SlideShare a Scribd company logo
HIGHWAY CONSTRUCTION METHODS
HMA PLACING
ENG. S.A.S.T SALAWAVIDANA
CEng FIESL, MCIHT, MEng (Highway & Traffic), BSc.Eng (Hons)
INTRODUCTION
• Mix placement and compaction are the two most
important elements in HMA pavement construction.
• Mix placement involves any equipment or procedures
used to place the delivered HMA on the desired
surface at the desired thickness.
• Mix placement can involve complicated asphalt paver
operations or simple manual shoveling.
• This section provides a basic description of HMA
placement operations.
Eng. Suneth Thushara Salawavidana 2
Placement Considerations
• There are, of course, many considerations to take into
account when placing HMA.
• Many are dependent upon local materials, weather, crew
knowledge and training, and individual experience.
• Lift thickness. A "lift" refers to a layer of pavement as
placed by the asphalt paver. In order to avoid mat tearing
(which generally shows up as a series of longitudinal
streaks) a good rule-of-thumb is that the depth of the
compacted lift should be at least twice the maximum
aggregate size or three times the nominal maximum
aggregate size.
Eng. Suneth Thushara Salawavidana 3
Placement Considerations
• Longitudinal joints. The interface between two
adjacent and parallel HMA mats.
• Improperly constructed longitudinal joints can
cause premature deterioration of multilane HMA
pavements in the form of cracking and raveling.
Handwork.
• HMA can be placed by hand in situations where the
paver cannot place it adequately.
• This can often occur around utilities, around
intersection corners and in other tight spaces.
Eng. Suneth Thushara Salawavidana 4
Placement Considerations
– Hand-placing should be minimized because it is prone to
aggregate segregation and results in a slightly rough
surface texture.
– If hand placement is necessary the following precautions
should be taken:
– Place the HMA in a pile far enough away from the
placement area that the whole pile must be moved.
– If the pile is located in the placement area its
appearance, density or aggregate distribution may be
slightly different than the surrounding handworked mat.
Eng. Suneth Thushara Salawavidana 5
Placement Considerations
• Carefully deposit the material with shovels and then
spread with lutes. Do not broadcast (scoop and pitch)
the HMA with shovels - this is likely to cause aggregate
segregation.
• All material should be thoroughly loosened and evenly
distributed. Chunks of HMA that do not easily break
apart should be removed and discarded.
• Check the handworked surface with a straightedge or
template before rolling to ensure uniformity.
Eng. Suneth Thushara Salawavidana 6
Placement Considerations
• Mat problems. The asphalt paver, MTV, rollers, mix
design and manufacturing introduce many variables
into flexible pavement construction.
• A familiarity with common causes of the more typical
mat problems can help improve construction quality.
• Some common mat problems are microcracking, fat
spots, joint problems, non-uniform texture, roller
marks, shoving, surface waves, tearing (streaks) and
transverse screed marks.
Eng. Suneth Thushara Salawavidana 7
Asphalt Paver
• In 1934 Barber-Greene introduced the Model 79 asphalt laydown
machine, a self-propelled formless laydown machine with a floating
screed.
• Since then, the basic concept of the asphalt paver has remained
relatively unchanged: HMA is loaded in the front, carried to the rear
by a set of flight feeders (conveyor belts), spread out by a set of
augers, then leveled and compacted by a screed.
• This set of functions can be divided into two main systems:
– The tractor (or material feed system)
– The screed
Eng. Suneth Thushara Salawavidana 8
Tractor (Material Feed System)
• The tractor contains the material feed system,
which accepts the HMA at the front of the
paver, moves it to the rear and spreads it out to
the desired width in preparation for screed
leveling and compaction.
• The basic tractor components are:
– Push Roller and Truck Hitch
– Hopper
– Conveyor
– Auger
Eng. Suneth Thushara Salawavidana 9
Push Roller and Truck Hitch
• The push roller is the portion of the paver that
contacts the transport vehicle and the truck hitch
holds the transport vehicle in contact with the
paver.
• They are located on the front of the hopper.
Eng. Suneth Thushara Salawavidana 10
Push Roller and Truck Hitch
Truck Hitch Engaged
Hopper
• The hopper is used as a temporary storage area for
HMA delivered by the transport vehicle.
• Therefore, the paver can accept more material than is
immediately needed and can use the volume in the
hopper to compensate for fluctuating material demands
created by such things as paving over irregular grades,
utility access openings or irregular intersection shapes.
• Hopper sides (or “wings”) can be tilted up (or “folded”)
to force material to the middle where it is carried to the
rear by the conveyor system.
Eng. Suneth Thushara Salawavidana 11
Hopper
• Hoppers can also be fit with inserts to
allow them to carry more HMA.
• These inserts are typically used in
conjunction with a material transfer
vehicle (MTV).
Eng. Suneth Thushara Salawavidana 12
Hopper with Wings Folded Up
Caterpillar AP-1055B with Hopper Insert
Conveyor
• The conveyor mechanism carries the
HMA from the hopper, under the chassis
and engine, then to the augers.
• The amount of HMA carried back by the
conveyors is regulated by either variable
speed conveyors and augers or flow
gates, which can be raised or lowered by
the operator or, more often, by an
automatic feed control system.
Eng. Suneth Thushara Salawavidana 13
Conveyors
(seen from the rear of a partially built paver)
Auger
• The auger receives HMA from the conveyor and
spreads it out evenly over the width to be paved.
• There is one auger for each side of the paver and
they can be operated independently.
• Some pavers allow the augers to be operated in
reverse direction so that one can be operated
forward and the other in reverse to send all the
received HMA to one side of the paver.
• The auger gearbox can either be located in the
middle or on the outside edge of each auger.
Eng. Suneth Thushara Salawavidana 14
Auger
• If an inadequate amount of HMA is
distributed under a middle-located gearbox
the result can be a thin longitudinal strip of
mat aligned with the gearbox that exhibits
lower densities from aggregate segregation
and/or temperature differentials
Eng. Suneth Thushara Salawavidana 15
Augers Distributing HMA
PLACEMENT
• Operation of the tractor, and specifically the
material feed system, can have significant
effects on overall construction quality and thus
long-term pavement performance.
• Although there are many detailed operational
concerns, the two broad statements below
encompass most of the detailed concerns:
Eng. Suneth Thushara Salawavidana 16
PLACEMENT
• HMA must be delivered to maintain a relatively
constant head of material in front of the screed.
• This involves maintaining a minimum amount of
HMA in the hopper, regulating HMA feed rate by
controlling conveyor/auger speed and flow gate
openings (if present), and maintaining a
constant paving speed.
• A fluctuating HMA head in front of the screed
will affect the screed angle of attack and
produce bumps and waves in the finished mat.
Eng. Suneth Thushara Salawavidana 17
PLACEMENT
• The hopper should never be allowed to empty during
paving.
• This results in the leftover cold, large aggregate in the
hopper sliding onto the conveyor in a concentrated mass
and then being placed on the mat without mixing with any
hot or fine aggregate.
• This can produce aggregate segregation or temperature
differentials, which will cause isolated low mat densities.
• If there are no transport vehicles immediately available to
refill the hopper it is better to stop the paving machine
than to continue operating and empty the hopper.
Eng. Suneth Thushara Salawavidana 18
Eng. S.A.S.T Salawavidana
Eng. S.A.S.T Salawavidana

More Related Content

Similar to HMA Placing.pptx

Transport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MITransport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MI
Dr Romil Mishra
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauli
Tauhid Mohammad
 
Heavy-duty-and equipment-2.pptxjjhhhhhhh
Heavy-duty-and equipment-2.pptxjjhhhhhhhHeavy-duty-and equipment-2.pptxjjhhhhhhh
Heavy-duty-and equipment-2.pptxjjhhhhhhh
teddiyfentaw
 
Road making machines in mines
Road making machines in minesRoad making machines in mines
Road making machines in mines
Vijayant Singh
 
Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2
AJEETH B
 
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLYTOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
Vj NiroSh
 
Bucket Conveyor.pptx
Bucket Conveyor.pptxBucket Conveyor.pptx
Bucket Conveyor.pptx
NehaSharma314452
 
Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...
Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...
Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...
A Makwana
 
Report_on_Conveyor_Design_Method
Report_on_Conveyor_Design_MethodReport_on_Conveyor_Design_Method
Report_on_Conveyor_Design_Method
Abhinev Singh Bhadauria
 
Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)
Construction Tech. and Mgmt., VNIT Nagpur
 
Components of Belt conveyor
Components of Belt conveyorComponents of Belt conveyor
Components of Belt conveyor
Karan Patel
 
Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators
ajaz malla
 
Asphalt paver
Asphalt  paverAsphalt  paver
Asphalt paver
Hashan Gunawardena
 
SURFACE MINERS
SURFACE MINERSSURFACE MINERS
SURFACE MINERS
NIRBHAY KUMAR SINHA
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
Prakalp Binzade
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
Safdar Ali
 
readymixconcrete-.pdf
readymixconcrete-.pdfreadymixconcrete-.pdf
readymixconcrete-.pdf
FaizanSolanki
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
Aglaia Connect
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
Darshiini Vig
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
Chow Hong Da
 

Similar to HMA Placing.pptx (20)

Transport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MITransport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MI
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauli
 
Heavy-duty-and equipment-2.pptxjjhhhhhhh
Heavy-duty-and equipment-2.pptxjjhhhhhhhHeavy-duty-and equipment-2.pptxjjhhhhhhh
Heavy-duty-and equipment-2.pptxjjhhhhhhh
 
Road making machines in mines
Road making machines in minesRoad making machines in mines
Road making machines in mines
 
Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2
 
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLYTOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
 
Bucket Conveyor.pptx
Bucket Conveyor.pptxBucket Conveyor.pptx
Bucket Conveyor.pptx
 
Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...
Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...
Belt conveyor system_Advanced Construction Technology (Semester-6), Civil Eng...
 
Report_on_Conveyor_Design_Method
Report_on_Conveyor_Design_MethodReport_on_Conveyor_Design_Method
Report_on_Conveyor_Design_Method
 
Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)
 
Components of Belt conveyor
Components of Belt conveyorComponents of Belt conveyor
Components of Belt conveyor
 
Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators
 
Asphalt paver
Asphalt  paverAsphalt  paver
Asphalt paver
 
SURFACE MINERS
SURFACE MINERSSURFACE MINERS
SURFACE MINERS
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
readymixconcrete-.pdf
readymixconcrete-.pdfreadymixconcrete-.pdf
readymixconcrete-.pdf
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 

Recently uploaded

Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
iemerc2024
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...
IJECEIAES
 
introduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdfintroduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdf
ravindarpurohit26
 

Recently uploaded (20)

Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...Adaptive synchronous sliding control for a robot manipulator based on neural ...
Adaptive synchronous sliding control for a robot manipulator based on neural ...
 
introduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdfintroduction to solar energy for engineering.pdf
introduction to solar energy for engineering.pdf
 

HMA Placing.pptx

  • 1. HIGHWAY CONSTRUCTION METHODS HMA PLACING ENG. S.A.S.T SALAWAVIDANA CEng FIESL, MCIHT, MEng (Highway & Traffic), BSc.Eng (Hons)
  • 2. INTRODUCTION • Mix placement and compaction are the two most important elements in HMA pavement construction. • Mix placement involves any equipment or procedures used to place the delivered HMA on the desired surface at the desired thickness. • Mix placement can involve complicated asphalt paver operations or simple manual shoveling. • This section provides a basic description of HMA placement operations. Eng. Suneth Thushara Salawavidana 2
  • 3. Placement Considerations • There are, of course, many considerations to take into account when placing HMA. • Many are dependent upon local materials, weather, crew knowledge and training, and individual experience. • Lift thickness. A "lift" refers to a layer of pavement as placed by the asphalt paver. In order to avoid mat tearing (which generally shows up as a series of longitudinal streaks) a good rule-of-thumb is that the depth of the compacted lift should be at least twice the maximum aggregate size or three times the nominal maximum aggregate size. Eng. Suneth Thushara Salawavidana 3
  • 4. Placement Considerations • Longitudinal joints. The interface between two adjacent and parallel HMA mats. • Improperly constructed longitudinal joints can cause premature deterioration of multilane HMA pavements in the form of cracking and raveling. Handwork. • HMA can be placed by hand in situations where the paver cannot place it adequately. • This can often occur around utilities, around intersection corners and in other tight spaces. Eng. Suneth Thushara Salawavidana 4
  • 5. Placement Considerations – Hand-placing should be minimized because it is prone to aggregate segregation and results in a slightly rough surface texture. – If hand placement is necessary the following precautions should be taken: – Place the HMA in a pile far enough away from the placement area that the whole pile must be moved. – If the pile is located in the placement area its appearance, density or aggregate distribution may be slightly different than the surrounding handworked mat. Eng. Suneth Thushara Salawavidana 5
  • 6. Placement Considerations • Carefully deposit the material with shovels and then spread with lutes. Do not broadcast (scoop and pitch) the HMA with shovels - this is likely to cause aggregate segregation. • All material should be thoroughly loosened and evenly distributed. Chunks of HMA that do not easily break apart should be removed and discarded. • Check the handworked surface with a straightedge or template before rolling to ensure uniformity. Eng. Suneth Thushara Salawavidana 6
  • 7. Placement Considerations • Mat problems. The asphalt paver, MTV, rollers, mix design and manufacturing introduce many variables into flexible pavement construction. • A familiarity with common causes of the more typical mat problems can help improve construction quality. • Some common mat problems are microcracking, fat spots, joint problems, non-uniform texture, roller marks, shoving, surface waves, tearing (streaks) and transverse screed marks. Eng. Suneth Thushara Salawavidana 7
  • 8. Asphalt Paver • In 1934 Barber-Greene introduced the Model 79 asphalt laydown machine, a self-propelled formless laydown machine with a floating screed. • Since then, the basic concept of the asphalt paver has remained relatively unchanged: HMA is loaded in the front, carried to the rear by a set of flight feeders (conveyor belts), spread out by a set of augers, then leveled and compacted by a screed. • This set of functions can be divided into two main systems: – The tractor (or material feed system) – The screed Eng. Suneth Thushara Salawavidana 8
  • 9. Tractor (Material Feed System) • The tractor contains the material feed system, which accepts the HMA at the front of the paver, moves it to the rear and spreads it out to the desired width in preparation for screed leveling and compaction. • The basic tractor components are: – Push Roller and Truck Hitch – Hopper – Conveyor – Auger Eng. Suneth Thushara Salawavidana 9
  • 10. Push Roller and Truck Hitch • The push roller is the portion of the paver that contacts the transport vehicle and the truck hitch holds the transport vehicle in contact with the paver. • They are located on the front of the hopper. Eng. Suneth Thushara Salawavidana 10 Push Roller and Truck Hitch Truck Hitch Engaged
  • 11. Hopper • The hopper is used as a temporary storage area for HMA delivered by the transport vehicle. • Therefore, the paver can accept more material than is immediately needed and can use the volume in the hopper to compensate for fluctuating material demands created by such things as paving over irregular grades, utility access openings or irregular intersection shapes. • Hopper sides (or “wings”) can be tilted up (or “folded”) to force material to the middle where it is carried to the rear by the conveyor system. Eng. Suneth Thushara Salawavidana 11
  • 12. Hopper • Hoppers can also be fit with inserts to allow them to carry more HMA. • These inserts are typically used in conjunction with a material transfer vehicle (MTV). Eng. Suneth Thushara Salawavidana 12 Hopper with Wings Folded Up Caterpillar AP-1055B with Hopper Insert
  • 13. Conveyor • The conveyor mechanism carries the HMA from the hopper, under the chassis and engine, then to the augers. • The amount of HMA carried back by the conveyors is regulated by either variable speed conveyors and augers or flow gates, which can be raised or lowered by the operator or, more often, by an automatic feed control system. Eng. Suneth Thushara Salawavidana 13 Conveyors (seen from the rear of a partially built paver)
  • 14. Auger • The auger receives HMA from the conveyor and spreads it out evenly over the width to be paved. • There is one auger for each side of the paver and they can be operated independently. • Some pavers allow the augers to be operated in reverse direction so that one can be operated forward and the other in reverse to send all the received HMA to one side of the paver. • The auger gearbox can either be located in the middle or on the outside edge of each auger. Eng. Suneth Thushara Salawavidana 14
  • 15. Auger • If an inadequate amount of HMA is distributed under a middle-located gearbox the result can be a thin longitudinal strip of mat aligned with the gearbox that exhibits lower densities from aggregate segregation and/or temperature differentials Eng. Suneth Thushara Salawavidana 15 Augers Distributing HMA
  • 16. PLACEMENT • Operation of the tractor, and specifically the material feed system, can have significant effects on overall construction quality and thus long-term pavement performance. • Although there are many detailed operational concerns, the two broad statements below encompass most of the detailed concerns: Eng. Suneth Thushara Salawavidana 16
  • 17. PLACEMENT • HMA must be delivered to maintain a relatively constant head of material in front of the screed. • This involves maintaining a minimum amount of HMA in the hopper, regulating HMA feed rate by controlling conveyor/auger speed and flow gate openings (if present), and maintaining a constant paving speed. • A fluctuating HMA head in front of the screed will affect the screed angle of attack and produce bumps and waves in the finished mat. Eng. Suneth Thushara Salawavidana 17
  • 18. PLACEMENT • The hopper should never be allowed to empty during paving. • This results in the leftover cold, large aggregate in the hopper sliding onto the conveyor in a concentrated mass and then being placed on the mat without mixing with any hot or fine aggregate. • This can produce aggregate segregation or temperature differentials, which will cause isolated low mat densities. • If there are no transport vehicles immediately available to refill the hopper it is better to stop the paving machine than to continue operating and empty the hopper. Eng. Suneth Thushara Salawavidana 18