SlideShare a Scribd company logo
1 of 3
Download to read offline
Asia Pacific Projects Update
FORCE MAJEURE CLAUSES –
REVISITED
KEY CONTACT
Damian McNair
Partner, Head of Finance & Projects, Asia Pacific
T +61 3 9274 5379
damian.mcnair@dlapiper.com
INTRODUCTION
Force majeure clauses in project agreements are common,
however, the amount of time spent negotiating those
clauses is often minimal. Generally, the assumption
appears to be that the risk will not affect us or the force
majeure clause is a legal necessity and does not impact on
our risk allocation under the contract. Both of these
assumptions are inherently dangerous and, particularly in
the second case, incorrect.
This paper follows from last fortnight's paper on force
majeure clauses and considers the drafting of those
clauses.
RISK ALLOCATION
The appropriate allocation of risk in project agreements is
fundamental to negotiations between the project company
and its contractors. Risks generally fall into the following
categories:
 Risks within the control of the project company
 Risks within the control of the contractor
 Risks outside the control of both parties.
The negotiation of the allocation of many of the risks
beyond the control of the parties, for example, latent site
conditions and change of law, is usually very detailed so
that it is clear which risks are borne by the contractor. The
same approach should be adopted in relation to the risks
arising from events of force majeure.
OPERATION OF FORCE MAJEURE CLAUSES
There are two aspects to the operation of force majeure
clauses:
 The definition of force majeure events
 The operative clause that sets out the effect on the
parties’ rights and obligations if a force majeure event
occurs.
Definition
The events that trigger the operative clause must be
clearly defined. Given the common law meaning of the
term force majeure is not certain and is open to
interpretation of the courts, it is in the interests of both
parties to ensure that the term force majeure is clearly
defined.
The preferred approach for a project company is to define
force majeure events as being any of the events in an
exhaustive list set out in the contract. In this manner, both
parties are aware of which events are force majeure events
and which are not. Clearly, defining force majeure events
makes the administration of the contract and, in particular,
the mechanism within the contract for dealing with force
majeure events simpler and more effective.
2  Force Majeure Clauses – Revisited
Operative clause
An operative clause will act as a shield for the party
affected by the event of force majeure so that a party can
rely on that clause as a defence to a claim that it has failed
to fulfil its obligations under the contract.
An operative clause should also specifically deal with the
rights and obligations of the parties if a force majeure
event occurs and affects the project. This means the
parties must consider each of the events that it intends to
include in the definition of force majeure events and then
to deal with what the parties will do if one of those events
occurs.
DRAFTING FORCE MAJEURE CLAUSES
Definition
An example of an exhaustive definition of force majeure
is:
"An event of force majeure is an event or circumstance
which is beyond the control and without the fault or
negligence of the party affected and which by the exercise
of reasonable diligence the party affected was unable to
prevent provided that event or circumstance is limited to
the following:
(a) riot, war, invasion, act of foreign enemies,
hostilities (whether war be declared or not) acts of
terrorism, civil war, rebellion, revolution,
insurrection of military or usurped power,
requisition or compulsory acquisition by any
governmental or competent authority;
(b) ionising radiation or contamination, radio activity
from any nuclear fuel or from any nuclear waste
from the combustion of nuclear fuel, radio active
toxic explosive or other hazardous properties of
any explosive assembly or nuclear component;
(c) pressure waves caused by aircraft or other aerial
devices travelling at sonic or supersonic speeds;
(d) earthquakes, flood, fire or other physical natural
disaster, but excluding weather conditions
regardless of severity; and
(e) strikes at national level or industrial disputes at a
national level, or strike or industrial disputes by
labour not employed by the affected party, its
subcontractors or its suppliers and which affect an
essential portion of the works but excluding any
industrial dispute which is specific to the
performance of the works or this contract."
The list of events to be included in this type of definition
is a matter for negotiation between the parties. In general,
it is preferable for a project company to have a short list of
events as the contractor is the party most likely to be
affected by force majeure events. The actual process of
negotiating this list clearly identifies the risk allocation
between the parties.
Operative clause
An example of an operative clause is:
"[ ].1 Neither party is responsible for any failure to
perform its obligations under this contract, if it is
prevented or delayed in performing those obligations by
an event of force majeure.
[ ].2 Where there is an event of force majeure, the party
prevented from or delayed in performing its obligations
under this contract must immediately notify the other
party giving full particulars of the event of force majeure
and the reasons for the event of force majeure preventing
that party from, or delaying that party in performing its
obligations under this contract and that party must use its
reasonable efforts to mitigate the effect of the event of
force majeure upon its or their performance of the
contract and to fulfil its or their obligations under the
contract.
[ ].3 Upon completion of the event of force majeure the
party affected must as soon as reasonably practicable
recommence the performance of its obligations under this
contract. Where the party affected is the contractor, the
contractor must provide a revised programme
rescheduling the works to minimise the effects of the
prevention or delay caused by the event of force majeure.
[ ].4 An event of force majeure does not relieve a party
from liability for an obligation which arose before the
occurrence of that event, nor does that event affect the
obligation to pay money in a timely manner which
matured prior to the occurrence of that event.
[ ].5 The contractor has no entitlement and the project
company has no liability for:
(a) any costs, losses, expenses, damages or the
payment of any part of the contract price during an
event of force majeure; and
(b) any delay costs in any way incurred by the
contractor due to an event of force majeure."
In addition to the above clause, it is important to
appropriately deal with other issues that will arise if a
force majeure event occurs. For example, it is common
practice for a contractor to be entitled to an extension of
time if a force majeure event impacts on its ability to
perform the works. For this reason, force majeure is
usually referred to in the extension of time mechanism as
an event which will entitle the contractor to an extension
of time.
Another key clause that relates to force majeure type
events is the contractor’s responsibility for care of the
3  Force Majeure Clauses – Revisited
works and the obligation to reinstate any damage to the
works prior to completion. A common example clause is:
"[ ].1 The contractor is responsible for the care of the site
and the works from when the project company makes the
site available to the contractor until 5.00pm on the date of
practical completion.
[ ].2 The contractor must promptly make good loss from,
or damage to, any part of the site and the works while it is
responsible for their care.
[ ].3 If the loss or damage is caused by an event of force
majeure, the project company may direct the contractor to
reinstate the works or change the works. The cost of the
reinstatement work or any change to the works arising
from a direction by the project company under this clause
will be dealt with as a variation except to the extent that
the loss or damage has been caused or exacerbated by the
failure of the contractor to fulfil its obligations under this
contract.
[ ].4 Except as contemplated in clause [ ].3, the cost of all
reinstatement works will be borne by the contractor."
CONCLUSION
It is important for a project company and its contractors to
carefully consider the definition of force majeure and how
an event of force majeure will affect their rights and
obligations under the contract.
The drafting of force majeure definitions and operative
clauses (including related clauses) should clearly define
the risk allocation between the parties. The above example
clauses have been used to demonstrate some options
available for dealing with events of force majeure. The
specific issues that need to be considered when drafting
force majeure clauses will depend on a variety of factors.
www.dlapiper.com
DLA Piper is a global law firm operating through various separate
and distinct legal entities.
For further information, please refer to www.dlapiper.com
Copyright © 2012 DLA Piper. All rights reserved.
1110409668  DLA188  0611

More Related Content

Similar to Force Majeure Clauses Drafting Tips

المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدEgyptian Engineers Association
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
LEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and bestLEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and best2cd
 
An Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private PartnershipAn Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private PartnershipStephen Faucher
 
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Construction in Focus
 
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...Dr. Oliver Massmann
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractPavitrah Segaran
 
Your Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter MostYour Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter MostAlex Barthet
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingRHKLegal
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction ProjectsLaina Chan
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTXRyan Hatton
 
Issues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticeIssues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticePalecek & Palecek, PLLC
 
Force Majeure Clauses in the Wake of COVID-19
Force Majeure Clauses in the Wake of COVID-19Force Majeure Clauses in the Wake of COVID-19
Force Majeure Clauses in the Wake of COVID-19Parsons Behle & Latimer
 

Similar to Force Majeure Clauses Drafting Tips (20)

المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
LEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and bestLEC - 1.ppt most important lecture note and best
LEC - 1.ppt most important lecture note and best
 
An Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private PartnershipAn Assignment On Risks In Public Private Partnership
An Assignment On Risks In Public Private Partnership
 
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
Likely effects of the COVID-19 pandemic on force majeure and EOT contract cla...
 
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
VIETNAM – COVID 19 – FORCE MAJEURE - HOW YOU CAN PREPARE FOR FORCE MAJEURE – ...
 
clause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contractclause 51.0 and 53.0 - contract
clause 51.0 and 53.0 - contract
 
Your Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter MostYour Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter Most
 
Hanscomb Intercontinental - UK Force majeure
Hanscomb Intercontinental - UK Force majeureHanscomb Intercontinental - UK Force majeure
Hanscomb Intercontinental - UK Force majeure
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract Drafting
 
Construction Insurance
Construction InsuranceConstruction Insurance
Construction Insurance
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction Projects
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 
Jbcc - out with the old
Jbcc - out with the oldJbcc - out with the old
Jbcc - out with the old
 
Issues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticeIssues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and Practice
 
Force Majeure Clauses in the Wake of COVID-19
Force Majeure Clauses in the Wake of COVID-19Force Majeure Clauses in the Wake of COVID-19
Force Majeure Clauses in the Wake of COVID-19
 

Recently uploaded

Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesHome Tax Saver
 
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfWhy Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfMilind Agarwal
 
如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书
如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书
如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书SD DS
 
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptxConstitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptxsrikarna235
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》o8wvnojp
 
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书SD DS
 
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一jr6r07mb
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书Fir L
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书SD DS
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书srst S
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceMichael Cicero
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书Fir sss
 
如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书Fir L
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书1k98h0e1
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书Fir L
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaNafiaNazim
 

Recently uploaded (20)

Key Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax RatesKey Factors That Influence Property Tax Rates
Key Factors That Influence Property Tax Rates
 
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdfWhy Every Business Should Invest in a Social Media Fraud Analyst.pdf
Why Every Business Should Invest in a Social Media Fraud Analyst.pdf
 
如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书
如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书
如何办理(Curtin毕业证书)科廷科技大学毕业证学位证书
 
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptxConstitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
Constitutional Values & Fundamental Principles of the ConstitutionPPT.pptx
 
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
国外大学毕业证《奥克兰大学毕业证办理成绩单GPA修改》
 
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
如何办理(UCD毕业证书)加州大学戴维斯分校毕业证学位证书
 
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
定制(WMU毕业证书)美国西密歇根大学毕业证成绩单原版一比一
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
 
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书如何办理(Rice毕业证书)莱斯大学毕业证学位证书
如何办理(Rice毕业证书)莱斯大学毕业证学位证书
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
 
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics GuidanceLaw360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
Law360 - How Duty Of Candor Figures In USPTO AI Ethics Guidance
 
如何办理纽约州立大学石溪分校毕业证学位证书
 如何办理纽约州立大学石溪分校毕业证学位证书 如何办理纽约州立大学石溪分校毕业证学位证书
如何办理纽约州立大学石溪分校毕业证学位证书
 
如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书如何办理澳洲南澳大学(UniSA)毕业证学位证书
如何办理澳洲南澳大学(UniSA)毕业证学位证书
 
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
昆士兰科技大学毕业证学位证成绩单-补办步骤澳洲毕业证书
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
young Call Girls in Pusa Road🔝 9953330565 🔝 escort Service
young Call Girls in  Pusa Road🔝 9953330565 🔝 escort Serviceyoung Call Girls in  Pusa Road🔝 9953330565 🔝 escort Service
young Call Girls in Pusa Road🔝 9953330565 🔝 escort Service
 
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
如何办理美国加州大学欧文分校毕业证(本硕)UCI学位证书
 
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Haqiqat Nagar Delhi reach out to us at 🔝8264348440🔝
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in India
 
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
 

Force Majeure Clauses Drafting Tips

  • 1. Asia Pacific Projects Update FORCE MAJEURE CLAUSES – REVISITED KEY CONTACT Damian McNair Partner, Head of Finance & Projects, Asia Pacific T +61 3 9274 5379 damian.mcnair@dlapiper.com INTRODUCTION Force majeure clauses in project agreements are common, however, the amount of time spent negotiating those clauses is often minimal. Generally, the assumption appears to be that the risk will not affect us or the force majeure clause is a legal necessity and does not impact on our risk allocation under the contract. Both of these assumptions are inherently dangerous and, particularly in the second case, incorrect. This paper follows from last fortnight's paper on force majeure clauses and considers the drafting of those clauses. RISK ALLOCATION The appropriate allocation of risk in project agreements is fundamental to negotiations between the project company and its contractors. Risks generally fall into the following categories:  Risks within the control of the project company  Risks within the control of the contractor  Risks outside the control of both parties. The negotiation of the allocation of many of the risks beyond the control of the parties, for example, latent site conditions and change of law, is usually very detailed so that it is clear which risks are borne by the contractor. The same approach should be adopted in relation to the risks arising from events of force majeure. OPERATION OF FORCE MAJEURE CLAUSES There are two aspects to the operation of force majeure clauses:  The definition of force majeure events  The operative clause that sets out the effect on the parties’ rights and obligations if a force majeure event occurs. Definition The events that trigger the operative clause must be clearly defined. Given the common law meaning of the term force majeure is not certain and is open to interpretation of the courts, it is in the interests of both parties to ensure that the term force majeure is clearly defined. The preferred approach for a project company is to define force majeure events as being any of the events in an exhaustive list set out in the contract. In this manner, both parties are aware of which events are force majeure events and which are not. Clearly, defining force majeure events makes the administration of the contract and, in particular, the mechanism within the contract for dealing with force majeure events simpler and more effective.
  • 2. 2  Force Majeure Clauses – Revisited Operative clause An operative clause will act as a shield for the party affected by the event of force majeure so that a party can rely on that clause as a defence to a claim that it has failed to fulfil its obligations under the contract. An operative clause should also specifically deal with the rights and obligations of the parties if a force majeure event occurs and affects the project. This means the parties must consider each of the events that it intends to include in the definition of force majeure events and then to deal with what the parties will do if one of those events occurs. DRAFTING FORCE MAJEURE CLAUSES Definition An example of an exhaustive definition of force majeure is: "An event of force majeure is an event or circumstance which is beyond the control and without the fault or negligence of the party affected and which by the exercise of reasonable diligence the party affected was unable to prevent provided that event or circumstance is limited to the following: (a) riot, war, invasion, act of foreign enemies, hostilities (whether war be declared or not) acts of terrorism, civil war, rebellion, revolution, insurrection of military or usurped power, requisition or compulsory acquisition by any governmental or competent authority; (b) ionising radiation or contamination, radio activity from any nuclear fuel or from any nuclear waste from the combustion of nuclear fuel, radio active toxic explosive or other hazardous properties of any explosive assembly or nuclear component; (c) pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds; (d) earthquakes, flood, fire or other physical natural disaster, but excluding weather conditions regardless of severity; and (e) strikes at national level or industrial disputes at a national level, or strike or industrial disputes by labour not employed by the affected party, its subcontractors or its suppliers and which affect an essential portion of the works but excluding any industrial dispute which is specific to the performance of the works or this contract." The list of events to be included in this type of definition is a matter for negotiation between the parties. In general, it is preferable for a project company to have a short list of events as the contractor is the party most likely to be affected by force majeure events. The actual process of negotiating this list clearly identifies the risk allocation between the parties. Operative clause An example of an operative clause is: "[ ].1 Neither party is responsible for any failure to perform its obligations under this contract, if it is prevented or delayed in performing those obligations by an event of force majeure. [ ].2 Where there is an event of force majeure, the party prevented from or delayed in performing its obligations under this contract must immediately notify the other party giving full particulars of the event of force majeure and the reasons for the event of force majeure preventing that party from, or delaying that party in performing its obligations under this contract and that party must use its reasonable efforts to mitigate the effect of the event of force majeure upon its or their performance of the contract and to fulfil its or their obligations under the contract. [ ].3 Upon completion of the event of force majeure the party affected must as soon as reasonably practicable recommence the performance of its obligations under this contract. Where the party affected is the contractor, the contractor must provide a revised programme rescheduling the works to minimise the effects of the prevention or delay caused by the event of force majeure. [ ].4 An event of force majeure does not relieve a party from liability for an obligation which arose before the occurrence of that event, nor does that event affect the obligation to pay money in a timely manner which matured prior to the occurrence of that event. [ ].5 The contractor has no entitlement and the project company has no liability for: (a) any costs, losses, expenses, damages or the payment of any part of the contract price during an event of force majeure; and (b) any delay costs in any way incurred by the contractor due to an event of force majeure." In addition to the above clause, it is important to appropriately deal with other issues that will arise if a force majeure event occurs. For example, it is common practice for a contractor to be entitled to an extension of time if a force majeure event impacts on its ability to perform the works. For this reason, force majeure is usually referred to in the extension of time mechanism as an event which will entitle the contractor to an extension of time. Another key clause that relates to force majeure type events is the contractor’s responsibility for care of the
  • 3. 3  Force Majeure Clauses – Revisited works and the obligation to reinstate any damage to the works prior to completion. A common example clause is: "[ ].1 The contractor is responsible for the care of the site and the works from when the project company makes the site available to the contractor until 5.00pm on the date of practical completion. [ ].2 The contractor must promptly make good loss from, or damage to, any part of the site and the works while it is responsible for their care. [ ].3 If the loss or damage is caused by an event of force majeure, the project company may direct the contractor to reinstate the works or change the works. The cost of the reinstatement work or any change to the works arising from a direction by the project company under this clause will be dealt with as a variation except to the extent that the loss or damage has been caused or exacerbated by the failure of the contractor to fulfil its obligations under this contract. [ ].4 Except as contemplated in clause [ ].3, the cost of all reinstatement works will be borne by the contractor." CONCLUSION It is important for a project company and its contractors to carefully consider the definition of force majeure and how an event of force majeure will affect their rights and obligations under the contract. The drafting of force majeure definitions and operative clauses (including related clauses) should clearly define the risk allocation between the parties. The above example clauses have been used to demonstrate some options available for dealing with events of force majeure. The specific issues that need to be considered when drafting force majeure clauses will depend on a variety of factors. www.dlapiper.com DLA Piper is a global law firm operating through various separate and distinct legal entities. For further information, please refer to www.dlapiper.com Copyright © 2012 DLA Piper. All rights reserved. 1110409668  DLA188  0611