The document is an internship report submitted by Pranjal Singh Parihar, a 7th semester civil engineering student. It summarizes their 15-day internship spent observing construction of a multi-story residential building project called FCP Harmony in Nagpur, India. Over the course of the internship, the student learned about various aspects of construction including formwork setup, reinforcement, concrete mixing and placement, and curing. The report provides details on the companies overseeing construction, project specifications, tasks performed each day, and components and process of mivan formwork used for vertical surfaces.
The document is a summer internship report submitted by Sumit Singh detailing his internship from 09/06/2016 - 23/07/2016 with Skyline engineering contracts (India) pvt. Ltd. on a residential building project. The report includes details of the project such as building materials used including cement, sand, aggregates, reinforcement steel. It also describes the machinery used on site such as batching plants, concrete pumps, transit mixers etc. and procedures followed for demarcation, concrete casting of slabs and beams, staircase construction and brickwork.
This document discusses different types of concrete. It begins by explaining that concrete is composed of cement, fine aggregates like sand, and coarse aggregates mixed with water. It then describes several types of concrete including ordinary concrete, self-compacting concrete, reinforced cement concrete, precast concrete, prestressed concrete, and pervious concrete. For each type, it provides a brief definition and some of the key characteristics. The document focuses on explaining the composition and properties of different concretes used in construction.
This progress report summarizes construction activities for June 2011 on the COBE project. Major accomplishments included recovering lost schedule time, completing the lecture hall roof, and structural erection of building area A through the third floor. Challenges included design changes and coordination through BIM modeling. Work progressed on site utilities and infrastructure, the lecture hall exterior, and interior framing and systems in building areas A and B. Quality control efforts addressed previously undiscovered issues. Financial reports provided contract amounts and pending changes for owner approval.
Chapter 4 Construction Project Management. Lec 4.pptssuserb4074f
This document provides an overview of construction project management topics including:
1) Mobilization activities such as scheduling, organizing the work site, and staffing.
2) Monitoring and control techniques including cost control using cash flow diagrams, quality management, safety management, and environmental management.
3) Resource management and documentation/communication are also briefly mentioned but not described.
Mivan shuttering is an aluminum formwork system originally developed in Europe that allows for fast and economical construction of buildings through cast-in-place concrete. It involves erecting large room-sized aluminum forms for walls and slabs that are poured with concrete in a single continuous pour. This results in monolithic structures that require no plastering and can be constructed at a rate of one floor per week. While it has been widely used internationally and offers benefits like reduced costs and timelines, Mivan technology has not been extensively utilized in India but has potential to help achieve goals around affordable housing construction.
This document discusses prefabrication in construction. Prefabrication involves assembling components of a structure in a factory then transporting them to the construction site. It has advantages like reduced cost, time, and waste and allows work during poor weather. Common prefabricated components include columns, beams, waffle floors/roofs which are cast and cured off-site then erected using cranes. While prefabrication offers benefits, it also has disadvantages like potential breakage during transport and need for specialized equipment and labor. The document concludes that partial prefabrication is well-suited for Indian conditions.
No fine concrete. or pervious concreteDigant Patel
The document discusses no fines concrete, also called porous concrete or permeable concrete. It provides information on the student's name and department, then defines no fines concrete as a type of concrete with high porosity that allows water to pass through, reducing runoff. No fines concrete consists of cement, a single size of coarse aggregate, and water, without fine aggregates. It has a void content of 30-40% and strengths from 3.5-28 MPa depending on ratios and compaction. No fines concrete has benefits for water management, land development, and mitigating pollution while reducing heat islands. Regular cleaning is needed to maintain permeability.
The document is a summer internship report submitted by Sumit Singh detailing his internship from 09/06/2016 - 23/07/2016 with Skyline engineering contracts (India) pvt. Ltd. on a residential building project. The report includes details of the project such as building materials used including cement, sand, aggregates, reinforcement steel. It also describes the machinery used on site such as batching plants, concrete pumps, transit mixers etc. and procedures followed for demarcation, concrete casting of slabs and beams, staircase construction and brickwork.
This document discusses different types of concrete. It begins by explaining that concrete is composed of cement, fine aggregates like sand, and coarse aggregates mixed with water. It then describes several types of concrete including ordinary concrete, self-compacting concrete, reinforced cement concrete, precast concrete, prestressed concrete, and pervious concrete. For each type, it provides a brief definition and some of the key characteristics. The document focuses on explaining the composition and properties of different concretes used in construction.
This progress report summarizes construction activities for June 2011 on the COBE project. Major accomplishments included recovering lost schedule time, completing the lecture hall roof, and structural erection of building area A through the third floor. Challenges included design changes and coordination through BIM modeling. Work progressed on site utilities and infrastructure, the lecture hall exterior, and interior framing and systems in building areas A and B. Quality control efforts addressed previously undiscovered issues. Financial reports provided contract amounts and pending changes for owner approval.
Chapter 4 Construction Project Management. Lec 4.pptssuserb4074f
This document provides an overview of construction project management topics including:
1) Mobilization activities such as scheduling, organizing the work site, and staffing.
2) Monitoring and control techniques including cost control using cash flow diagrams, quality management, safety management, and environmental management.
3) Resource management and documentation/communication are also briefly mentioned but not described.
Mivan shuttering is an aluminum formwork system originally developed in Europe that allows for fast and economical construction of buildings through cast-in-place concrete. It involves erecting large room-sized aluminum forms for walls and slabs that are poured with concrete in a single continuous pour. This results in monolithic structures that require no plastering and can be constructed at a rate of one floor per week. While it has been widely used internationally and offers benefits like reduced costs and timelines, Mivan technology has not been extensively utilized in India but has potential to help achieve goals around affordable housing construction.
This document discusses prefabrication in construction. Prefabrication involves assembling components of a structure in a factory then transporting them to the construction site. It has advantages like reduced cost, time, and waste and allows work during poor weather. Common prefabricated components include columns, beams, waffle floors/roofs which are cast and cured off-site then erected using cranes. While prefabrication offers benefits, it also has disadvantages like potential breakage during transport and need for specialized equipment and labor. The document concludes that partial prefabrication is well-suited for Indian conditions.
No fine concrete. or pervious concreteDigant Patel
The document discusses no fines concrete, also called porous concrete or permeable concrete. It provides information on the student's name and department, then defines no fines concrete as a type of concrete with high porosity that allows water to pass through, reducing runoff. No fines concrete consists of cement, a single size of coarse aggregate, and water, without fine aggregates. It has a void content of 30-40% and strengths from 3.5-28 MPa depending on ratios and compaction. No fines concrete has benefits for water management, land development, and mitigating pollution while reducing heat islands. Regular cleaning is needed to maintain permeability.
A UHPC (ultra high performance concrete) presentation projects.Nolan Mayrhofer
UHPC presentation featuring select international Ductal projects. This is an in depth look at the types of architectural projects UHPC is best suited for.
Prefabrication involves assembling building components in a factory and transporting them to the construction site. There are several prefabrication systems including open prefab, box type, and large prefab. Prefabricated components include panels, roofs, floors, and more which are manufactured off-site and assembled on-site. Prefabrication offers benefits like reduced construction time and costs, improved quality, and less waste. However, it also has disadvantages such as requiring specialized equipment and skilled labor for transportation and assembly. A case study on a housing project in India demonstrated how prefabrication helped complete buildings faster and with higher quality.
Ppt summer presentation on finishing Of Police Station Construction SiteAlok Mishra
finishing Works at Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
The strength of a material is defined as the ability to resist stress without failure.
It is important to note that High strength and High-performance concrete are not synonymous.
Concrete is defined as High strength concrete on the basis of its compressive strength measured at a given age.
In early 1970’s any concrete mixture that showed 40MPa or more compressive strength at 28 days were design as High strength concrete.
Later 60-100MPa concrete mixture was commercially developed and used in the construction of high rise buildings and long-span bridges in many parts of the world.
Pile foundations Case Study Delhi Metro Site VisitMohd Kashif
This document provides information about deep foundations, including what they are, where they are used, how they are classified, and examples of different pile types. It defines deep foundations as transferring loads to deeper layers of soil or rock compared to shallow foundations. It classifies piles based on function and material and provides details on common types like timber, concrete, steel, and composite piles. The document also includes a case study describing the construction of drilled shaft pile foundations for a metro station in Delhi, with steps like drilling, stabilizing holes, and pouring concrete.
Autoclaved aerated concrete (AAC) block is a building material made of Portland cement, fine aggregates (fly ash or sand), water and an expansion agent in an autoclaving process heated under pressure which results in the production of air voids in the material, making it less dense, easy to cut/mould and better insulating
This document provides information on diaphragm walls, including:
- Diaphragm walls are reinforced concrete walls constructed using the slurry trench technique, reaching depths of up to 50m.
- They are commonly used as retaining walls, for supporting deep excavations, and as basement or underground structure walls.
- Construction involves excavating trenches using bentonite slurry, installing reinforcement cages, and pouring concrete to form wall panels either successively or alternately.
- Proper specifications are required for bentonite slurry, reinforcement, and construction methods to ensure continuity and water-tightness of the completed diaphragm wall structure.
This document discusses rice husk ash based geopolymer concrete. Geopolymer concrete is an alternative to traditional cement-based concrete that uses industrial byproducts like rice husk ash instead of cement. It has lower CO2 emissions and improved properties like chemical resistance. The document outlines how rice husk ash can be used as a source material in geopolymer concrete production due to its pozzolanic properties. Experimental results show rice husk ash improves strength and corrosion resistance of geopolymer concrete. While more expensive than traditional concrete, geopolymer concrete offers sustainability benefits and rice husk ash utilization provides an outlet for a waste product.
This document provides guidelines for designing columns, including three important thumb rules: 1) The size of columns should be no less than 9"x9" for a single story structure and larger for taller structures; 2) The distance between columns should not exceed 4m for 9"x9" columns and larger columns are needed for greater distances; 3) Columns should be aligned in straight lines or a grid to avoid structural issues. It emphasizes the importance of following these rules to prevent disastrous mistakes by engineers that could compromise safety and cost lives.
The construction industry consists of building infrastructure projects like buildings, roads, bridges, ports, and power systems. It is a major contributor to GDP and employment. Construction requires effective planning and coordination to consider factors like costs, scheduling, safety, and environmental impacts. The demand for construction is dependent on interest rates, financing availability, and government investment. The industry faces challenges like rising costs and stalled projects. However, increased government spending on infrastructure and policy changes are expected to benefit major construction companies and drive growth in the industry over the next few years.
civil enginnering industrial training report KRISHNA MURARI
This document provides a report on Krishna Murari Kandu's industrial training at the Vinod Nagar Station Yard project of Delhi Metro Rail Corporation Ltd. It discusses the construction of the double deck stabling yard including piling, pile caps, piers and the boundary wall. It also describes the bar bending schedule process and various tests performed at the site and in the lab, including tests on bentonite, slump tests, and concrete cube tests. The training helped provide an overview of the construction process and quality control measures for a metro rail project.
Shear walls are vertical reinforced concrete walls that resist lateral forces like wind and earthquakes. They provide strength and stiffness to control lateral building movement. Shear walls are classified into different types including simple rectangular, coupled, rigid frame, framed with infill, column supported, and core type walls. Design of shear walls involves reviewing the building layout, determining loads, estimating earthquake forces, analyzing the structural system, and designing for flexural and shear strengths with proper reinforcement detailing. The behavior of shear walls under seismic loading depends on their height to width ratio, with squat walls experiencing more shear deformation and slender walls undergoing primarily bending deformation.
This internship summary provides an overview of an internship at a structural design firm. The internship objectives were to become familiar with the workflow of structural design, bridge the gap between academic and industrial knowledge, and understand real-world design assumptions. The intern performed tasks like analyzing and designing structural elements manually and using software, modeled projects in ETABS, and assisted with drafting detailing drawings. Overall, the internship provided both technical skills in structural design and analysis and non-technical skills such as teamwork, communication, and time management.
Chandan Singh is a structural design engineer with over 6 years of experience in conceptual design, detailed design, analysis, and construction engineering of temporary and permanent steel structures. He has extensive experience designing launching girders and ground supported erection systems for various metro and bridge projects across India. Some of the key projects he has worked on include the Jaipur Metro, Hyderabad Metro, DMRC Yamuna Bridge, and several projects for the Bangalore and Kolkata Metro.
This document discusses construction project management and cost reduction techniques. It explains that construction project management aims to control time, cost, and quality of large, complex construction projects. However, many projects experience issues like cost overruns, delays, and conflicts. The document then outlines various cost reduction techniques that can be used, including value engineering, material management, budgetary control, and cost optimization methods. It emphasizes applying these techniques through a multidisciplinary approach to improve value and economy without compromising quality or requirements.
This document discusses materials for low-cost housing construction in India. It describes natural materials like bamboo, earth, straw and fiber cement that are locally available and affordable. It also discusses man-made materials like fly ash, aerocon panels, cement hollow blocks and rice husks that can be used. These alternative materials allow for reduced construction costs through local sourcing and efficient designs while maintaining structural integrity. The document concludes that widespread use of these sustainable low-cost materials could address housing shortages by lowering material costs.
The document discusses reinforced cement concrete (RCC), including its history, materials, specifications, and advantages/disadvantages. RCC uses steel reinforcement embedded in concrete to resist tensile, shear, and sometimes compressive stresses. François Coignet is considered a pioneer of RCC, building the first reinforced concrete structure in 1853. Proper proportions and mixing of cement, aggregates like sand and gravel, and water are needed to produce durable concrete. Precast concrete involves casting pieces off-site then transporting them for assembly.
The document discusses Total Quality Management (TQM) in construction. It provides an overview of TQM, including its basis in satisfying customer needs through continuous improvement. TQM builds on systems theory by emphasizing managing cross-functional processes and contributions from all individuals. The key elements of TQM include employee involvement, continuous improvement, measurement of quality and performance, and viewing the organization as part of a supply chain with customers and suppliers providing feedback. The document also reviews quality management writers and modern construction management concepts, as well as quality system standards and assurance.
This document discusses several special concreting techniques:
- Pumped concrete is concrete that can be pushed through a pipeline and must have a design that prevents blockages.
- Shortcrete or gunite is a mortar or fine concrete pneumatically projected at high velocity, used for thin sections with less formwork.
- Underwater concrete requires special mixes placed via bagging, buckets, tremie pipes, or grouted aggregates to prevent water intrusion.
- Other techniques include pre-packed concrete placed underwater and special considerations for hot/cold weather concreting. Proper mix design and placement methods are essential for successful implementation of special concreting applications.
The document summarizes an internship report submitted by Naveen Kumar for his summer internship with Larsen & Toubro Construction from June 23rd to July 22nd 2016. It provides details of the Barapullah elevated corridor project being constructed by L&T from Sarai Kale Khan to Mayur Vihar Phase 1, including project parameters, departments involved, construction methodology, safety measures, and equipment used. It also acknowledges the support received from the internship guide and L&T staff during the training period.
The document is an internship report on Bharat Pride Park, a residential and commercial development project in Kalaburagi, India. It provides details about the project, including an overview of the consulting firm and the intern's responsibilities. The internship involved taking measurements to calculate quantities of materials, interpreting drawings, and assisting engineers and supervisors. The intern gained experience in construction processes and project documentation during the one-month internship.
A UHPC (ultra high performance concrete) presentation projects.Nolan Mayrhofer
UHPC presentation featuring select international Ductal projects. This is an in depth look at the types of architectural projects UHPC is best suited for.
Prefabrication involves assembling building components in a factory and transporting them to the construction site. There are several prefabrication systems including open prefab, box type, and large prefab. Prefabricated components include panels, roofs, floors, and more which are manufactured off-site and assembled on-site. Prefabrication offers benefits like reduced construction time and costs, improved quality, and less waste. However, it also has disadvantages such as requiring specialized equipment and skilled labor for transportation and assembly. A case study on a housing project in India demonstrated how prefabrication helped complete buildings faster and with higher quality.
Ppt summer presentation on finishing Of Police Station Construction SiteAlok Mishra
finishing Works at Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
The strength of a material is defined as the ability to resist stress without failure.
It is important to note that High strength and High-performance concrete are not synonymous.
Concrete is defined as High strength concrete on the basis of its compressive strength measured at a given age.
In early 1970’s any concrete mixture that showed 40MPa or more compressive strength at 28 days were design as High strength concrete.
Later 60-100MPa concrete mixture was commercially developed and used in the construction of high rise buildings and long-span bridges in many parts of the world.
Pile foundations Case Study Delhi Metro Site VisitMohd Kashif
This document provides information about deep foundations, including what they are, where they are used, how they are classified, and examples of different pile types. It defines deep foundations as transferring loads to deeper layers of soil or rock compared to shallow foundations. It classifies piles based on function and material and provides details on common types like timber, concrete, steel, and composite piles. The document also includes a case study describing the construction of drilled shaft pile foundations for a metro station in Delhi, with steps like drilling, stabilizing holes, and pouring concrete.
Autoclaved aerated concrete (AAC) block is a building material made of Portland cement, fine aggregates (fly ash or sand), water and an expansion agent in an autoclaving process heated under pressure which results in the production of air voids in the material, making it less dense, easy to cut/mould and better insulating
This document provides information on diaphragm walls, including:
- Diaphragm walls are reinforced concrete walls constructed using the slurry trench technique, reaching depths of up to 50m.
- They are commonly used as retaining walls, for supporting deep excavations, and as basement or underground structure walls.
- Construction involves excavating trenches using bentonite slurry, installing reinforcement cages, and pouring concrete to form wall panels either successively or alternately.
- Proper specifications are required for bentonite slurry, reinforcement, and construction methods to ensure continuity and water-tightness of the completed diaphragm wall structure.
This document discusses rice husk ash based geopolymer concrete. Geopolymer concrete is an alternative to traditional cement-based concrete that uses industrial byproducts like rice husk ash instead of cement. It has lower CO2 emissions and improved properties like chemical resistance. The document outlines how rice husk ash can be used as a source material in geopolymer concrete production due to its pozzolanic properties. Experimental results show rice husk ash improves strength and corrosion resistance of geopolymer concrete. While more expensive than traditional concrete, geopolymer concrete offers sustainability benefits and rice husk ash utilization provides an outlet for a waste product.
This document provides guidelines for designing columns, including three important thumb rules: 1) The size of columns should be no less than 9"x9" for a single story structure and larger for taller structures; 2) The distance between columns should not exceed 4m for 9"x9" columns and larger columns are needed for greater distances; 3) Columns should be aligned in straight lines or a grid to avoid structural issues. It emphasizes the importance of following these rules to prevent disastrous mistakes by engineers that could compromise safety and cost lives.
The construction industry consists of building infrastructure projects like buildings, roads, bridges, ports, and power systems. It is a major contributor to GDP and employment. Construction requires effective planning and coordination to consider factors like costs, scheduling, safety, and environmental impacts. The demand for construction is dependent on interest rates, financing availability, and government investment. The industry faces challenges like rising costs and stalled projects. However, increased government spending on infrastructure and policy changes are expected to benefit major construction companies and drive growth in the industry over the next few years.
civil enginnering industrial training report KRISHNA MURARI
This document provides a report on Krishna Murari Kandu's industrial training at the Vinod Nagar Station Yard project of Delhi Metro Rail Corporation Ltd. It discusses the construction of the double deck stabling yard including piling, pile caps, piers and the boundary wall. It also describes the bar bending schedule process and various tests performed at the site and in the lab, including tests on bentonite, slump tests, and concrete cube tests. The training helped provide an overview of the construction process and quality control measures for a metro rail project.
Shear walls are vertical reinforced concrete walls that resist lateral forces like wind and earthquakes. They provide strength and stiffness to control lateral building movement. Shear walls are classified into different types including simple rectangular, coupled, rigid frame, framed with infill, column supported, and core type walls. Design of shear walls involves reviewing the building layout, determining loads, estimating earthquake forces, analyzing the structural system, and designing for flexural and shear strengths with proper reinforcement detailing. The behavior of shear walls under seismic loading depends on their height to width ratio, with squat walls experiencing more shear deformation and slender walls undergoing primarily bending deformation.
This internship summary provides an overview of an internship at a structural design firm. The internship objectives were to become familiar with the workflow of structural design, bridge the gap between academic and industrial knowledge, and understand real-world design assumptions. The intern performed tasks like analyzing and designing structural elements manually and using software, modeled projects in ETABS, and assisted with drafting detailing drawings. Overall, the internship provided both technical skills in structural design and analysis and non-technical skills such as teamwork, communication, and time management.
Chandan Singh is a structural design engineer with over 6 years of experience in conceptual design, detailed design, analysis, and construction engineering of temporary and permanent steel structures. He has extensive experience designing launching girders and ground supported erection systems for various metro and bridge projects across India. Some of the key projects he has worked on include the Jaipur Metro, Hyderabad Metro, DMRC Yamuna Bridge, and several projects for the Bangalore and Kolkata Metro.
This document discusses construction project management and cost reduction techniques. It explains that construction project management aims to control time, cost, and quality of large, complex construction projects. However, many projects experience issues like cost overruns, delays, and conflicts. The document then outlines various cost reduction techniques that can be used, including value engineering, material management, budgetary control, and cost optimization methods. It emphasizes applying these techniques through a multidisciplinary approach to improve value and economy without compromising quality or requirements.
This document discusses materials for low-cost housing construction in India. It describes natural materials like bamboo, earth, straw and fiber cement that are locally available and affordable. It also discusses man-made materials like fly ash, aerocon panels, cement hollow blocks and rice husks that can be used. These alternative materials allow for reduced construction costs through local sourcing and efficient designs while maintaining structural integrity. The document concludes that widespread use of these sustainable low-cost materials could address housing shortages by lowering material costs.
The document discusses reinforced cement concrete (RCC), including its history, materials, specifications, and advantages/disadvantages. RCC uses steel reinforcement embedded in concrete to resist tensile, shear, and sometimes compressive stresses. François Coignet is considered a pioneer of RCC, building the first reinforced concrete structure in 1853. Proper proportions and mixing of cement, aggregates like sand and gravel, and water are needed to produce durable concrete. Precast concrete involves casting pieces off-site then transporting them for assembly.
The document discusses Total Quality Management (TQM) in construction. It provides an overview of TQM, including its basis in satisfying customer needs through continuous improvement. TQM builds on systems theory by emphasizing managing cross-functional processes and contributions from all individuals. The key elements of TQM include employee involvement, continuous improvement, measurement of quality and performance, and viewing the organization as part of a supply chain with customers and suppliers providing feedback. The document also reviews quality management writers and modern construction management concepts, as well as quality system standards and assurance.
This document discusses several special concreting techniques:
- Pumped concrete is concrete that can be pushed through a pipeline and must have a design that prevents blockages.
- Shortcrete or gunite is a mortar or fine concrete pneumatically projected at high velocity, used for thin sections with less formwork.
- Underwater concrete requires special mixes placed via bagging, buckets, tremie pipes, or grouted aggregates to prevent water intrusion.
- Other techniques include pre-packed concrete placed underwater and special considerations for hot/cold weather concreting. Proper mix design and placement methods are essential for successful implementation of special concreting applications.
The document summarizes an internship report submitted by Naveen Kumar for his summer internship with Larsen & Toubro Construction from June 23rd to July 22nd 2016. It provides details of the Barapullah elevated corridor project being constructed by L&T from Sarai Kale Khan to Mayur Vihar Phase 1, including project parameters, departments involved, construction methodology, safety measures, and equipment used. It also acknowledges the support received from the internship guide and L&T staff during the training period.
The document is an internship report on Bharat Pride Park, a residential and commercial development project in Kalaburagi, India. It provides details about the project, including an overview of the consulting firm and the intern's responsibilities. The internship involved taking measurements to calculate quantities of materials, interpreting drawings, and assisting engineers and supervisors. The intern gained experience in construction processes and project documentation during the one-month internship.
recruitment and selection policy of reliancebunnysharma
This document provides details about Neha Goyal's summer training project on the recruitment and selection policies of Reliance Infrastructure Ltd. It includes an introduction, company profile describing Reliance Infrastructure and its business segments, and sections on the project profile describing the recruitment and selection process, market analysis, SWOT analysis, and research methodology for the project. The project was undertaken as a partial fulfillment of the BBM program at IIS University under the guidance of Vandana ma'am.
RECRUITMENT & SELECTION POLICIES OF RELIANCE By Jai Rane.pdfVikas Gupta
Reliance Infrastructure Ltd. has recruitment and selection policies to fill vacancies that arise from staffing changes, work requirement changes, or new projects. The process involves identifying vacancies, reviewing position needs, setting budgets, and creating job descriptions with HR and department heads. Reliance recruits both internally through promotions, transfers, and externally through campus recruitment primarily at top engineering and management institutes across India relevant to project locations and needs.
The document provides details about a training report submitted by Lakshit Joshi for their Bachelor of Technology degree. It includes information such as an introduction to the commercial building construction site project, the various companies involved including the general contractor and structural designer, and an overview of the 8+2 floor commercial building being constructed.
The document provides details about Ravi Kumar Oruganti's resume. It includes information about his educational qualifications, 23 years of work experience in the construction industry, technical skills, and details of 15 work experience entries from 1994 to present. His most recent role was as Deputy General Manager with Viraj Projects from 2016 to present, overseeing residential construction projects in Bangalore for Brigade Enterprises and Vaswani Estate Developers.
The document discusses a study conducted to analyze the effectiveness of employee trainings at TATA HITACHI CONSTRUCTION MACHINERY PVT. LTD. using the Kirkpatrick model. Data was collected through questionnaires given to training participants and their supervisors to assess any changes in on-the-job behavior and performance. The study aimed to identify areas of improvement and enhance future training programs. Analysis was done department-wise to evaluate pre- and post-training employee performance and determine if knowledge from trainings was applied on the job.
full details about building construction & process karthikachanta1
This document provides an internship review report from six students who interned at Vishwanadh Avenues India Pvt. Ltd. It includes an abstract, introduction to the internship (FSI), objectives and benefits. It also details the company profile, projects worked on, tasks completed by the interns such as material estimations and construction supervision. Building materials and construction methodology are described. The report concludes with overall gains from the internship experience.
At present scenario, productivity and economics of machining work pieces in large
quantity is greatly affected by use of work holding devices like fixture. To achieve
require accuracy with reduced rework and easy handling, fixtures are provided. This
project is about designing the fixture for pressing bearing inside the crank case. For
this purpose of designing and analysing the modelling software known as solid works is
to be used. The fixture is design mainly to get multiple bearing pressed on crank case
while keeping it stable and to get the accuracy of press within tolerance limit.
This document is a project report submitted by Ch. Rakesh Kumar Patro on the social media marketing strategy of The Accurates company. It includes an introduction to The Accurates, an industry profile of the construction sector in India, and covers topics like the company profile, product portfolio, analysis and interpretation of findings, recommendations, and conclusion. The report was submitted as part fulfillment of a post graduate diploma in management from Indus Business Academy.
This document is a project report submitted by Devi Narasimha Rao for the partial fulfillment of the requirement for a Masters in Business Administration. The report examines the working capital management of Vishwa Infrastructures & Services Private Limited, an infrastructure company in India. The report includes an introduction to the company, the construction industry in India, objectives of the study, research methodology, analysis of working capital management and ratios, findings, and suggestions.
The document is a summer internship report submitted by Sunil Kumar detailing his internship from July 6th to July 15th, 2017 at the L&T-SUCG JV Delhi construction site for Phase 3 of the Delhi Metro Rail project. The report provides an overview of the organizations involved in the project (L&T, DMRC, SUCG), safety policies, construction methodology used at the Vasant Vihar metro station site, and details of the internship activities including tunneling, shaft construction, and batching plant operations.
The document discusses engineering and infrastructure development in India. It begins by paying tribute to M. Visvesvaraya and his contributions to economic planning in India. It then notes that large-scale infrastructure development is needed for socioeconomic upliftment, and that the government has allocated funds for this purpose. Some challenges engineers face are a lack of managerial skills training and many pursuing IT instead of core engineering. The author shares their experiences innovating as an engineer in India. They conclude that India has a legacy of quality engineering and encourage the students to work hard and be innovative.
The document is a curriculum vitae for Ramachary Manivannan applying for a position as a Project Manager. It details his 35 years of experience in project management and construction management across various countries. It provides information on his educational qualifications and outlines several high profile projects he has worked on in India and abroad worth billions of dollars. The CV emphasizes his leadership, communication, problem-solving, and time management skills gained over his long career in the construction industry.
This document provides information about a proposed new management complex building for the Department and Faculty of Management at Aligarh Muslim University (AMU) in India. It discusses the brief history of management education at AMU, outlines the key developments and constraints related to the current department, and describes plans for the new complex building. These include selecting an architect, allocating land, forming committees, and fundraising campaigns among alumni worldwide to support the project. The new building aims to provide world-class facilities to help the department become a leading management institute.
This document provides a company profile for Asia Bridge Limited, an infrastructure development firm based in Singapore. It outlines Asia Bridge's history and capabilities in areas such as project management, financing, and delivering projects across sectors including buildings, transportation, utilities and more. The profile also lists several example infrastructure projects Asia Bridge has worked on in countries around Asia and details the experience and roles of key members of Asia Bridge's team.
1. The document describes an industrial training report submitted by Love Kothari at Consagous Technologies Pvt Ltd in Indore, India.
2. The report provides details of the project including the site location, map, developer information, and safety measures implemented.
3. Key aspects studied were the structure details, page layout process, search engine optimization techniques, and use of social bookmarking and Facebook advertising.
This document summarizes Susom Dutta's internship report from his summer internship in 2014 with Larsen & Toubro Construction's Buildings & Factories division in Kolkata. The report provides an introduction to Larsen & Toubro, including its vision, policies, and the Atmosphere residential project in Kolkata that Dutta worked on. It describes his orientation, training in areas like safety and project management, and responsibilities during the execution of the project like surveys, formwork, and use of plant and machinery. Dutta concludes the report by reflecting on what he learned during the internship experience.
This document provides a summary of a training report submitted by Divesh Sharma at the Himachal Pradesh Public Works Department in India from June 15th to July 30th. It discusses the construction site of a building for the Indira Gandhi Medical College Outpatient Department. It acknowledges those who supported the training and provides an index of topics covered in the report, including introductions to the Central Public Works Department of India and the construction site location, as well as discussions of formwork, planning, construction sequencing, project monitoring, quality, and conclusions.
Similar to Internship file for summer training (20)
Generative AI Use cases applications solutions and implementation.pdfmahaffeycheryld
Generative AI solutions encompass a range of capabilities from content creation to complex problem-solving across industries. Implementing generative AI involves identifying specific business needs, developing tailored AI models using techniques like GANs and VAEs, and integrating these models into existing workflows. Data quality and continuous model refinement are crucial for effective implementation. Businesses must also consider ethical implications and ensure transparency in AI decision-making. Generative AI's implementation aims to enhance efficiency, creativity, and innovation by leveraging autonomous generation and sophisticated learning algorithms to meet diverse business challenges.
https://www.leewayhertz.com/generative-ai-use-cases-and-applications/
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...shadow0702a
This document serves as a comprehensive step-by-step guide on how to effectively use PyCharm for remote debugging of the Windows Subsystem for Linux (WSL) on a local Windows machine. It meticulously outlines several critical steps in the process, starting with the crucial task of enabling permissions, followed by the installation and configuration of WSL.
The guide then proceeds to explain how to set up the SSH service within the WSL environment, an integral part of the process. Alongside this, it also provides detailed instructions on how to modify the inbound rules of the Windows firewall to facilitate the process, ensuring that there are no connectivity issues that could potentially hinder the debugging process.
The document further emphasizes on the importance of checking the connection between the Windows and WSL environments, providing instructions on how to ensure that the connection is optimal and ready for remote debugging.
It also offers an in-depth guide on how to configure the WSL interpreter and files within the PyCharm environment. This is essential for ensuring that the debugging process is set up correctly and that the program can be run effectively within the WSL terminal.
Additionally, the document provides guidance on how to set up breakpoints for debugging, a fundamental aspect of the debugging process which allows the developer to stop the execution of their code at certain points and inspect their program at those stages.
Finally, the document concludes by providing a link to a reference blog. This blog offers additional information and guidance on configuring the remote Python interpreter in PyCharm, providing the reader with a well-rounded understanding of the process.
Build the Next Generation of Apps with the Einstein 1 Platform.
Rejoignez Philippe Ozil pour une session de workshops qui vous guidera à travers les détails de la plateforme Einstein 1, l'importance des données pour la création d'applications d'intelligence artificielle et les différents outils et technologies que Salesforce propose pour vous apporter tous les bénéfices de l'IA.
Software Engineering and Project Management - Software Testing + Agile Method...Prakhyath Rai
Software Testing: A Strategic Approach to Software Testing, Strategic Issues, Test Strategies for Conventional Software, Test Strategies for Object -Oriented Software, Validation Testing, System Testing, The Art of Debugging.
Agile Methodology: Before Agile – Waterfall, Agile Development.
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Sinan KOZAK
Sinan from the Delivery Hero mobile infrastructure engineering team shares a deep dive into performance acceleration with Gradle build cache optimizations. Sinan shares their journey into solving complex build-cache problems that affect Gradle builds. By understanding the challenges and solutions found in our journey, we aim to demonstrate the possibilities for faster builds. The case study reveals how overlapping outputs and cache misconfigurations led to significant increases in build times, especially as the project scaled up with numerous modules using Paparazzi tests. The journey from diagnosing to defeating cache issues offers invaluable lessons on maintaining cache integrity without sacrificing functionality.
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
1. INTERNSHIP REPORT
ON
MULTISTOREY RESIDENTIAL
BUILDING CONSTRUCTION
(29-08-2023 TO 12-09-2023)
TAKEN AT
NAGPUR INTEGRATED TOWNSHIP
PVT. LTD.
PLOT NO. 2, SECTOR-21, MIHAN, DE-NOTIFIED SEZ,
KHAPRI(RLY), NAGPUR RURAL 441108,(M.H.)
SUBMITTED TO:- SUBMITTED BY:-
Prof. RAJESH CHAUHAN SIR PRANJAL SINGH PARIHAR
HEAD OF DEPARTMENT B.E. VIITH
SEMESTER
CIVIL ENGINEERING CIVIL ENGINEERING
ROLL NO.:- 20302013
ENROLLMENT NO.:- V20R538290001
SCHOOL OF ENGINEERING & TECHNOLOGY
VIKRAM UNIVERSITY
UJJAIN (M.P.) 456010
SESSION:- (2023-2024)
2.
3. SCHOOL OF ENGINEERING & TECHNOLOGY
VIKRAM UNIVERSITY
UJJAIN (M.P.)
SESSION:- (2023-2024)
CERTIFICATE
This is to certify that the report of internship entitled “ MULTISTOREY
RESIDENTIAL BUILDING CONSTRUCTION” submitted to Head of
department, Civil Engineering, School of Engineering & Technology, Vikram
University, Ujjain (M.P.) by Pranjal Singh Parihar, B.E. VIIth
Sem, Civil
Engineering, required for the fulfilment of practical and viva voice of
internship.
INTERNAL EXAMINER EXTERNAL EXAMINER
4. ACKNOWLEDGEMENT
I take this opportunity to extend my gratitude to IJM INDIA
INFRASTRUCTURE PVT. LTD. as well as TEAM UNIVERSAL INFRATECH
PVT. LTD for providing me an unbelievable practical learning experience
during the internship. It was indeed to be a pleasure to be part of such
organization for 15 days.
First and foremost, I would like to thank Mr. VIDYA SAGAR INJETI,
Project Manager, NITPL( for IJM INFRASTRUCTURE) and special
thanks to Mr. MAHESH DESAI, Project Manager (for TEAM
UNIVERSAL) and Mr. TEJRAM GOSWAMI, Engineer – Projects, and all
others site engineer and lab engineer, who supported and helped me
throughout the internship and for giving me nice industrial experience.
Secondly, I am no less grateful to other employees and members of the
department for their kind co-operation and spontaneous response.
Last but not the least, I express my gratitude towards my college faculty
Prof. Rajesh Chauhan Sir (HOD), Prof. Sachin Sironiya Sir, Prof.
Chetan Gurjar Sir, Prof. Mohit Prajapati Sir as their guidance is never
forgettable and for sharing their knowledge, helping me and gave me
inspiration to complete the internship program successfully.
PRANJAL SINGH PARIHAR
B.E. VIITH
SEM
CIVIL ENGINEERING
5. ABSTRACT
The internship program is designed to provide students engaged in a
field experience within opportunity to share their insight, to explore the
links between students’ academic preparation and their field work, and to
assist participants in developing and carrying out the major research
project which will serve culminate their internship experience.
An internship is a period of work experience offered by an organization
for a limited period of time. Once confined to medical graduates, the term
is now used for wide range of placements in business, non-profit
organization and government agencies. They are undertaken by students
and graduates looking to gain relevant skills and experience in a particular
field. Employers benefit from these placements because they often recruit
employees from their interns, who have known capabilities, thus saving
time and money in the long run.
Typically, an internship consists of an exchange of service for experience
between the intern and the organization. Internship are used to
determine if the interns still have an interest in that field after the real-life
experience. In addition, an internship can be used to create a professional
network that can assist with letters of recommendation or lead to future
employment opportunities. The benefit of brining an intern into full-time
employment is that they are already with the company, their position, and
they typically need to no training.
6. COMPANY PROFILE
IJM INDIA INFRASTRUCTURE PVT. LTD
IJM (India) Infrastructure Limited (IJMII) is a subsidiary company of IJM
Corporation Berhad, with its Group Headquarters at Kuala Lumpur, Malaysia.
It is one of the world's leading companies in infrastructure, construction,
property, plantation and industry for the last 38 years of operations.
IJMII, incorporated in 1998, is a pioneer in highway infrastructure, commercial
and residential construction with its India operations headquartered at
Hyderabad. IJMII has been delivering one sterling performance after another
in its operations in India and has many firsts to its credit.
IJMII has Extensive experience in Highways & Bridges and Properities:
• Built over 5500 lane Km(1500+ Route Kms) of highways and 20Km of
urban rail projects.
• 20.2 Million Sq.ft of Prime Residential/Commercial developemnt.
IJMII has been actively participating in the high growth opportunities offered
by Indian Infrastructure Industry, more specifically in the construction sector.
IJMII's main thrust is in construction and upgrading of highways and property
development including world class townships and commercial buildings using
modern technology and equipment.
IJMII completed India's first flagship Expressway Project - The Mumbai Pune
Expressway from Kon to Chowk in April 2000. One of the more recent projects
7. completed by IJMII in 2020 is the Dewas Bypass Road Project (Madhya
Pradesh).
IJMII has also delivered world-class integrated townships including Rain tree
Park (Malaysian Township) Kukatpally,Hyderabad, Raintree Park Dwaraka
Krishna Township Phase 1, in Mangalagiri, Guntur. First City Residential
Township Project, Nagpur is currently underway.
The Group Company IJM Corporation Berhad, whose core competency is
construction, is one of Malaysia's largest and most diversified construction
groups, with world-wide presence with specialization in the areas of
construction, property development, manufacturing, quarrying, plantation
and international ventures. Its current operations are spread over Malaysia,
India, Australia, Argentina, Chile, China, Myanmar, Singapore and Vietnam.
IJM is a highly quality conscious company with the motto of "Excellence
Through Quality".
TEAM UNIVERSAL INFRATECH PVT. LTD (An IJM Group
Company)
8. Team group emerged in the year 2007 to provide services to construction &
infrastructure industry. We are a team of Exceptional Engineers and Managers, who
believe in constantly pushing limits and delighting our clients with our exceptional
delivery capabilities and state of the art technology.
Since inception we are involved in building Commercial, Residential complex, Housing,
Roads, Railways, Airports. We don´t consider construction as just a business, but we
provide professional Service with Passion.
Today, the Team Group keep exploring new horizons in infrastructure development,
housing, townships, real estate development & turnkey construction services.
The professional individuals has grouped under flagship of Team Universal having
registered office at Hyderabad, India, consists team of multicultural, multifaceted &
versatile committed individuals & advisors who share core values & are highly focused
on leveraging their complementary skills for the benefit of clients.
The Team is capable of handling multiple projects, uniquely complex, with passion to
excel. We are on the way to achieve our bold vision of being among top service
providers in construction industry within next three-five years.
Quality has been our prime objective all through and it will remain as we believe in
long term relation with our clients. Efficient project management professionals &
Enterprise Resource Planning tools in the right hands help us to keep up the pace
while we optimize the utilization of resources and maintain transparency.
The reason that makes us feel proud and stand out is our ethics and we think plan in
unison and therefore deliver product with quality.
We believe in importance of maintaining reputation build over past years reinforcing
our motto at Team Service with Passion.
9. PROJECT INFORMATION
FCP Harmony, Nagpur
Configuration: 2BHK, 2.5BHK, 3BHK, 3.5BHK
Area: 3.9 Lakhs Sq. ft
Number of Units: 210 Apartments
No of Buildings: 2 Buildings (Ground+Podium+15 Floors)
Location: MIHAN, Nagpur
Commencement: 2023
Possession: 2027
RERA No.: P50500049468
ABOUT PROJECT:-
FCP Harmony is a unique luxury apartment community in a part of 7.5 acres of
prime land with stunningly designed 210 Apartments. After successfully
completing the Phase-1 of the Project i.e., Symphony Buildings, the Harmony
buildings are launched to cater to the market demand. The towers are equipped
with 2 level car Parking with 15 residential floors - What can be more
magnificent & splendid than residing in a green paradise with amenities par
excellence!
Enjoy the landscape from the sky-high balconies demonstrating visual richness
and discover yourself falling in love with the natural change of beauty that
comes with every season.
10. The Harmony towers are designed with ample natural ventilation with open
area on 3 sides and all along with central space dedicated to more features like
clubhouse, Leisure Park (Miyawaki Forest), Party Lawn with deck, Box Cricket
Pitch etc.
All blocks are aligned to true north and designed as per Vastu. At present, 2
buildings i.e Harmony 1 & 6 are under construction and will be ready for
possession by 2027.
11. REVIEW OF TASKS PERFORMED
The Internship work has been carried out at NITPL after the completion of 6th
semester for the duration of 15 days.
The following table shows the day wise Internship Training sessions.
DATE COVERED TOPICS
Day 1
29-08-2023
Overall site visit and gathered information about the project.
Day 2
30-08-2023
Introduction about the components of Mivan Formwork
Day 3
31-08-2023
Over view of construction plans of the project
Day 4
01-09-2023
Setting up the wall reinforcement steel
Day 5
02-09-2023
Inspection of the wall reinforcement steel
Day 6
03-09-2023
Setting up the slab reinforcement steel and inspection on
electrical and plumbing connection
Day 7
04-09-2023
Placement of aluminium formwork
Day 8
05-09-2023
Inspection of the placed aluminium formwork and checking the
dimensions
Day 9
06-09-2023
Visited near to Batching plant and materials feed in batching
plant
Day 10
07-09-2023
Operation of batching plant
Day 11
08-09-2023
Different tests performed in lab
Day 12
09-09-2023
Construction of domestic water supply tank
Day 13
10-09-2023
Casting of stair case and steel binding and casting of raft
foundation
12. Day 14
11-09-2023
Learnt about the curing process
Day 15
12-09-2023
Marking to place the bars by using total station
SITE PLAN & FLOOR PLAN
13.
14. MIVAN TECHNOLOGY
Mivan shuttering is a fast-paced construction technique which offers strength and
durability to a building by use of aluminium formworks.
ASSEMBLE THE MASSIVE SHAPE
Because of the effortlessness of the aluminum formwork and the tedious idea of the
get together cycle, it is feasible to configuration building scenes precisely and,
thusly, a whole lot sooner handling time. Besides, it permits gifted specialists to help
out molds, diminishing the weight on them when there is a lack of capable laborers.
All boards are obviously distinguished and amassed utilizing standard formwork
drawings prior to leaving the item office for simple recognizable proof nearby.
Mivan accentuates the utilization of cutting-edge development advances and gear in
the entirety of its activities. Subsequent to leaving the MIVAN fabricating office, all
boards are plainly set apart with their space to guarantee that distinctions on the
site are light and can be amassed utilizing pass on adjusting drawings.
MIVAN FORMWORK ASSEMBLY
15. WORK CYCLE
Mivan is a method of scheduling and maintaining work cycles produced by other
related building styles, such as steel-reinforced solid formations, in which the work
cycle follows a specific assembly. After that, the sections and are placed at the stage
level. This exercise takes 7 to 10 hours to complete. In 7 hours, the kickers and
outdoor suite are complete. In 6 hours, the wall shutters will be built. The main
reinforcements took 10 to 12 hours. Finally, the bob electrical conduit is fixed, and
concrete is poured. This is a well-synchronized cycle of 7 days from 10 to 12 hours.
Cementing is then left until the solids have taken quality before the next cycle
begins and the molds are assembled from side to side in a quick and easy manner.
All panels are clearly marked when leaving the Mivan processing facility, ensuring
that they can be easily identified and installed nearby.
The regimen usually follows a four-day cycle
Day 1: The first task is to install the vertical reinforcement bars and part of the entire
floor or floor on one side of the vertical formwork.
Day 2: The second task is to create the second part of the vertical formwork as well
as pouring the concrete.
Day 3: Installation of floor slab reinforcement bars, walls and casting panels.
Day 4: Column-shaped work boards are removed after 24 hours, kept in place for 7
days and formwork is kept for 2.5 days.
16. Formwork – Components
The plate, which is important for an aluminium bar welded to an aluminium sheet, is
the principle part of the shape. The outcome is a lightweight board with a high
extent to weight proportion, which avoids the substantial marginally under tension.
Boards can be made to any measure or shape to address the issues of explicit
applications. The boards are made of high-strength aluminium amalgam and have a
4mm thick facade plate and 6mm thick ribbed sponsorship to build up it. Mivan's
exceptional offices in Europe and Southeast Asia produce boards. Whenever they
are constructed, they go through a preliminary erection cycle to preclude any
dimensional or positional issues. The most commonly used components in
construction are listed below.
Wall Components:-
Wall Pannel
Make a divider face. It is a sheet of aluminium that is appropriately
managed to fit the specific size of the divider.
WALL PANNEL
17. Rocker
It is a supporting component to the divider. It is a L-molded plate
with adjustable openings for the heel screw.
ROCKER
Kicker
It frames the divider face at the highest point of the boards and
goes about as an edge to help.
KICKER
Stub
Pin It helps in joining two divider boards. It helps in joining two
joints.
18. STUB & PINS
Beam Components:-
Beam Side Panel
Shaped on the shafts. It has a rectangular construction and is
sliced to the size of a shaft.
BEAM SIDE PANNEL
Prop Heads for Soffit Beam
It frames an extraordinary pillar and has an Angular head that
permits the molds to be effectively dismantled.
19. PROP HEADS FOR SOFFIT BEAM
Beam Soffit Panel
It upholds the soffit shaft. It is a plain rectangular
construction of aluminium.
BEAM SOFFIT PANNEL
Beam Soffit Bulkhead
It is the bulkhead for shaft. It conveys the majority of
the mass burden.
20. BEAM SOFFIT BULKHEAD
Deck Components:-
Deck Board
This structures a flat surface for the chunk shape. Intended
for appropriate labour security.
DECK BOARD
21. Deck Prop
Structures an Angular swagger head that upholds the deck and
conveys the heap on the deck plate.
DECK PROP
Prop Length
It is the length of the prop. It relies on the length of the
section.
PROP LENGTH
Deck mid – Beam
It upholds the center bit of the shaft. It holds the substantial.
22. DECK MID-BEAM
Other Components:-
Internal Soffit Corner
Structures an upward interior point between dividers, supports, pieces and
equalinear moldings between dividers, brace boards and shaft support.
INTERNAL SOFFIT CORNER
23. External Soffit Corner
Outside points structure the upward outside point between the dividers and/or shaft
faces and the level outside corners between the divider/pillar face and the outside of
the boards.
EXTERNAL SOFFIT CORNER
External Corner
The outside corner interfaces ver cal or flat structure
cooperate at right points.
EXTERNAL CORNER
27. Installation of Building Blocks
With the help of sophisticated design tools, molds are created with the
lowest cost selection of sheet sizes. By ensuring the most efficient
assembly methods, the cheapest panel option and ultimately the
reduction of capital and maintenance costs, the software, along with the
knowledge and efficiency of the designers, ensures an efficient building
process.
ERECTION OF PLATFORM
30. Mivan Construction Technique
Setting up the wall reinforcing steel
Placement of aluminium formwork
Pouring concrete
Setting up the wall reinforcing steel:-
The wall reinforcing steel is used to give a structure to the building and
support the concrete until they gain half of the required strength. The
aluminium formworks are cast around the steel mesh, which is factory
made and directly erected on the construction site.
31.
32. SHEAR WALL AND MIVAN WALL IN CONSTRUCTION SITE
Reinforcement
Steel is the major part of construction; reinforcement provides
tensile strength for the concrete. Although steel is manufactured
somewhere else but like batching plant to make concrete there is a
steel yard also to cut the steel into the specified shapes. For proper
administrating the construction and fast progress of the work “Bar
Bending Schedule” generally called BBS. Every steel rod has a
number which is clearly mentioned in the RC drawings. BBS is made
for each drawing and shall be handed over to the sub-contractors to
cut the steel according to it. There will be monthly quality check of
the steel 1 sample is taken and sent for third party testing.
BBS contains all the parts of the steel for the respective structural
member. It has different structural members and the all types of
steel rods with respective shapes. Those steel rods are after been cut
and bent into the respective shapes are labelled with respective
number so that it will be easy for the workmen to pick them up for a
member and tie it up fast without an extra cross checking.
33. Lap-length is the length that one bar should be tied to another in
case of extending it and it varies with the grade of concrete. The
development length for M40 it should be greater than equal to
36xdiameter, M30 it should be greater than equal to 46xdiameter
and for M25 it should be greater than equal to 49xdiameter.
As there are grades in concrete there are different types of steels
the one used here is Fe500 which means 500 is the minimum yield
stress in N/mm2
of the steel and it is mentioned in general notes
that everywhere fy(Y) refers to Fe500. In our site HYSD bars are used.
The works such as bending the bars and making stirrups are handed
over to sub-contractors. The sub-contractors are given Bar Bending
Schedule and seeing that they will cut bend and label the steel into
the respective dimensions. There is a separate machine for stirrups
because one will be needing many stirrups in a construction site.
Placement of aluminium formwork:-
Along the wall reinforcing steel, prefabricated room sized walls and floor
slabs are erected. These aluminium alloy slabs are accurately made and
are easy to handle. Spaces for windows, ducts, doors and other features
such as staircases, pannels and sunshade(chajjas) are also integrated in
these structures. The forms are joint together using the pin and wedge
system, which can be dismantled quickly after the concrete structure is
made.
The sequence of orders and method of removal of formwork are as
follows:
34. Shuttering forming the vertical faces of walls, beams and column
sides should be removed in the above order first, as they bear no
load but only retain the concrete.
Shuttering forming soffit of slabs should be removed next.
Shuttering forming soffit of beams, girders or other heavily loaded
shuttering should be removed in the end.
METHOD FOR FORM WORK:-
Formwork Drawings
Site will be provided with a set of formwork drawings which entailed the
followings: -
Shell Plan Layout, Formwork layout drawings, Elevations and sections
drawings indicating the location of formwork panels and component,
35. Typical Fixing Detail drawings and location of Box outs and Transfer Box
out drawings for transfer of Formwork, etc.
Pre-Check
Check if the shutters are properly cleaned by removing the concrete/
mortar and protruding nails.
Formwork shall be made to the exact dimensions within the
permissible tolerances as mentioned below.
Required thickness and quality of steel conforming to IS 6461 shall be
used to meet the requirements of design and surface finish.
For beam bottom & sides, proper size of steel at required spacing shall
be provided to take the design loads/ pressure considering sleeves,
conduit anchors & inserts.
PRE CHECKING OF ALUMINIUM FORMWORK
36. Erection of formwork
Sufficiently rigid and tight to prevent the loss of grout or mortar
from the concrete.
Capable of providing concrete of the correct shape and surface
finish within the specified tolerance limits.
Soffits forms capable of imparting a camber if required.
The formwork may be of timber, plywood, steel, plastic or concrete
depending upon the type of finish specified.
Erect staging/shuttering as per drawing/sketches in such a way that
de-shuttering can be done easily including provision for re-
propping, if planned.
Check the location, line, level, plumb and dimensions of the
formwork to ensure that the deviations are within the permissible
limits.
Provide bracing at proper places & intervals as specified by the
manufacturer or as per formwork scheme to take care of lateral
loads.
Apply mould oil/other coatings as release agents before
reinforcement steel is placed.
37. Wire ties passing through beams, columns and walls shall not be
allowed. In their place bolts passing through sleeves shall be used.
For liquid retaining structures, sleeves shall not be provided for
through bolts.
Check all the shutters are properly aligned and fixed firmly with
required lateral supports and ties.
Check all the spanning members have proper bearing at the
supports.
Forms shall be thoroughly cleaned of all dirt, mortar and other
matters such as metals, blocks, saw dust and foreign materials
before concreting if required through clean-out openings.
Check all the gaps/openings are properly closed to avoid leakages.
Check all the inserts and openings are exactly placed as per the
drawings.
In case of leakages, bulging and sagging immediate actions shall be
taken by tightening wedges or adjusting by jacks which must be
done before the concrete takes its initial set.
Wedges or jacks shall be secured in position after the final check of
alignment.
Removal of Forms
Formwork components shall not be dropped but shall be lowered
without damage to the components and structures. All the removed
38. formwork materials shall be thoroughly scarped, cleaned immediately
and stacked properly for reuse.
All forms shall be removed after the minimum period stipulated
mentioned below without damage to the concrete including removal
without shock as per IS 456.
CONSTRUCTION SITE PHOTOS
39. Batching Plant
A Concrete Batching Plant is a machine to manufacture Concrete from its
ingredients viz Cement, Crushed Stone, Sand, Water and Admixture
Chemicals. The word Batching Plant comes from the word "Batch", which
essentially means that concrete is manufactured in measured bathes inside
a Concrete Batching Plant.
Material feeding:-
Cement OPC 53 Grade
Fly Ash
Aggregate 10mm
Aggregate 20mm
Crushed Stone Dust
Sand
Water
Poly Vinyl Plasticizers
Grade Of Concrete Used In Construction:-
M20 for PCC work
M30 for Slab Casting
M40 for Shear Wall and Foundation.
Concrete Strength Test Result:-
Grade Of
Concrete
7 Days 14 Days 28 Days
M20 22.15 N/mm2 27.83 N/mm2 34.59 N/mm2
M30 34.63 N/mm2 42.34 N/mm2 60.13 N/mm2
M40 42.29 N/mm2 48.22 N/mm2 55.72 N/mm2
40.
41. Pouring Concrete:-
After casting the forms, high-quality concrete is poured. This concrete
takes the form and shape of the cast, which is later removed to make way
for a structure made entirely of cement concrete supported by wall
reinforcing steel. The aluminium forms can be reused at least 250 times,
resulting in minimum waste from the construction site Ensure site
coordinators are available and on stand-by during the concreting process.
Always ensure that concrete pouring is distributed evenly throughout the
wall sections before commencing to cast the slab level areas. This is to
prevent loading pressure on the formwork panels due to uneven casting.
Recheck the areas whenever cement slurry leakage is noted to determine
the cause of it. Remedy work should be done immediately to ensure the
concreting process is not affected. During concreting, always ensure that
immediate step is taken to remove/clean all the excess concrete that is
stuck on the back of the formwork panels. Non removal will result in the
formwork panels getting too heavy and also the scrapping task after the
concrete has dried up becomes more tedious.
42.
43. CURING
Curing of concrete is defined as providing adequate moisture, temperature, and
me to allow the concrete to achieve the desired proper es for its intended use.
Curing is essen al for the hydra on of cement in concrete making. So, to
maintain required moisture content. From the next day of concre ng the curing
has to be done con nuously for the next 7 days. The curing has been done by
the spraying method for aluminium formwork structures. For conven onal
structure, membrane curing has been done.
44. Advantages of Mivan Technology
The time frame for the construction is drastically reduced and is
more advantages and sustainable for fast track project.
As the walls are casted along with slab as monolithic, the time for
construction of walls and plaster is reduced.
Wall thickness is reduced and hence the dead load is reduced and
economically the structure and foundation can be designed.
These structures result unnatural high strength against natural
disastrous due to its unique style monolithic structure as compared
to the conventional.
Number of activities can be reduced.
The form (Mivan Shuttering) is a self-aligning and locking system
which ensures dimensional accuracy with less manpower.
Disadvantages of Mivan Technology
Its initial cost and setup time is higher than conventional formwork.
Less Scope of modification or alteration.
Visible finishing lines.
Expensive in construction.
Can have contraction cracks.
45. FOUNDATION
Foundation is one of the essential parts of the structure. It is defined as
that part of the structure that transfers the load from the structure
constructed on it as well as its weight over a large area of soil in such a
way that the amount does not exceed the ultimate bearing capacity of the
soil and the settlement of the whole structure remains within a tolerable
limit. Foundation is the part of a structure on which the building stands.
The solid ground on which it rests is known as the foundation bed.
Raft or Mat Foundation:-
Raft or Mat foundations are used where other shallow or pile foundations
are not suitable. It is also recommended in situations where the bearing
capacity of the soil is inadequate, the load of the structure is to be
distributed over a large area, or the structure is subjected continuously to
shocks or jerks.
A raft foundation consists of a reinforced concrete slab or T-beam slab
placed over the entire area of the structure. In this type, the whole
basement floor slab acts as the foundation. The total load of the structure
is spread evenly over the entire area of the structure. This is called a raft
because, in this case, the building seems like a vessel that floats on a sea of
soil.
Raft foundations are economic when:-
The soil is weak and the load has to be spread over a large area.
The structure includes a basement.
Columns are closely placed.
Other kinds of foundations are not feasible.
Differential settlement is to be prevented.
47. TOTAL STATION
A total station is an electronic/optical instrument used in
modern surveying and building construction that uses electronic transit
theodolite in conjunction with electronic distance meter (EDM). It is also
integrated with microprocessor, electronic data collector and storage
system
The instrument is used to measure sloping distance of object to the
instrument, horizontal angles and vertical angles. This Microprocessor unit
enables for computation of data collected to further calculate the
horizontal distance, coordinates of a point and reduced level of point.
Data collected from total station can be downloaded into
computer/laptops for further processing of information.
DISTANCE MEASUREMENT:-
1. Setting of the Atmospheric Correction When setting the atmospheric
correction, obtain the correct value by measuring the temperature and
pressure.
2. Setting of the Correction for Prism Constant Topcon’s prism constant
value is 0. Set correction for prism at 0. If the prism is of another
manufacture, the appropriate constant shall be set beforehand.
3. Distance Measurement (Continuous Measurement)
Make sure the mode displays angle measurement.
48.
49. Benefits of this Internship
Practical skills are improved.
Communication skills are developed.
Learnt different types of Construction works and its uses.
Learnt to execute the work as planned.
More Construction Site Images
50.
51.
52. CONCLUSION
It has been a remarkable experience in working with IJM
INFRASTRUCTURE & TEAM UNIVERSAL INFRATECH PVT. LTD. in the
project “NAGPUR INTEGRATED TOWNSHIP PVT. LTD. (First City
Harmony Buildings 1-6)”, where I could witness all the phases of
construction for 15 days in Nagpur. I have been exposed to all the phases
of the site where I have learned many useful things to develop my intuition
and gained knowledge about almost all of the aspects. I have witnessed
different challenges in such a short time period. The caring accommodation
in the office shows the true experience and kindness of every employee
here. I am very thankful to all of the employees here for guiding me through
a wonderful life experience with a positive composure. I am sure that this
experience would guide me in life and drive me towards my goals.
---------------x---------------