that the plaintiffs have
established that Mr and Mrs Paxton began construction work before they had
obtained the required resource and building consents, and that the construction work
did not comply with material requirements imposed by the Building Code. It
follows that the plaintiffs have established that Mr and Mrs Paxton breached the
warranties contained in cl 6.2(5)(a) and (b) of the agreement for sale and purchase.
Damages
Should damages be awarded based on diminution of value of the property or the
likely cost of remedial work?
[29] As a general proposition, damages awarded for breach of contract are
designed to return the injured party to the same position he or she would have been
in but for the breach in question. The circumstances of the present case are such,
however, that there could have been a real issue as to whether the plaintiffs should
receive damages based on the cost of repairing the property or damages based on the
extent to which the defects have diminished the value of the property. Although the
plaintiffs ultimately elected for practical purposes to proceed on the latter basis, I
propose to briefly consider whether they may have been able to recover damages
based on the likely cost of remedial work.
[30] There being no evidence to the contrary, I accept that the likely costs of
remedial works to the land will be $657,797 and the likely costs of repairing the
house would be $253,745.
[31] It is then necessary is to fix a present value for the property. The plaintiffs'
valuer says it is difficult to assess the current market value of the property, because it
is difficult to see why a reasonable purchaser would be prepared to pay anything to
acquire a property requiring so much remedial work to be carried out before it will
be code compliant. He says that the property may in fact have a negative value. By
that I take him to say that the plaintiffs may need to pay a purchaser to take the
property off their hands. At the most, the plaintiffs' valuer considers the property
may be worth $150,000.
12. [32] The problems that beset this property are such that I do not consider that it
currently has any value. I reach that conclusion because I cannot conceive of any
rational person being prepared to pay for the privilege of fixing them. In the absence
of further evidence quantifying the negative value of the property, however, I would
not be prepared to ascribe a negative value to it.
[33] The potential issue, therefore, was whether the plaintiffs should receive
damages in the sum of $911,542 or damages in the sum of $550,000.
[34] The most recent New Zealand authority in relation to the measure of damages
for breach of contract is the decision of the Supreme Court in Marlborough District
Council v Altimarloch Joint Venture Ltd.5
In that case Tipping J observed:
[156] It is as well to remember at the outset that what damages are
appropriate is a question of fact. There are no absolute rules in this area,
albeit the courts have established prima facie approaches in certain types of
case to give general guidance and a measure of predictability. The key
purpose when assessing damages is to reflect the extent of the loss actually
and reasonably suffered by the plaintiff. The reference to reasonableness has
echoes of mitigation. A plaintiff cannot claim damages which could have
been avoided or reduced by the taking of reasonable steps.
[35] I also draw assistance from the following passages of the judgment of
Tipping J in Altimarloch.
[157] In the leading case of Robinson v Harman, Parke B said that a party
who suffers loss on account of a breach of contract is, by means of damages,
to be placed in the same situation as if the contract had been performed. In
Radford v de Froberville Oliver J emphasised that this formulation did not
necessarily mean only as good a financial position; more may be required. In
some cases the appropriate and sufficient measure of damages for breach
will put the plaintiff in as good a financial position as if the contract had not
been broken. That is likely to be the case where the contract involves a
marketable (that is, readily substitutable) commodity or other subject-matter.
But if the subject-matter of the contract is not of that kind, an actual or
notional sale of the defective item and its replacement with an item of the
contractual standard will not usually be a feasible measure. A performance
measure rather than one which is strictly compensatory may then be
necessary. The difference in subject-matter which underpins this approach is
similar to the difference between cases where damages are an adequate
remedy and those where the subject-matter is such that specific performance
is the appropriate remedy for non-performance.
5
Marlborough District Council v Altimarloch Joint Venture Ltd [2012] NZSC 11, [2012] 2 NZLR
726.
13. [158] In the first kind of case, where the subject-matter is readily
substitutable, the damages are truly compensatory, that is, they compensate
for the difference between the value of the defective subject-matter (which is
either actually or notionally sold) and the value or cost of goods or other
subject-matter answering to the contractual requirements. In the second kind
of case, where the subject-matter is not readily substitutable, the damages are
designed to require the defendant to pay the plaintiff enough money to
enable the plaintiff to have the contract performed as fully as is reasonable
and possible. Damages in this second kind of case can therefore usefully be
called performance damages, as opposed to damages which compensate for
loss of value.
(footnotes omitted)
[36] Although the members of the Court were ultimately divided as to the appropriate
outcome in Altimarloch, I do not read the judgments of the other members of the Court
as taking issue with the statements of principle set out above. By way of example, the
Chief Justice, who disagreed as to the outcome on this point, observed:
[27] The usual measure of damages for breach of a term of a contract is
the difference between the value contracted for and the value obtained. That
measure may not be appropriate where achieving substitute performance is
necessary mitigation of loss or itself establishes the value lost, or in cases
where the performance interest in a contract is not captured through damages
representing the economic loss on the bargain. The last are usually
encountered where the contractual breach consists of failure to perform or
defective performance of contracts to supply services, construct buildings or
keep premises in repair, and where the usual measure is inadequate to meet
the failure in stipulated performance. In such cases, the appropriate measure
of damages may be the cost to the innocent party of having substitute
performance undertaken by a third party.
[37] Tipping J went on to refer to two modern cases of “high persuasive authority”
to demonstrate the distinction between compensatory and performance-based
damages.6
In Ruxley Electronics and Construction Ltd v Forsyth,7
contractors had built
a swimming pool to a lesser depth than that required by the contractual specifications.
The cost of rebuilding the pool in accordance with the specifications was approximately
£21,550. The evidence established, however, that the lesser depth of the pool did not
diminish the value of the plaintiff’s property in any way at all. The trial Judge held that
the costs involved in rebuilding the pool were therefore unreasonable and not
recoverable. The Court of Appeal allowed the resulting appeal, holding that the proper
measure of the plaintiff’s loss was the amount necessary to put him in the same position
6
At [159]-[166].
7
Ruxley Electronics and Construction Ltd v Forsyth [1996] AC 344 (HL).
14. as if the contract had been performed. This meant that the plaintiff was entitled to
recover the costs of rebuilding the pool.
[38] The House of Lords disagreed. It considered that the appropriate measure of
damages was diminution in value rather than reconstruction. Reconstruction of the pool
would have been unreasonable in all the circumstances, and the expenditure necessary to
achieve that outcome was out of all proportion to the benefit to be obtained from it.
Tipping J took their Lordships in Ruxley to be saying that to award the cost of rebuilding
the pool “would have the effect of unreasonably inflating the loss suffered”.8
[39] This approach is to be contrasted with that taken by the High Court of
Australia in Tabcorp Holdings Ltd v Bowen Investments Pty Ltd.9
In that case the
tenant of office premises had covenanted not to alter the premises without the
landlord’s prior written approval. The tenant proceeded to alter the ornate entrance
lobby of the premises without first obtaining the landlord’s approval. The landlord
then sued the tenant to recover the cost of restoring the lobby to its former state. The
tenant argued that the proper measure of damages was the amount by which the
premises had diminished in value as a result of the breach of covenant. This was
substantially less than the cost of restoring it to its former condition. The High Court
rejected this argument, holding that it was reasonable for the landlord to insist on
restoration of the lobby to its original state. The proper measure of damages was
therefore the cost of undertaking that work.
[40] Another case that provides useful assistance is the decision of the High Court
of Australia in Bellgrove v Eldridge.10
In that case the plaintiff had entered into a
contract under which a builder agreed to build a house for her. The plaintiff issued
proceedings after she discovered defects in the composition of the concrete used in
the foundations of the building, and in the mortar used in the erection of brick walls.
The Court held that the defects in the foundations were such that it was reasonable to
award damages reflecting the cost of demolishing the whole of the building and
erecting another in its place. In reaching this conclusion the Court said:11
8
Marlborough District Council v Altimarloch Joint Venture Ltd, above n 5 at [160].
9
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8, (2009) 236 CLR 272.
10
Bellgrove v Eldridge (1954) 90 CLR 613 (HCA).
11
At 618.
15. The qualification, however, to which this rule is subject is that, not only must
the work undertaken be necessary to produce conformity, but that also, it
must be a reasonable course to adopt. No one would doubt that where
pursuant to a building contract calling for the erection of a house with
cement rendered external walls of second-hand bricks, the builder has
constructed the walls of new bricks of first quality the owner would not be
entitled to the cost of demolishing the walls and re-erecting them in second-
hand bricks. In such circumstances the work of demolition and re-erection
would be quite unreasonable or it would, to use a term current in the United
States, constitute “economic waste”.12
We prefer, however, to think that the
building owner’s right to undertake remedial works at the expense of a
builder is not subject to any limit other than is to be found in the expressions
“necessary” and “reasonable”, for the expression “economic waste” appears
to us to go too far and would deny to a building owner the right to demolish
a structure which, though satisfactory as a structure of a particular type, is
quite different in character from that called for by the contract. Many
examples may, of course, be given of remedial work, which though
necessary to produce conformity would not constitute a reasonable method
of dealing with the situation and in such cases the true measure of the
building owner’s loss will be the diminution in value, if any, produced by the
departure from the plans and specifications or by the defective workmanship
or materials.
[41] I consider that the present case lies at the margin in terms of whether it would
have been reasonable for the plaintiffs to obtain performance-based damages. Many
would consider it unreasonable to spend more than $950,000 to produce an end product
having a market value of just $650,000. Having regard to the authorities, however, it is
at least arguable that the plaintiffs would be entitled to recover the full cost of rectifying
the defects so as to make their property code compliant. The authorities, and in
particular the approach taken in Altimarloch, appear to indicate that performance-based
damages will usually be justified in cases where the subject-matter of the contract is not
readily substitutable for another equivalent alternative. That would clearly be the
situation in the present case.
[42] Acceptance of that argument would necessarily involve a major qualification.
Before the Court would award performance-based damages, it would need to be satisfied
that the plaintiffs were genuinely committed to undertaking the remedial works in
respect of which the damages were to be awarded.13
By the end of the evidence,
however, several factors left me unconvinced that the plaintiffs would take that step.
First, it does not make economic sense for the plaintiffs to repair the property given the
costs involved and the likely market value of the property once repairs have been
12
See Restatement of the Law of Contracts (1932) par 346.
13
16. completed. Secondly, I did not sense that the plaintiffs have any emotional or spiritual
commitment to either the property or its location. Rather, their evidence was to the
effect that their involvement with the property has been a financial and emotional
disaster for them from the outset. Thirdly, their evidence did not go so far as to
expressly confirm their commitment to undertaking the remedial work. In addition, their
relationship has been placed under severe strain by the problems they have encountered
with the property. This was likely to undermine their commitment to the remedial
works. The fact that Mr and Mrs Paxton now reside overseas is also likely to mean that
the plaintiffs would not commence the remedial work unless they could be sure that any
judgment they obtain against Mr and Mrs Paxton is likely to bear fruit.
[43] These factors led me to conclude that there was a realistic prospect that the
plaintiffs would use whatever funds they recover from this litigation to dispose of the
property and acquire alternative accommodation. In that event the plaintiffs' true loss
would be approximately $550,000, being the difference between the current market
value of the home that they have had to abandon and the value their property would have
had if it had been code compliant from the outset. An award of performance-based
damages in those circumstances would be inappropriate, because it would provide the
plaintiffs with a windfall profit of approximately $400,000.
[44] The issue ultimately became moot when counsel for the plaintiffs clarified his
clients’ position during closing submissions. He advised me that the plaintiffs do not
intend to carry out the remedial works. Instead, they propose to try to sell the property
and use the sale proceeds and the funds realised by this litigation to pay off their
mortgage. They will then divide any remaining balance between them and go their
separate ways.
[45] For that reason counsel for the plaintiffs appropriately confirmed that his clients
now sought damages on a diminution of value basis. They seek damages in respect of
the difference between the current value of the property and the value that it would have
had but for the defects that have been identified. The judgment sum must then be
reduced to reflect the cash payment that the plaintiffs are shortly to receive from the
other parties to this litigation. Given my earlier conclusion that the property has no
realistic value in its current state, I agree with this approach. As a consequence, I award
damages to the plaintiffs in the sum of $290,000.
17. General damages
[46] The plaintiffs have given extensive evidence as to the severe impact that the
issues giving rise to this proceeding have had on them since before they settled the
purchase of the property in December 2005. I accept their evidence on this issue
without reservation. The only factor that reduces the quantum of damages that
would otherwise be appropriate is the fact that the plaintiffs' evidence confirms that a
significant proportion of their stress and anxiety has been caused by their dealings
with the first defendant. Mr and Mrs Paxton should not be required to pay damages
in respect of anxiety and stress caused by the actions of another party. I consider an
appropriate award of general damages to be $15,000.00.
Costs
[47] The plaintiffs are entitled to costs on a Category 2B basis, together with
disbursements as fixed by the Registrar. The disbursements are to include the
reasonable costs incurred in engaging experts to provide them with advice and
evidence in relation to this proceeding.
Lang J
Solicitors:
Rainey Law, Auckland
18. APPENDIX 2 – BUILDING DEFECTS
CONSTRUCTION
DETAIL AND
LOCATION
DEPARTURES FROM
THE BUILDING
CONSENT
APPROVED
CONSTRUCTION
METHOD AND NON-
COMPLIANCE WITH
THE BUILDING CODE
DEFECT
Roofing A Zincalume Styleline
longrun roof was
installed not the Council
approved Coloursteel
longrun roof.
20 November 2010 -
DBH Determination at
page 20, paragraph
10.2.1.14
Breach of Building
Code Compliance
Document E2/AS1 of
July 2004.15
1. The roof installed is not a
marine grade product. It is
rusting at the base of sheets.
2. No wire mesh was installed to
provide support to the roofing
paper that underlies the roof.
3. Failure to provide suitable
stopends to the profile metal
roof sheets.
4. Failure to provide turn downs
to the profile metal roof
sheets at the junction with the
gutter.
Cladding Breach of the
Acceptable Solution
E2/AS1.
1. The cavity plywood cladding
system has been incorrectly
installed with a continuous
horizontal fixed batten at the
mid-point and at the base of
the cladding which prevents
ventilation and moisture
control.
2. The cladding has been
installed with insufficient
14
CBD Volume 1, Tab 49, pg 278
15
Evidence of Mr Gill at paragraph 120(a) and at CBD Volume 3
19. Insufficient clearance is
a breach of the
Acceptance Solution
E2/AS1 of the Building
Code.
Breach of the Building
Code E2/AS1 of July
2004.
Contrary to the
requirements of the
Compliance Document
E2/AS1.16
clearance at the junction with
the deck membrane, resulting
in potential for moisture
ingress from wicking up of
water.
3. The cladding has been
installed with insufficient
clearance at the junction with
the deck membrane, resulting
in potential for moisture
ingress from wicking up of
water.
4. The horizontal flashing at the
junction between the plywood
cladding sheets has:
5. The flashing has been
incorrectly penetrated with
nail fixings creating potential
moisture ingress points.
6. The copper horizontal
flashing installed between
sheets of plywood cladding is
in contact with the galvanised
back-flashings and corner
flashings. The two materials
are incompatible and corrode
each other.
7. The profile of the copper
horizontal sheet joint flashing
was not installed with the
minimum 15 degree fall
resulting in the junction
collecting moisture and being
prone to allowing water entry.
8. Building paper was installed
in contact with the rear face of
the plywood cladding.
Because the cladding cavity
system has been blocked by
the installation of horizontal
battens, moisture cannot exit
16
Evidence of Mr Gill at paragraph 118 and at CBD Volume 3, Tab 117 page 651
20. Contrary to the
recommendations of
the Acceptable Solution
E2/AS1 of July 2004.17
the cavity.
9. Failure to provide a suitable
support for the roof underlay.
Window joinery Breach of Building
Code Compliance
Document E2/AS1 of
July 2004.18
Breach of Building
Code Compliance
Document E2/AS1 of
July 2004.
1. The window head flashings
have not been installed with
suitable stop-ends.19
2. The head flashings have been
installed with excessive lap to
them causing a gap between
it and the window allowing a
moisture ingress pathway.
3. No jamb flashings have been
provided to the window units
resulting in moisture ingress
at the junction with the
horizontal copper sheet joint
flashings.
4. No air seals have been
provided to the windows,
creating a potential pathway
for moisture ingress
17
Evidence of Mr Gill at paragraph 126.
18
Evidence of Mr Gill at paragraph 103(b) and at CBD Volume 3, Tab 117 page 660
19
Evidence of Mr Gill at paragraphs 18 and 19 and at CBD Volume 2, Tab 61, pg 446 and 447