HIGHBANK RECEIVES COMMENTS ON NOTICE OF WORK (NoW) PERMIT
APPLICATION FOR ITS SWAMP POINT NORTH AGGREGATE PROJECT.
Vancouver, B.C. – December 6, 2013 – Highbank Resources Ltd. (the “Company”) (TSX Venture: HBK). Further
to our news release on October 29, 2013, the Company has received review comments from the Ministry of Energy
and Mines (“MEM”) indicating the results of MEM’s review and future expectations for this particular project in
regards only to the Mines Act permitting.
The Regional Director of MEM, Smithers has made a decision in regards to our project, to establish a Mine
Development Review Committee (MDRC), pursuant to Part 10.3.1 of the Health, Safety and Reclamation Code for
Mines in B.C., to meet in early 2014. The MDRC will provide an opportunity for the Company, pertinent regulators
and First Nations to gather and discuss requirements of the project as it relates to both federal and provincial
regulatory authorities.
The Company and Micon International Limited will be reviewing the response and begin compiling its reply as soon
as possible in preparation for discussion with the MDRC.
Victor N. Bryant-CEO/President, James H. Place-Director, and Stan Spletzer, V.P. of Operations will be travelling
to Prince Rupert on Tuesday. The Company will be meeting with representatives from the Metlakatla First Nation
(Prince Rupert), site of the Petronas $18 billion proposed liquefied natural gas (LNG) export facility, on Lelu Island
within the District of Port Edward on land administered by the Port of Prince Rupert. Also included in the meeting
will be a representative from the Lax Kw’alaams Band (Port Simpson- nearby Grassy Point), where China’s
CNOOC Ltd. has secured exclusive rights with Japan’s Inpex Corp. and JGC Corp. to examine building a LNG
export plant and terminal. These discussions will center on further joint venture participations with the First Nations
as they will be involved in the public consultations and potential partnerships of these builds. It was hoped that a
similar meeting could be arranged with the heads of the Nisga’a Lisims Government at the same time, unfortunately
they were not available as they are currently attending meetings in Ottawa.
On behalf of the Board of Directors of
HIGHBANK RESOURCES LTD.
“Victor N. Bryant”
Victor N. Bryant,
CEO/President
This News Release may contain forward-looking statements based on assumptions and judgments of management regarding future events or
results that may prove to be inaccurate as a result of exploration and other risk factors beyond its control, and actual results may differ
materially from the expected results.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

More Related Content

Viewers also liked

Released August 19th, 2016 - Fundamental Research Corp. has updated their res...
Released August 19th, 2016 - Fundamental Research Corp. has updated their res...Released August 19th, 2016 - Fundamental Research Corp. has updated their res...
Released August 19th, 2016 - Fundamental Research Corp. has updated their res...Follow me on Twitter @Stockshaman
 
Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...
Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...
Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...Follow me on Twitter @Stockshaman
 
Bea .july15.16 results of annual general meeting of shareholders.final [1887620]
Bea .july15.16 results of annual general meeting of shareholders.final [1887620]Bea .july15.16 results of annual general meeting of shareholders.final [1887620]
Bea .july15.16 results of annual general meeting of shareholders.final [1887620]Follow me on Twitter @Stockshaman
 
Highbank reports approvals, updates-swamp point north oltc lng conferences a...
Highbank reports approvals, updates-swamp point north  oltc lng conferences a...Highbank reports approvals, updates-swamp point north  oltc lng conferences a...
Highbank reports approvals, updates-swamp point north oltc lng conferences a...Follow me on Twitter @Stockshaman
 
HIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERS
HIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERSHIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERS
HIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERSFollow me on Twitter @Stockshaman
 
Highbank’s Swamp Point North Aggregate Project NoW Application
Highbank’s Swamp Point North Aggregate Project NoW ApplicationHighbank’s Swamp Point North Aggregate Project NoW Application
Highbank’s Swamp Point North Aggregate Project NoW ApplicationFollow me on Twitter @Stockshaman
 

Viewers also liked (7)

Released August 19th, 2016 - Fundamental Research Corp. has updated their res...
Released August 19th, 2016 - Fundamental Research Corp. has updated their res...Released August 19th, 2016 - Fundamental Research Corp. has updated their res...
Released August 19th, 2016 - Fundamental Research Corp. has updated their res...
 
Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...
Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...
Hbk nr. july 24.14 highbank continues mobilizing & development at swamp point...
 
Bea .july15.16 results of annual general meeting of shareholders.final [1887620]
Bea .july15.16 results of annual general meeting of shareholders.final [1887620]Bea .july15.16 results of annual general meeting of shareholders.final [1887620]
Bea .july15.16 results of annual general meeting of shareholders.final [1887620]
 
Highbank reports approvals, updates-swamp point north oltc lng conferences a...
Highbank reports approvals, updates-swamp point north  oltc lng conferences a...Highbank reports approvals, updates-swamp point north  oltc lng conferences a...
Highbank reports approvals, updates-swamp point north oltc lng conferences a...
 
Highbank Resources - MDRC Presentation
Highbank Resources - MDRC PresentationHighbank Resources - MDRC Presentation
Highbank Resources - MDRC Presentation
 
HIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERS
HIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERSHIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERS
HIGHBANK ANNOUNCES RESULTS OF ANNUAL GENERAL MEETING OF SHAREHOLDERS
 
Highbank’s Swamp Point North Aggregate Project NoW Application
Highbank’s Swamp Point North Aggregate Project NoW ApplicationHighbank’s Swamp Point North Aggregate Project NoW Application
Highbank’s Swamp Point North Aggregate Project NoW Application
 

Similar to Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permit Application For Its Swamp Point North Aggregate Project

Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...Follow me on Twitter @Stockshaman
 
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...Follow me on Twitter @Stockshaman
 
Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing Follow me on Twitter @Stockshaman
 
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...Follow me on Twitter @Stockshaman
 
Highbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW NewsHighbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW NewsFollow me on Twitter @Stockshaman
 
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...Follow me on Twitter @Stockshaman
 
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...Follow me on Twitter @Stockshaman
 
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...Follow me on Twitter @Stockshaman
 
Highbank Resources Proceeding with 3rd Tranche & Oversubscriptions of Financing
Highbank Resources Proceeding with 3rd Tranche & Oversubscriptions of FinancingHighbank Resources Proceeding with 3rd Tranche & Oversubscriptions of Financing
Highbank Resources Proceeding with 3rd Tranche & Oversubscriptions of FinancingFollow me on Twitter @Stockshaman
 
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...Follow me on Twitter @Stockshaman
 
NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...
NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...
NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...Follow me on Twitter @Stockshaman
 
Preliminary Economic Assessment For Swamp Point North Aggregate Project
Preliminary Economic Assessment For Swamp Point North Aggregate Project Preliminary Economic Assessment For Swamp Point North Aggregate Project
Preliminary Economic Assessment For Swamp Point North Aggregate Project Follow me on Twitter @Stockshaman
 
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 PresentationHighbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 PresentationFollow me on Twitter @Stockshaman
 
Hbk nr aug.20. 14 finalizes barge load-out and piling contract other
Hbk nr  aug.20. 14  finalizes barge load-out and piling contract  otherHbk nr  aug.20. 14  finalizes barge load-out and piling contract  other
Hbk nr aug.20. 14 finalizes barge load-out and piling contract otherFollow me on Twitter @Stockshaman
 
HBK News - BC Government Approves Bill 30, the LNG Project Agreements Act
HBK News -  BC Government Approves Bill 30, the LNG Project Agreements ActHBK News -  BC Government Approves Bill 30, the LNG Project Agreements Act
HBK News - BC Government Approves Bill 30, the LNG Project Agreements ActFollow me on Twitter @Stockshaman
 

Similar to Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permit Application For Its Swamp Point North Aggregate Project (20)

Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
Highbank NEWS May 23.2017 Highbank arranges demand loan for $100,000 & pr...
 
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
Highbank Resources Updates SPN Work & Comments on an estimated $154 Billion i...
 
Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing Highbank Resources Closes $350,400 Second Tranche of Financing
Highbank Resources Closes $350,400 Second Tranche of Financing
 
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
HIGHBANK (HBK-TSXV) (HBKRF-U.S.) NEWS FIRST NATIONS APPROVE OIL & GAS PIPELIN...
 
Highbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW NewsHighbank Closes First Tranche of P.P. and Updates Pacific NW News
Highbank Closes First Tranche of P.P. and Updates Pacific NW News
 
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
Highbank Completes 1st Tranche of Private Placement for $91,500 & LNG in the ...
 
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
Highbank Receives Amended Mines Act Permit on its Swamp Point North Aggregate...
 
HIGHBANK SPN Quarry commissioning and LNG news update
HIGHBANK SPN Quarry commissioning and LNG news update HIGHBANK SPN Quarry commissioning and LNG news update
HIGHBANK SPN Quarry commissioning and LNG news update
 
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
Canadian Environmental Assessment Agency Rules Petronas Led LNG Project Could...
 
Highbank Ships Crusher & Wash Plant to Swamp Point North
Highbank Ships Crusher & Wash Plant to Swamp Point NorthHighbank Ships Crusher & Wash Plant to Swamp Point North
Highbank Ships Crusher & Wash Plant to Swamp Point North
 
B.C. LNG Infrastructure Build Commences
B.C. LNG Infrastructure Build CommencesB.C. LNG Infrastructure Build Commences
B.C. LNG Infrastructure Build Commences
 
Hbk.nr dec.1.16
Hbk.nr dec.1.16Hbk.nr dec.1.16
Hbk.nr dec.1.16
 
Highbank Resources Proceeding with 3rd Tranche & Oversubscriptions of Financing
Highbank Resources Proceeding with 3rd Tranche & Oversubscriptions of FinancingHighbank Resources Proceeding with 3rd Tranche & Oversubscriptions of Financing
Highbank Resources Proceeding with 3rd Tranche & Oversubscriptions of Financing
 
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
Highbank Arranges Shares for Debt for $565,343 Convertible Debenture Interest...
 
Pacific Northwest BC News & Management Agreement with CEO
 Pacific Northwest BC News & Management Agreement with CEO Pacific Northwest BC News & Management Agreement with CEO
Pacific Northwest BC News & Management Agreement with CEO
 
NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...
NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...
NEWS RELEASE HIGHBANK PRESENTS PERMIT APPLICATION TO B.C. REGIONAL...
 
Preliminary Economic Assessment For Swamp Point North Aggregate Project
Preliminary Economic Assessment For Swamp Point North Aggregate Project Preliminary Economic Assessment For Swamp Point North Aggregate Project
Preliminary Economic Assessment For Swamp Point North Aggregate Project
 
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 PresentationHighbank Resources Ltd. (HBK.V) - February 2015 Presentation
Highbank Resources Ltd. (HBK.V) - February 2015 Presentation
 
Hbk nr aug.20. 14 finalizes barge load-out and piling contract other
Hbk nr  aug.20. 14  finalizes barge load-out and piling contract  otherHbk nr  aug.20. 14  finalizes barge load-out and piling contract  other
Hbk nr aug.20. 14 finalizes barge load-out and piling contract other
 
HBK News - BC Government Approves Bill 30, the LNG Project Agreements Act
HBK News -  BC Government Approves Bill 30, the LNG Project Agreements ActHBK News -  BC Government Approves Bill 30, the LNG Project Agreements Act
HBK News - BC Government Approves Bill 30, the LNG Project Agreements Act
 

More from Follow me on Twitter @Stockshaman

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...Follow me on Twitter @Stockshaman
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Follow me on Twitter @Stockshaman
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...Follow me on Twitter @Stockshaman
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryFollow me on Twitter @Stockshaman
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...Follow me on Twitter @Stockshaman
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...Follow me on Twitter @Stockshaman
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...Follow me on Twitter @Stockshaman
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...Follow me on Twitter @Stockshaman
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Follow me on Twitter @Stockshaman
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Follow me on Twitter @Stockshaman
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...Follow me on Twitter @Stockshaman
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...Follow me on Twitter @Stockshaman
 

More from Follow me on Twitter @Stockshaman (20)

MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
MONTORO RESOURCES ENTERS INTO FINANCING FACILITY UP TO $2-MILLION CAD AND APP...
 
Imt black fly mobilization and permit
Imt black fly mobilization and permitImt black fly mobilization and permit
Imt black fly mobilization and permit
 
PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]PDAC 2020 ppp hand out 2020 [autosaved]
PDAC 2020 ppp hand out 2020 [autosaved]
 
Lamontage down hole probe data pecors
Lamontage down hole probe data pecorsLamontage down hole probe data pecors
Lamontage down hole probe data pecors
 
Rich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources incRich tv 2019 international montoro resources inc
Rich tv 2019 international montoro resources inc
 
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
Montoro NEWS release 03.12.19 doubles size estimate of Pecors Nickel copper p...
 
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
ZTEM 2D Synthetic Modelling - Pecors Magmatic Massive Sulphide Target - Power...
 
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summaryInternational Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
International Montoro Res. Wicheeda North_Mag_Em_inv_interp_summary
 
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
International Montoro Resources Inc. Wicheeda (Rare Earth Element, REE) proje...
 
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
International Montoro Res.(IMT.V) (IMTFF-OTC) (O4T1- Franfurt) Wicheeda North...
 
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
International Montoro Resources Inc. (IMTFF- USA) (IMT -TSXV) (O4T1-Frankfurt...
 
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
International Montoro Res. Conductivity  2 d ztem inversion start model test ...International Montoro Res. Conductivity  2 d ztem inversion start model test ...
International Montoro Res. Conductivity 2 d ztem inversion start model test ...
 
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...Montoro - Serpent River, Ontario  Ni Cu PGE project  2D Geotech ZTEM survey r...
Montoro - Serpent River, Ontario Ni Cu PGE project 2D Geotech ZTEM survey r...
 
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
Ppt 3 d geotechppp 3d_ztem_inversion_results_v4
 
Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018Geotech IMT ZTEM 3d ppp Nov.2018
Geotech IMT ZTEM 3d ppp Nov.2018
 
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028Benchmark Megafactory Assessment exceeds 1 TWh by 2028
Benchmark Megafactory Assessment exceeds 1 TWh by 2028
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
Belmont to DRILL for #lithium brine #Nevada November - KB3- 139 feet 393ppm #...
 
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...International Montoro Resources (IMT-TSXV) Duhamel,Quebec -  Ni, Cu, Co, Ti, ...
International Montoro Resources (IMT-TSXV) Duhamel,Quebec - Ni, Cu, Co, Ti, ...
 
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
NEWS Montoro adds #Vanadium Titanium #Chromium ground@ Duhamel -#Nickel #Copp...
 

Highbank Resources - Highbank Receives Comments on Notice of Work (NoW) Permit Application For Its Swamp Point North Aggregate Project

  • 1. #600 – 625 Howe Street, Vancouver, B.C. V6C 2T6 Ph: (604) 683-6648 Fax: (604) 683-1350 E-Mail: highbank@telus.net www.highbankresources.com TSX.V: HBK Frankfurt: V7O HIGHBANK RECEIVES COMMENTS ON NOTICE OF WORK (NoW) PERMIT APPLICATION FOR ITS SWAMP POINT NORTH AGGREGATE PROJECT. Vancouver, B.C. – December 6, 2013 – Highbank Resources Ltd. (the “Company”) (TSX Venture: HBK). Further to our news release on October 29, 2013, the Company has received review comments from the Ministry of Energy and Mines (“MEM”) indicating the results of MEM’s review and future expectations for this particular project in regards only to the Mines Act permitting. The Regional Director of MEM, Smithers has made a decision in regards to our project, to establish a Mine Development Review Committee (MDRC), pursuant to Part 10.3.1 of the Health, Safety and Reclamation Code for Mines in B.C., to meet in early 2014. The MDRC will provide an opportunity for the Company, pertinent regulators and First Nations to gather and discuss requirements of the project as it relates to both federal and provincial regulatory authorities. The Company and Micon International Limited will be reviewing the response and begin compiling its reply as soon as possible in preparation for discussion with the MDRC. Victor N. Bryant-CEO/President, James H. Place-Director, and Stan Spletzer, V.P. of Operations will be travelling to Prince Rupert on Tuesday. The Company will be meeting with representatives from the Metlakatla First Nation (Prince Rupert), site of the Petronas $18 billion proposed liquefied natural gas (LNG) export facility, on Lelu Island within the District of Port Edward on land administered by the Port of Prince Rupert. Also included in the meeting will be a representative from the Lax Kw’alaams Band (Port Simpson- nearby Grassy Point), where China’s CNOOC Ltd. has secured exclusive rights with Japan’s Inpex Corp. and JGC Corp. to examine building a LNG export plant and terminal. These discussions will center on further joint venture participations with the First Nations as they will be involved in the public consultations and potential partnerships of these builds. It was hoped that a similar meeting could be arranged with the heads of the Nisga’a Lisims Government at the same time, unfortunately they were not available as they are currently attending meetings in Ottawa. On behalf of the Board of Directors of HIGHBANK RESOURCES LTD. “Victor N. Bryant” Victor N. Bryant, CEO/President This News Release may contain forward-looking statements based on assumptions and judgments of management regarding future events or results that may prove to be inaccurate as a result of exploration and other risk factors beyond its control, and actual results may differ materially from the expected results. Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.