INTRODUCTION
In our subject Introduction to Construction Industry, we were
given an assignment that require us select a site in Taylor’s University
that create a certain purpose of it. Our site is located in block A, ground
floor on the left side of Taylor’s University entrance.
We are going to create a recreational area consisting an elevated
garden that will attract students to rest there and have a breath of fresh
air from the hustle of college.
PURPOSE
The purpose of this project is for Taylor’s Lakeside University
students for them to have a better place to rest. We would like to also
bring the students closer to nature.
This area is also to create fresh air for the students from all the
carbon dioxide air coming from all the car at the main entrance of the
campus.
This project will also make the school compound more greener
because of its green implantation to the site.
CONCEPT
We choose that area because Taylor’s Lakeside University is not
putting use to that area. It’s a wasted area. The site size is 10m x 7m.
The reason why we chose this site is because this site was not really
appreciated and also not put to use
The concept of this project is to give the students a rest/ waiting
area. We are going to provide an area for the students to wait for their
parents at a more comfortable way and also more convenient for them.
The materials we are going to use are wooden planks, beams,
columns and etc.
This new concept for this project will increase the population in
that area and it will increase the usage in that area.
OUR SITE LOCATION
I. Front view
II. Main Entrance
III. Back View
SITE ANALYSIS
INTRODUCTION TO OUR SITE
In our site its an open space and its also an open area. Our site is also shady
and its also a big space area. Our site is also right at the entrance which is good for
the students to chill and hang out or socialize around to wait for their parents to
pick them up to go home.
ADVANTAGE
- Open space
- Shady
- At the entrance
- Big space
- Open air
DISADVANTAGE
- No water drainage
- Wasted area
- Dead space
- Not Lively
- Empty land
- No greenery
IMPROVEMENTS
- Make that area interesting
- Attracts people
- Rest area for students
- Provide more shade
- Make the area useful
- Make it a green area
- A place for students to relax and study
CURRENT EXISTING SITUATION
Existing plant having in the site we choose. Our site is located right beside the admin
block, which is Block A
TYPES OF PLANTS
Bucida Buceras
 Botanical name: Bucida buceras
 Height: 40 - 50 feet
 Canopy Width: 35 - 50 feet
 USDA Hardiness Zones: 10 - 11
 Water Needs: Well Drained Soil
 Exposure: Full Sun to Partial Shade
 Growth Rate: 12 to 36 Inches per Season
Red Trumpet Vines
Botanical name: Distictis
buccinatoria
Category: Vine
Family: Bignoniaceae (Bignonias)
Origin: Mexico (North America)
Evergreen: Yes
Flower Color: Orange Red
Bloomtime: Spring/Summer
Height: Climbing (Vine)
Width: Spreading
Exposure: Sun or Shade
Green velvet boxwood
Botanical name: Buxus 'Green Velvet'
Best Soil: Moist, well-drained soil
Light: Sun dappled shade to full sun
Growth Rate: Moderate
Foilage: Green
Fall Color: Green with a bronze cast
Bloom: Tiny pale yellow flowers in the spring are almost unnoticeable except for the
fragrance that attracts bees
Mature Size and Shape: Can grow to 3 to 4 feet tall and wide; round growth habit
Hardiness Zone: 4 – 9
Plant Spacing: Place plants 2.5 to 3 feet apart for hedges
Lawn grass
Common Name: Bermuda grass
Type: Turfgrass
Family: Poaceae
Zone: 7 to 10
Height: 0.25 to 0.25 feet
Spread: 0.25 to 0.50 feet
Bloom Time: Non-flowering
Bloom Description: Green
Sun: Full sun
Water: Dry to medium
Maintenance: Medium
Tolerate: Drought
Conclusion
From this assignment, we were able to learn and understand the building
team, their duties and inter-relation within which we will seek employment, career
progression or further study.
We will also be able to develop an awareness of the building teams
professional responsibilities and to appreciate their profession in the construction
industry.
In conclusion, this report will help us to understand the research and
procedures required when doing a project that serves a certain purpose.
Elements
Tables and chairs
Teak Garden Dining Set DS-04
FOB Price: RM 560/ set
Min.Order Quantity: 5 Set/Sets
Supply Ability: 200 Set/Sets per Month
Port: Port Klang / Port Semarang
Payment Terms: T/T,Western Union,MoneyGram
Stone Pathway
Unit Price: $8.3 - $20.0/
Square Meter
Min. Order: 500 Square
Meters
Trade Terms: FOB, CFR, CIF
natural Granite Paving
Stone for garden or
landscape wall price 1.
Advantage: Lowest Prices,
Fast Delivery and Friendly
Customer Service 2.
Product Keyword: Granite
stone, paving stone
Benches
Stock: 6ft FSC Solid Name: Teak Kingston Garden Bench
Reference No: 5726
£749.99£349.99
Bench Package:
Bench Only, £349.99
Procedures
Procedure Time to Complete Associated Costs
1 Submit and obtain Development Approval through OSC
Builders can now apply for construction permits through OSC 1Submission (single
entry). OSC will then refer the submissions to the Planning Department, Building
Department, Engineering Department, Fire Department, Sewerage Agency, Water
Agency and the Telecommunication Operators.
OSC will issue the development approval (Planning aprrovals, Building approvals,
Engineering approvals, Fire safety plan endorsements, water approvals, sewerage
works approvals and Telecommunications approvals) to the builder.
Builder will submit and obtain approval through OSC for the following documents:
• Planning plan
• Building plan
• Engineering plan (earthwork, road & drainage plan, road excavation permit &
street lighting plan)
• Landscape plan
• Water supply plan
• Sewerage plan
• Infrastructure communication plan
• Fire safety plan
Estimated Processing Costs
1. Planning plan = MYR 500.00
2. Building plan= MYR 1,300.
3. Engineering plan = MYR 100.00
4. Water supply plan = MYR 1,000.00
1. Submission to Local Authority through OSC
2. Obtain Development Order (DO) from Planning Department
3. Obtain Water Approval
4. Obtain Sewerage Approval
5. Obtain Fire Safety (Arch) Comment
6. Obtain Earthwork Approval
7. Obtain Road and Drainage Approval
8. Obtain Landscape Approval
9. Obtain Street Lighting Approval
10. Obtain MSMA and SPAH Approvals
11. Obtain Building Plan Approval
12. Obtain Fire Safety (M&E) Approval
Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC) 61 days MYR
2,900
2 Submit pre-construction notifications to OSC
Under OSC 1Submission, all notifications are submitted via OSC. OSC will then
distribute notifications to the relevant agencies such as:
• Building Department (B Form - notification to start building work)
• Engineering Department (B Form - notification to start earthwork)
• Sewerage Certifying Agency (IWK) (PDC 6 Form - notification to start sewerage
work)
Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC) 1 day no charge
3 Request final utilities inspections through OSC
Under OSC 1Submission, the builder has to request for inspections via OSC. OSC will
arrange and coordinate inspections and connections schedule with relevant
agencies
1. TELCO connection = MYR495.00
2. Water connection = MYR 30.00
3. Fire safety inspection = MYR 111.00
Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC) 1 day MYR 636
4 Receive Road and Drainage Final Inspection
Once the road and drainage works has been completed, the builder will request the
Road and Drainage clearance letter from the Engineering Department of CHKL. The
builder has to submit a construction report notification and by signing form G 17,
the Engineer certifies that all works were carried out according to regulations. Form
G17 will be filed along with Form F (Certificate of Completion and Compliance (CCC)
via OSC to the Engineering Department.
Agency: Sewerage Certifying Agency (IWK) 1 day no charge
5 Obtain Road and Drainage Clearance Letter
A date for the inspection will be set-up prior to the issuance of clearance letter for
the road and drainage work
Agency: Sewerage Certifying Agency (IWK) 12 days no charge
6 Receive Sewage Final Inspection
The Sewerage Certifying Agency (IWK) will carry out an inspection of the sewerage
system and issue to the builder a clearance letter for sewerage.
Agency: Sewerage Certifying Agency (IWK) 1 day no charge
7 Obtain Sewage Clearance Letter
Once the inspection has been carried out, a clearance letter is issued to the Builder.
This clearance letter will allow the Engineer to issue the Certificate of Completion
and compliance (CCC).
Agency: Sewerage Certifying Agency (IWK) 12 days no charge
8 Receive Fire Safety Final Inspection
Fire and Rescue Department will carry out fire safety inspection
Agency: Fire and Rescue Department 1 day no charge
9 Obtain Fire Safety Final Letter
Fire and Rescue Department will issue to the builder the clearance letter for fire
safety
Agency: Fire Department 12 days no charge
10 Receive Water Inspection
Water Authority SYABAS will conduct an onsite inspection of the works and make
the connection to the public pipe.
Agency: Water Authority SYABAS 1 day no charge
11 Submit Water Test and Commissioning (T&C) Report
Water Authority SYABAS will conduct an onsite inspection of the works and make
the connection to the public pipe.
Agency: Water Authority SYABAS 11 days no charge
12 Obtain Water Clearance Letter
The Water Authority SYABAS will issue a clearance letter to the builder and install
the water meter at the same time for water connection.
Agency: Water Authority SYABAS 1 day MYR 1,000
13 Builder’s Principal Submitting Person files the Certificate of Completion and
compliance (CCC)
The Builder’s Principal Submitting Person (professional architect) will issue
Certificate of Completion and compliance (Form F - CCC) to the Builder/Owner and
2 copies of the CCC will be filed at the OSC for the Building Department (JRBB) and
the Board of Architects/Engineers (LAM/LJM).
Agency: Building Department and Board of Architect via OSC. 1 day no charge
14 Obtain Water Connection
Agency: Water Authority SYABAS 1 day no charge
15 Obtain Telco Connection
Agency: Telekom Malaysia (Telco) 15 days no charge

More Related Content

Similar to Ici final 2

Project brief
Project brief Project brief
Project brief PK146
 
Ici project brief2
Ici project brief2Ici project brief2
Ici project brief2itsmylifesl
 
A Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingA Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingIRJET Journal
 
Ici final project (final)
Ici final project (final)Ici final project (final)
Ici final project (final)Joe Onn Lim
 
Site visit report
Site visit reportSite visit report
Site visit reportwleying
 
Project brief
Project brief Project brief
Project brief Haziq1511
 
ICI Project 3 - The Project Brief
ICI Project 3 - The Project BriefICI Project 3 - The Project Brief
ICI Project 3 - The Project BriefRyan Kerry Jy
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)Lwj Welson
 
Building Construction and Technology
Building Construction and TechnologyBuilding Construction and Technology
Building Construction and TechnologySultan M Muzahir
 
Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)jinlieww
 
Ici final project proposal 2
Ici final project proposal 2Ici final project proposal 2
Ici final project proposal 2harrygirn
 
fnbe0414- Ici final project proposal
fnbe0414- Ici final project proposal fnbe0414- Ici final project proposal
fnbe0414- Ici final project proposal harrygirn
 

Similar to Ici final 2 (20)

Project
Project Project
Project
 
Project Brief
Project BriefProject Brief
Project Brief
 
Project brief
Project brief Project brief
Project brief
 
Green Building 2018
 Green Building  2018 Green Building  2018
Green Building 2018
 
Ici project brief2
Ici project brief2Ici project brief2
Ici project brief2
 
A Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment BuildingA Descriptive Study on Construction Progress Involved in Apartment Building
A Descriptive Study on Construction Progress Involved in Apartment Building
 
induarial trainin report
induarial trainin reportinduarial trainin report
induarial trainin report
 
Ici final project (final)
Ici final project (final)Ici final project (final)
Ici final project (final)
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Project brief
Project brief Project brief
Project brief
 
ICI Project 3 - The Project Brief
ICI Project 3 - The Project BriefICI Project 3 - The Project Brief
ICI Project 3 - The Project Brief
 
Ici final project report
Ici final project reportIci final project report
Ici final project report
 
Slk m india
Slk m indiaSlk m india
Slk m india
 
Assignment (1)
Assignment (1)Assignment (1)
Assignment (1)
 
Training Report
Training ReportTraining Report
Training Report
 
Building Construction and Technology
Building Construction and TechnologyBuilding Construction and Technology
Building Construction and Technology
 
Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)Ici final project (proposal 2) (1)
Ici final project (proposal 2) (1)
 
Ici final project proposal 2
Ici final project proposal 2Ici final project proposal 2
Ici final project proposal 2
 
fnbe0414- Ici final project proposal
fnbe0414- Ici final project proposal fnbe0414- Ici final project proposal
fnbe0414- Ici final project proposal
 
Green Roofs and Vertical Gardens ~ Institute Overseas Fellowship
Green Roofs and Vertical Gardens ~ Institute Overseas FellowshipGreen Roofs and Vertical Gardens ~ Institute Overseas Fellowship
Green Roofs and Vertical Gardens ~ Institute Overseas Fellowship
 

More from Ricco Wei

More from Ricco Wei (12)

Building construction
Building constructionBuilding construction
Building construction
 
Ricco
Ricco Ricco
Ricco
 
Psy journal 1
Psy journal 1 Psy journal 1
Psy journal 1
 
English essay
English essayEnglish essay
English essay
 
Allegro
Allegro Allegro
Allegro
 
enbe report
enbe reportenbe report
enbe report
 
Magzine 3
Magzine 3Magzine 3
Magzine 3
 
Magazine
MagazineMagazine
Magazine
 
Magazine 4
Magazine 4Magazine 4
Magazine 4
 
Magazine 5
Magazine 5Magazine 5
Magazine 5
 
magazine 2
magazine 2magazine 2
magazine 2
 
Magazine 3
Magazine 3Magazine 3
Magazine 3
 

Recently uploaded

Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call GirlsPragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call GirlsKishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call GirlsLaxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | DelhiMalviyaNagarCallGirl
 
Bridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.comBridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.comthephillipta
 
Retail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College ParkRetail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College Parkjosebenzaquen
 
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...akbard9823
 
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...anilsa9823
 
Jagat Puri Call Girls : ☎ 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ☎ 8527673949, Low rate Call GirlsJagat Puri Call Girls : ☎ 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call GirlsFaridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiFULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiMalviyaNagarCallGirl
 
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in DowntownDowntown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtowndajasot375
 
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call GirlsMandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girlsashishs7044
 
FULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | DelhiFULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | DelhiMalviyaNagarCallGirl
 
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | DelhiMalviyaNagarCallGirl
 
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857delhimodel235
 
Zagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdfZagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdfStripovizijacom
 
9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi Ncr
9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi Ncr9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi Ncr
9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi NcrSapana Sha
 
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service AkolaAkola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service Akolasrsj9000
 

Recently uploaded (20)

Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call GirlsPragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
Pragati Maidan Call Girls : ☎ 8527673949, Low rate Call Girls
 
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call GirlsKishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
Kishangarh Call Girls : ☎ 8527673949, Low rate Call Girls
 
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call GirlsLaxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
Laxmi Nagar Call Girls : ☎ 8527673949, Low rate Call Girls
 
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Moti Nagar | Delhi
 
Bur Dubai Call Girls # 971504361175 # Call Girls In Bur Dubai || (UAE)
Bur Dubai Call Girls # 971504361175 # Call Girls In Bur Dubai || (UAE)Bur Dubai Call Girls # 971504361175 # Call Girls In Bur Dubai || (UAE)
Bur Dubai Call Girls # 971504361175 # Call Girls In Bur Dubai || (UAE)
 
Bridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.comBridge Fight Board by Daniel Johnson dtjohnsonart.com
Bridge Fight Board by Daniel Johnson dtjohnsonart.com
 
Retail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College ParkRetail Store Scavanger Hunt - Foundation College Park
Retail Store Scavanger Hunt - Foundation College Park
 
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
Hazratganj ] (Call Girls) in Lucknow - 450+ Call Girl Cash Payment 🧄 89231135...
 
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
 
Jagat Puri Call Girls : ☎ 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ☎ 8527673949, Low rate Call GirlsJagat Puri Call Girls : ☎ 8527673949, Low rate Call Girls
Jagat Puri Call Girls : ☎ 8527673949, Low rate Call Girls
 
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call GirlsFaridabad Call Girls : ☎ 8527673949, Low rate Call Girls
Faridabad Call Girls : ☎ 8527673949, Low rate Call Girls
 
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | DelhiFULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
FULL ENJOY - 9953040155 Call Girls in Dwarka Mor | Delhi
 
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in DowntownDowntown Call Girls O5O91O128O Pakistani Call Girls in Downtown
Downtown Call Girls O5O91O128O Pakistani Call Girls in Downtown
 
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call GirlsMandi House Call Girls : ☎ 8527673949, Low rate Call Girls
Mandi House Call Girls : ☎ 8527673949, Low rate Call Girls
 
FULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | DelhiFULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | Delhi
FULL ENJOY - 9953040155 Call Girls in Gandhi Vihar | Delhi
 
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | DelhiFULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
FULL ENJOY - 9953040155 Call Girls in Laxmi Nagar | Delhi
 
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
Low Rate Call Girls in Laxmi Nagar Delhi Call 9990771857
 
Zagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdfZagor VČ OP 055 - Oluja nad Haitijem.pdf
Zagor VČ OP 055 - Oluja nad Haitijem.pdf
 
9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi Ncr
9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi Ncr9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi Ncr
9654467111 Full Enjoy @24/7 Call Girls In Saket Delhi Ncr
 
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service AkolaAkola Call Girls #9907093804 Contact Number Escorts Service Akola
Akola Call Girls #9907093804 Contact Number Escorts Service Akola
 

Ici final 2

  • 1. TAYLOR’S UNIVERSITY Foundation in Natural & Built Environments APRIL 2014 CHRISTINA NG SUE LI MOREIRA RICCO SOH ZHENG WEI MR. FARIZ HILMI
  • 4. INTRODUCTION In our subject Introduction to Construction Industry, we were given an assignment that require us select a site in Taylor’s University that create a certain purpose of it. Our site is located in block A, ground floor on the left side of Taylor’s University entrance. We are going to create a recreational area consisting an elevated garden that will attract students to rest there and have a breath of fresh air from the hustle of college.
  • 5. PURPOSE The purpose of this project is for Taylor’s Lakeside University students for them to have a better place to rest. We would like to also bring the students closer to nature. This area is also to create fresh air for the students from all the carbon dioxide air coming from all the car at the main entrance of the campus. This project will also make the school compound more greener because of its green implantation to the site.
  • 6. CONCEPT We choose that area because Taylor’s Lakeside University is not putting use to that area. It’s a wasted area. The site size is 10m x 7m. The reason why we chose this site is because this site was not really appreciated and also not put to use The concept of this project is to give the students a rest/ waiting area. We are going to provide an area for the students to wait for their parents at a more comfortable way and also more convenient for them. The materials we are going to use are wooden planks, beams, columns and etc. This new concept for this project will increase the population in that area and it will increase the usage in that area.
  • 11. SITE ANALYSIS INTRODUCTION TO OUR SITE In our site its an open space and its also an open area. Our site is also shady and its also a big space area. Our site is also right at the entrance which is good for the students to chill and hang out or socialize around to wait for their parents to pick them up to go home. ADVANTAGE - Open space - Shady - At the entrance - Big space - Open air DISADVANTAGE - No water drainage - Wasted area - Dead space
  • 12. - Not Lively - Empty land - No greenery IMPROVEMENTS - Make that area interesting - Attracts people - Rest area for students - Provide more shade - Make the area useful - Make it a green area - A place for students to relax and study CURRENT EXISTING SITUATION
  • 13. Existing plant having in the site we choose. Our site is located right beside the admin block, which is Block A TYPES OF PLANTS Bucida Buceras  Botanical name: Bucida buceras  Height: 40 - 50 feet  Canopy Width: 35 - 50 feet  USDA Hardiness Zones: 10 - 11  Water Needs: Well Drained Soil  Exposure: Full Sun to Partial Shade  Growth Rate: 12 to 36 Inches per Season Red Trumpet Vines Botanical name: Distictis buccinatoria Category: Vine Family: Bignoniaceae (Bignonias) Origin: Mexico (North America) Evergreen: Yes
  • 14. Flower Color: Orange Red Bloomtime: Spring/Summer Height: Climbing (Vine) Width: Spreading Exposure: Sun or Shade Green velvet boxwood Botanical name: Buxus 'Green Velvet' Best Soil: Moist, well-drained soil Light: Sun dappled shade to full sun Growth Rate: Moderate
  • 15. Foilage: Green Fall Color: Green with a bronze cast Bloom: Tiny pale yellow flowers in the spring are almost unnoticeable except for the fragrance that attracts bees Mature Size and Shape: Can grow to 3 to 4 feet tall and wide; round growth habit Hardiness Zone: 4 – 9 Plant Spacing: Place plants 2.5 to 3 feet apart for hedges Lawn grass Common Name: Bermuda grass Type: Turfgrass Family: Poaceae Zone: 7 to 10 Height: 0.25 to 0.25 feet Spread: 0.25 to 0.50 feet Bloom Time: Non-flowering Bloom Description: Green Sun: Full sun Water: Dry to medium
  • 16. Maintenance: Medium Tolerate: Drought Conclusion From this assignment, we were able to learn and understand the building team, their duties and inter-relation within which we will seek employment, career progression or further study. We will also be able to develop an awareness of the building teams professional responsibilities and to appreciate their profession in the construction industry. In conclusion, this report will help us to understand the research and procedures required when doing a project that serves a certain purpose.
  • 17. Elements Tables and chairs Teak Garden Dining Set DS-04 FOB Price: RM 560/ set Min.Order Quantity: 5 Set/Sets Supply Ability: 200 Set/Sets per Month Port: Port Klang / Port Semarang Payment Terms: T/T,Western Union,MoneyGram
  • 18. Stone Pathway Unit Price: $8.3 - $20.0/ Square Meter Min. Order: 500 Square Meters Trade Terms: FOB, CFR, CIF natural Granite Paving Stone for garden or landscape wall price 1. Advantage: Lowest Prices, Fast Delivery and Friendly Customer Service 2. Product Keyword: Granite stone, paving stone Benches
  • 19. Stock: 6ft FSC Solid Name: Teak Kingston Garden Bench Reference No: 5726 £749.99£349.99 Bench Package: Bench Only, £349.99 Procedures Procedure Time to Complete Associated Costs 1 Submit and obtain Development Approval through OSC Builders can now apply for construction permits through OSC 1Submission (single entry). OSC will then refer the submissions to the Planning Department, Building Department, Engineering Department, Fire Department, Sewerage Agency, Water Agency and the Telecommunication Operators. OSC will issue the development approval (Planning aprrovals, Building approvals, Engineering approvals, Fire safety plan endorsements, water approvals, sewerage works approvals and Telecommunications approvals) to the builder. Builder will submit and obtain approval through OSC for the following documents: • Planning plan • Building plan • Engineering plan (earthwork, road & drainage plan, road excavation permit & street lighting plan) • Landscape plan • Water supply plan • Sewerage plan • Infrastructure communication plan • Fire safety plan Estimated Processing Costs 1. Planning plan = MYR 500.00 2. Building plan= MYR 1,300. 3. Engineering plan = MYR 100.00
  • 20. 4. Water supply plan = MYR 1,000.00 1. Submission to Local Authority through OSC 2. Obtain Development Order (DO) from Planning Department 3. Obtain Water Approval 4. Obtain Sewerage Approval 5. Obtain Fire Safety (Arch) Comment 6. Obtain Earthwork Approval 7. Obtain Road and Drainage Approval 8. Obtain Landscape Approval 9. Obtain Street Lighting Approval 10. Obtain MSMA and SPAH Approvals 11. Obtain Building Plan Approval 12. Obtain Fire Safety (M&E) Approval Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC) 61 days MYR 2,900 2 Submit pre-construction notifications to OSC Under OSC 1Submission, all notifications are submitted via OSC. OSC will then distribute notifications to the relevant agencies such as: • Building Department (B Form - notification to start building work) • Engineering Department (B Form - notification to start earthwork) • Sewerage Certifying Agency (IWK) (PDC 6 Form - notification to start sewerage work) Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC) 1 day no charge 3 Request final utilities inspections through OSC Under OSC 1Submission, the builder has to request for inspections via OSC. OSC will arrange and coordinate inspections and connections schedule with relevant agencies 1. TELCO connection = MYR495.00 2. Water connection = MYR 30.00 3. Fire safety inspection = MYR 111.00 Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC) 1 day MYR 636
  • 21. 4 Receive Road and Drainage Final Inspection Once the road and drainage works has been completed, the builder will request the Road and Drainage clearance letter from the Engineering Department of CHKL. The builder has to submit a construction report notification and by signing form G 17, the Engineer certifies that all works were carried out according to regulations. Form G17 will be filed along with Form F (Certificate of Completion and Compliance (CCC) via OSC to the Engineering Department. Agency: Sewerage Certifying Agency (IWK) 1 day no charge 5 Obtain Road and Drainage Clearance Letter A date for the inspection will be set-up prior to the issuance of clearance letter for the road and drainage work Agency: Sewerage Certifying Agency (IWK) 12 days no charge 6 Receive Sewage Final Inspection The Sewerage Certifying Agency (IWK) will carry out an inspection of the sewerage system and issue to the builder a clearance letter for sewerage. Agency: Sewerage Certifying Agency (IWK) 1 day no charge 7 Obtain Sewage Clearance Letter Once the inspection has been carried out, a clearance letter is issued to the Builder. This clearance letter will allow the Engineer to issue the Certificate of Completion and compliance (CCC). Agency: Sewerage Certifying Agency (IWK) 12 days no charge 8 Receive Fire Safety Final Inspection Fire and Rescue Department will carry out fire safety inspection Agency: Fire and Rescue Department 1 day no charge
  • 22. 9 Obtain Fire Safety Final Letter Fire and Rescue Department will issue to the builder the clearance letter for fire safety Agency: Fire Department 12 days no charge 10 Receive Water Inspection Water Authority SYABAS will conduct an onsite inspection of the works and make the connection to the public pipe. Agency: Water Authority SYABAS 1 day no charge 11 Submit Water Test and Commissioning (T&C) Report Water Authority SYABAS will conduct an onsite inspection of the works and make the connection to the public pipe. Agency: Water Authority SYABAS 11 days no charge 12 Obtain Water Clearance Letter The Water Authority SYABAS will issue a clearance letter to the builder and install the water meter at the same time for water connection. Agency: Water Authority SYABAS 1 day MYR 1,000 13 Builder’s Principal Submitting Person files the Certificate of Completion and compliance (CCC) The Builder’s Principal Submitting Person (professional architect) will issue Certificate of Completion and compliance (Form F - CCC) to the Builder/Owner and 2 copies of the CCC will be filed at the OSC for the Building Department (JRBB) and the Board of Architects/Engineers (LAM/LJM). Agency: Building Department and Board of Architect via OSC. 1 day no charge 14 Obtain Water Connection Agency: Water Authority SYABAS 1 day no charge 15 Obtain Telco Connection Agency: Telekom Malaysia (Telco) 15 days no charge