SlideShare a Scribd company logo
#600 – 625 Howe Street, Vancouver, B.C. V6C 2T6
Ph.: (604) 683-6648 Fax: (604) 683-1350
E-Mail:highbank@telus.net
Website:www.highbankresources.com
TSX.V: HBK
SPN QUARRY PROJECT & LNG UPDATES
Vancouver, B.C. –February 19, 2015 – Highbank Resources Ltd. (the “Company”), TSX Venture: HBK.
Victor N. Bryant, CEO/President reports: “A crew at Swamp Point North (“SPN”) has recently returned to the site
and is active clearing snow, upgrading and maintaining roads, and logging/clearing further quarry area for
stockpiles. Khtada Environmental Services LP monitoring personnel were on site last week taking samples in
compliance with our Mines Act Permit. A supply barge left the Port of Prince Rupert, Wednesday morning to
arrive later today. The barge manifest included specific winter weather materials---chains for the 30 ton rock
trucks, corks/spikes for the bulldozer, winter camp supplies and additional large diameter culvert pipes for
appropriate road and drainage use.”
“I will be arriving at the SPN project today with Stan Spletzer (V.P. of Aggregate Operations) and Bill Faulhaffer
(Journeyman Quarry Operations Manager), who will be in charge of the day to day operations of our quarry
operation. Also accompanying us will be a Micon International engineer to commence work on the PEA study as
per our February 16, 2015 new release.”
“The SPN project crew was making ready to move on site for February 1, 2015 when a significant snow event
occurred. Presently, there is about three feet of snow on site, but we can see no reason that we, as a Canadian
Company are going to stop progress for snow. Additional crews are expecting to arrive to SPN Friday, February
20th
to further enhance roads; excavate discharge settling ponds for the wash plant; commission the wash plant,
move the jaw crusher to optimal positioning and commission the jaw crusher; install culverts for further water
runoff management; expand shoreline area for stockpiling and shipping finished aggregates; and last but not least,
commission the quarry and plant to process through the first of many barge loads of aggregate for 2015 sales.
LNG Developments:
‘Northern View’- Prince Rupert news….. Prince Rupert LNG (a partnership with BG Canada and The Westcoast
Connector Gas Transmission Project) have opened a community engagement office at 610 -2nd
Ave. in Prince
Rupert, B.C. and welcomes you to come by and visit them to discuss their Ridley Island LNG project or visit their
website at www.princerupertlng.ca
Also, Aurora LNG (a joint venture between Nexen Energy ULC- a CNOOC Limited company, INPEX
Corporation and JGC Exploration Canada Ltd.) will be opening their community office at 344, 2nd
Avenue West in
Prince Rupert in early March or visit their website at www.auroralng.com . For more information about the B.C.
environmental assessment process, go to www.eao.gov.bc.ca A Community Information Open House has taken
place on February 18th
in Prince Rupert in addition to the BC Environmental Assessment Office (BCEAO) –led
public comment periods that are part of the environmental assessment process. Aurora LNG is currently studying
the viability of constructing and operating a LNG facility and marine terminal, near Prince Rupert, on Digby
Island. Feedback received from the Open House will be considered by the Aurora Project team, along with
environmental, technical and socio-economic considerations.
On behalf of the Board of Directors of
HIGHBANK RESOURCES LTD.
“Victor N. Bryant”
Victor N. Bryant,
CEO/President
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
This news release may contain forward-looking statements based on assumptions and judgments of management regarding future events or
results. Forward-looking statements are projections of events, revenues, income, future economic performance or management’s plan and
objective for future operations and include, without limitation, statements with respect to the anticipated production from the Swamp Point
North Aggregate Project, the realization of mineral estimates, success of mining operations, the timing and amount of estimated future
production, title disputes or claims, environmental risks, limitations on insurance coverage, current and anticipated purchase negotiations and
arrangements, requirements for additional capital; and government regulation of mining operations. In some cases, you can identify forward-
looking statements by the use of terminology such as “may”, “should”, “expects”, “plans”, “anticipates”, “believes”, “estimates”,
“predicts”, “potential” or “continue” or the negative of these terms or other comparable terminology. By their very nature forward-looking
statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements
of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking
statements. Such factors, including: fluctuations in worldwide prices and demand for aggregates; changes in project parameters as plans
continue to be refined; possible variations in grade and or recovery rates; accidents, labour disputes as well as those factors detailed from time
to time in the Company's interim and annual financial statements and management's discussion and analysis of those statements, are filed and
available for review on SEDAR at www.sedar.com.

More Related Content

Viewers also liked

Ac 556
Ac 556Ac 556
Ac 556
murphy vivan
 
памятка уверенности
памятка уверенностипамятка уверенности
памятка уверенностиMihail Bukatin
 
Jornadas Politicas progresistas
Jornadas Politicas progresistasJornadas Politicas progresistas
Jornadas Politicas progresistas
Economistas Frente a la Crisis
 
Historia del parque natural de cabo de gata en almeria
Historia del parque natural de cabo de gata en almeriaHistoria del parque natural de cabo de gata en almeria
Historia del parque natural de cabo de gata en almeria
mariajemancho
 
Proctor
ProctorProctor
соколенко г.в. значение информационный технологий копия
соколенко г.в. значение информационный технологий    копиясоколенко г.в. значение информационный технологий    копия
соколенко г.в. значение информационный технологий копияТатьяна Дадатченко
 

Viewers also liked (6)

Ac 556
Ac 556Ac 556
Ac 556
 
памятка уверенности
памятка уверенностипамятка уверенности
памятка уверенности
 
Jornadas Politicas progresistas
Jornadas Politicas progresistasJornadas Politicas progresistas
Jornadas Politicas progresistas
 
Historia del parque natural de cabo de gata en almeria
Historia del parque natural de cabo de gata en almeriaHistoria del parque natural de cabo de gata en almeria
Historia del parque natural de cabo de gata en almeria
 
Proctor
ProctorProctor
Proctor
 
соколенко г.в. значение информационный технологий копия
соколенко г.в. значение информационный технологий    копиясоколенко г.в. значение информационный технологий    копия
соколенко г.в. значение информационный технологий копия
 

Similar to HIGHBANK SPN Quarry commissioning and LNG news update

Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Follow me on Twitter @Stockshaman
 
Hbk nr june 19.15 highbank resumes aggregate production
Hbk nr june 19.15 highbank resumes aggregate productionHbk nr june 19.15 highbank resumes aggregate production
Hbk nr june 19.15 highbank resumes aggregate production
Follow me on Twitter @Stockshaman
 
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Follow me on Twitter @Stockshaman
 
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Follow me on Twitter @Stockshaman
 
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Follow me on Twitter @Stockshaman
 
Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing
Follow me on Twitter @Stockshaman
 
Hbk.nr dec.1.16
Hbk.nr dec.1.16Hbk.nr dec.1.16
B.C. LNG Infrastructure Build Commences
B.C. LNG Infrastructure Build CommencesB.C. LNG Infrastructure Build Commences
B.C. LNG Infrastructure Build Commences
Follow me on Twitter @Stockshaman
 
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
Follow me on Twitter @Stockshaman
 
Highbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW NewsHighbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW News
Follow me on Twitter @Stockshaman
 
Highbank Year-End Update
Highbank Year-End UpdateHighbank Year-End Update
Highbank Year-End Update
Follow me on Twitter @Stockshaman
 
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Follow me on Twitter @Stockshaman
 
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 PresentationHighbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Follow me on Twitter @Stockshaman
 
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Follow me on Twitter @Stockshaman
 
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Viral Network Inc
 
BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...
BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...
BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...
Follow me on Twitter @Stockshaman
 
Highbank Appoints Hans Smit, P. Geo. To Its Advisory Board
Highbank Appoints Hans Smit, P. Geo. To Its Advisory BoardHighbank Appoints Hans Smit, P. Geo. To Its Advisory Board
Highbank Appoints Hans Smit, P. Geo. To Its Advisory Board
Follow me on Twitter @Stockshaman
 
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 PresentationHighbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Follow me on Twitter @Stockshaman
 
Pacific Northwest BC News & Management Agreement with CEO
 Pacific Northwest BC News & Management Agreement with CEO Pacific Northwest BC News & Management Agreement with CEO
Pacific Northwest BC News & Management Agreement with CEO
Follow me on Twitter @Stockshaman
 
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Follow me on Twitter @Stockshaman
 

Similar to HIGHBANK SPN Quarry commissioning and LNG news update (20)

Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
 
Hbk nr june 19.15 highbank resumes aggregate production
Hbk nr june 19.15 highbank resumes aggregate productionHbk nr june 19.15 highbank resumes aggregate production
Hbk nr june 19.15 highbank resumes aggregate production
 
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
 
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
 
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
 
Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing
 
Hbk.nr dec.1.16
Hbk.nr dec.1.16Hbk.nr dec.1.16
Hbk.nr dec.1.16
 
B.C. LNG Infrastructure Build Commences
B.C. LNG Infrastructure Build CommencesB.C. LNG Infrastructure Build Commences
B.C. LNG Infrastructure Build Commences
 
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
 
Highbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW NewsHighbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW News
 
Highbank Year-End Update
Highbank Year-End UpdateHighbank Year-End Update
Highbank Year-End Update
 
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
 
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 PresentationHighbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
 
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
 
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permi...
 
BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...
BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...
BEA-TSXV NEWS 01.16.18 Belmont secures quantec geoscience to conduct mt resis...
 
Highbank Appoints Hans Smit, P. Geo. To Its Advisory Board
Highbank Appoints Hans Smit, P. Geo. To Its Advisory BoardHighbank Appoints Hans Smit, P. Geo. To Its Advisory Board
Highbank Appoints Hans Smit, P. Geo. To Its Advisory Board
 
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 PresentationHighbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
 
Pacific Northwest BC News & Management Agreement with CEO
 Pacific Northwest BC News & Management Agreement with CEO Pacific Northwest BC News & Management Agreement with CEO
Pacific Northwest BC News & Management Agreement with CEO
 
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
 

More from Follow me on Twitter @Stockshaman

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
Follow me on Twitter @Stockshaman
 
Imt black fly mobilization and permit
Imt black fly mobilization and permitImt black fly mobilization and permit
Imt black fly mobilization and permit
Follow me on Twitter @Stockshaman
 
PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]
Follow me on Twitter @Stockshaman
 
Lamontage down hole probe data pecors
Lamontage down hole probe data pecorsLamontage down hole probe data pecors
Lamontage down hole probe data pecors
Follow me on Twitter @Stockshaman
 
Rich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources incRich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources inc
Follow me on Twitter @Stockshaman
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Follow me on Twitter @Stockshaman
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
Follow me on Twitter @Stockshaman
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
Follow me on Twitter @Stockshaman
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
Follow me on Twitter @Stockshaman
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
Follow me on Twitter @Stockshaman
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
Follow me on Twitter @Stockshaman
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
Follow me on Twitter @Stockshaman
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Follow me on Twitter @Stockshaman
 
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Follow me on Twitter @Stockshaman
 
Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018
Follow me on Twitter @Stockshaman
 
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Follow me on Twitter @Stockshaman
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
Follow me on Twitter @Stockshaman
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
Follow me on Twitter @Stockshaman
 

More from Follow me on Twitter @Stockshaman (20)

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
 
Imt black fly mobilization and permit
Imt black fly mobilization and permitImt black fly mobilization and permit
Imt black fly mobilization and permit
 
PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]
 
Lamontage down hole probe data pecors
Lamontage down hole probe data pecorsLamontage down hole probe data pecors
Lamontage down hole probe data pecors
 
Rich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources incRich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources inc
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
 
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
 
Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018
 
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
 

Recently uploaded

Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24
Philip Rabenok
 
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
f3wjr2q2
 
Cleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is BlueCleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is Blue
Cleades Robinson
 
Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024
CollectiveMining1
 
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptxUnderstanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
cosmo-soil
 
ppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.pptppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.ppt
TestOrg1
 
2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf
Sysco_Investors
 
Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024
Methanex Corporation
 
Mandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPTMandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPT
MandalayResources
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdf
CyberAgent, Inc.
 
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
SOFTTECHHUB
 
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUESMUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
WilliamRodrigues148
 
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
ybout
 
AGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdfAGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdf
Probe Gold
 

Recently uploaded (14)

Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24Osisko Development - Investor Presentation - June 24
Osisko Development - Investor Presentation - June 24
 
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
快速办理(CUBoulder毕业证书)科罗拉多大学博尔德分校毕业证录取通知书一模一样
 
Cleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is BlueCleades robinson:The Diplomat is Blue
Cleades robinson:The Diplomat is Blue
 
Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024Collective Mining | Corporate Presentation - June 2024
Collective Mining | Corporate Presentation - June 2024
 
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptxUnderstanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
Understanding-the-E-Way-Bill-A-Digital-Transformation-in-Logistics.pptx
 
ppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.pptppt-namibia-worldeconomy-standardbank.ppt
ppt-namibia-worldeconomy-standardbank.ppt
 
2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf2024-deutsche-bank-global-consumer-conference.pdf
2024-deutsche-bank-global-consumer-conference.pdf
 
Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024Methanex Investor Presentation - April 2024
Methanex Investor Presentation - April 2024
 
Mandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPTMandalay Resouces June 2024 Investor Relations PPT
Mandalay Resouces June 2024 Investor Relations PPT
 
Cyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdfCyberagent_For New Investors_EN_240424.pdf
Cyberagent_For New Investors_EN_240424.pdf
 
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdfZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
ZKsync airdrop of 3.6 billion ZK tokens is scheduled by ZKsync for next week.pdf
 
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUESMUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
MUTUAL FUNDS (ICICI Prudential Mutual Fund) BY JAMES RODRIGUES
 
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
一比一原版(UW毕业证)华盛顿大学毕业证成绩单专业办理
 
AGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdfAGM Presentation Probe June 11 Final.pdf
AGM Presentation Probe June 11 Final.pdf
 

HIGHBANK SPN Quarry commissioning and LNG news update

  • 1. #600 – 625 Howe Street, Vancouver, B.C. V6C 2T6 Ph.: (604) 683-6648 Fax: (604) 683-1350 E-Mail:highbank@telus.net Website:www.highbankresources.com TSX.V: HBK SPN QUARRY PROJECT & LNG UPDATES Vancouver, B.C. –February 19, 2015 – Highbank Resources Ltd. (the “Company”), TSX Venture: HBK. Victor N. Bryant, CEO/President reports: “A crew at Swamp Point North (“SPN”) has recently returned to the site and is active clearing snow, upgrading and maintaining roads, and logging/clearing further quarry area for stockpiles. Khtada Environmental Services LP monitoring personnel were on site last week taking samples in compliance with our Mines Act Permit. A supply barge left the Port of Prince Rupert, Wednesday morning to arrive later today. The barge manifest included specific winter weather materials---chains for the 30 ton rock trucks, corks/spikes for the bulldozer, winter camp supplies and additional large diameter culvert pipes for appropriate road and drainage use.” “I will be arriving at the SPN project today with Stan Spletzer (V.P. of Aggregate Operations) and Bill Faulhaffer (Journeyman Quarry Operations Manager), who will be in charge of the day to day operations of our quarry operation. Also accompanying us will be a Micon International engineer to commence work on the PEA study as per our February 16, 2015 new release.” “The SPN project crew was making ready to move on site for February 1, 2015 when a significant snow event occurred. Presently, there is about three feet of snow on site, but we can see no reason that we, as a Canadian Company are going to stop progress for snow. Additional crews are expecting to arrive to SPN Friday, February 20th to further enhance roads; excavate discharge settling ponds for the wash plant; commission the wash plant, move the jaw crusher to optimal positioning and commission the jaw crusher; install culverts for further water runoff management; expand shoreline area for stockpiling and shipping finished aggregates; and last but not least, commission the quarry and plant to process through the first of many barge loads of aggregate for 2015 sales. LNG Developments: ‘Northern View’- Prince Rupert news….. Prince Rupert LNG (a partnership with BG Canada and The Westcoast Connector Gas Transmission Project) have opened a community engagement office at 610 -2nd Ave. in Prince Rupert, B.C. and welcomes you to come by and visit them to discuss their Ridley Island LNG project or visit their website at www.princerupertlng.ca Also, Aurora LNG (a joint venture between Nexen Energy ULC- a CNOOC Limited company, INPEX Corporation and JGC Exploration Canada Ltd.) will be opening their community office at 344, 2nd Avenue West in Prince Rupert in early March or visit their website at www.auroralng.com . For more information about the B.C. environmental assessment process, go to www.eao.gov.bc.ca A Community Information Open House has taken place on February 18th in Prince Rupert in addition to the BC Environmental Assessment Office (BCEAO) –led public comment periods that are part of the environmental assessment process. Aurora LNG is currently studying the viability of constructing and operating a LNG facility and marine terminal, near Prince Rupert, on Digby Island. Feedback received from the Open House will be considered by the Aurora Project team, along with environmental, technical and socio-economic considerations.
  • 2. On behalf of the Board of Directors of HIGHBANK RESOURCES LTD. “Victor N. Bryant” Victor N. Bryant, CEO/President Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. This news release may contain forward-looking statements based on assumptions and judgments of management regarding future events or results. Forward-looking statements are projections of events, revenues, income, future economic performance or management’s plan and objective for future operations and include, without limitation, statements with respect to the anticipated production from the Swamp Point North Aggregate Project, the realization of mineral estimates, success of mining operations, the timing and amount of estimated future production, title disputes or claims, environmental risks, limitations on insurance coverage, current and anticipated purchase negotiations and arrangements, requirements for additional capital; and government regulation of mining operations. In some cases, you can identify forward- looking statements by the use of terminology such as “may”, “should”, “expects”, “plans”, “anticipates”, “believes”, “estimates”, “predicts”, “potential” or “continue” or the negative of these terms or other comparable terminology. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors, including: fluctuations in worldwide prices and demand for aggregates; changes in project parameters as plans continue to be refined; possible variations in grade and or recovery rates; accidents, labour disputes as well as those factors detailed from time to time in the Company's interim and annual financial statements and management's discussion and analysis of those statements, are filed and available for review on SEDAR at www.sedar.com.