For the following table of dependencies use a rough hand drawn network diagram to answer the following questions No need to upload the diagram, it is for your reference only. 1. What is the total project duration? 2. Which activity has float and how much is it? 3. Which is a burst activity? 4. Which is a merge activity? 5. What is the critical path? (Use correct notation A > B etc) For the toolbar, press A L T + F 10 ( PC ) or ALT + FN + F 10 (MaC). B I U s Click Saue and Submit to sque and submti. CLick Sate All Antewers to sate all ansuers. .