This document provides project details for the Harvard Medical School construction at DHCC in Dubai. The original contract value was Dhs. 289,927,807 but was revised to Dhs. 323,560,976. As of May 2009, Dhs. 219,382,328 had been invoiced. The project completion date was extended from November 2008 to December 2009 and was 69% complete at that time, with 360 days of extension claimed. Over 3.9 million manhours had been worked on the project with no fatalities or serious accidents, though there were 194 minor incidents reported.