156 FERC ¶ 61,114
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Before Commissioners: Norman C. Bay, Chairman;
Cheryl A. LaFleur, Tony Clark,
and Colette D. Honorable.
Downeast Liquefaction, LLC
Downeast LNG, Inc.
Downeast Pipeline, LLC
Docket Nos. PF14-19-000
CP07-52-000
CP07-53-000
CP07-53-001
CP07-54-000
CP07-55-000
ORDER DISMISSING DOCKETS AND TERMINATING PROCEEDINGS
(Issued August 17, 2016)
1. On December 22, 2006, Downeast LNG, Inc. and Downeast Pipeline, LLC
(collectively, Downeast), filed applications under sections 3 and 7, respectively, of the
Natural Gas Act (NGA) for the siting, construction, and operation of a liquefied natural
gas (LNG) import terminal and associated pipeline take-away facilities in Washington
County, Maine. On July 22, 2014, Downeast filed a letter requesting the Commission
initiate the pre-filing process for the conversion of its proposed import project facilities
into a bidirectional import/export LNG terminal and associated pipeline facilities.1
Downeast indicated it would operate the export project on an integrated basis with the
import project and stated it intended to submit, by January 2015, an application to amend
its pending import project applications so that the Commission could review the proposed
import and export projects together as a single project. On August 11, 2014, the
Commission approved Downeast’s request to use the Commission’s pre-filing process for
the bidirectional import/export project.
1
See 18 C.F.R. §§ 153.12 and 157.21 (2015).
20160817-3009 FERC PDF (Unofficial) 08/17/2016
Docket No. PF14-19-000, et al. - 2 -
2. The Commission’s pre-filing process in Downeast has resulted in no significant
recent progress toward the development of the bidirectional import/export project
application or in stakeholder engagement. On June 2, 2016, Downeast requested the
Commission hold the pre-filing process in abeyance until September 30, 2016, while it
“pursued discussions with existing and potential investors to optimize the Downeast LNG
Project.” As discussed below, because of this lack of progress, we are terminating the
pre-filing review process for the bidirectional import/export project and dismissing the
pending import project applications. This dismissal is without prejudice to Downeast
filing new applications, if it so chooses, in the future when it is in a position to commit to
actively pursuing development and authorization of its project.
Discussion
3. Downeast entered the Commission’s pre-filing process for its bidirectional import-
export LNG terminal and associated pipeline proposal on August 11, 2014. However, no
significant, recent progress has been made in that process. Downeast filed initial drafts of
Resource Reports 2 (on April 15, 2015), 3 (on June 1, 2015), 8 (on April 14, 2015), and
10 (on August 11, 2014). Downeast’s last environmental submissions were a second
draft of Resource Report 1, generally describing the project, filed on August 3, 2015, and
a draft Resource Report 5 concerning potential socioeconomic impacts filed on June 6,
2016, in conjunction with Downeast’s latest request that the Commission hold its
proceedings in abeyance. There has been no other demonstrable progress on the
development of the environmental information needed to prepare an eventual application
to be submitted to the Commission since at least October 2015. With no new draft
resource reports provided in the last 12 months (other than the revised Resource Reports
1 and 5 referenced above), the parties and the Commission have lost any benefit of the
early identification and resolution of environmental and stakeholder issues the pre-filing
process was initiated to achieve.2
We are unaware of any ongoing stakeholder outreach
by Downeast, and at this point, two years after pre-filing on the liquefaction/export-
related components of the project commenced, additional scoping and outreach, including
2
See 18 C.F.R. § 157.21. The Commission’s pre-filing process is intended to
facilitate cooperation among applicants and state and local officials, early involvement by
public and governmental agencies, and widespread dissemination of information about
proposed projects. For example, the regulations provide that the applicant will respond to
issues raised during the scoping comment period within 14 days of the end of that period
and file draft Resource Reports 1 through 12 within 60 days of the end of the scoping
comment period. 18 C.F.R. § 157.21(f)(9) and (10).
20160817-3009 FERC PDF (Unofficial) 08/17/2016
Docket No. PF14-19-000, et al. - 3 -
surveys and consultation, would likely be required if the Commission were to grant the
latest requested delay in processing.3
4. Downeast filed with the Commission on October 30, 2015, to hold its
proceedings in abeyance until February 29, 2016, while “Downeast LNG and its investors
undertake an economic analysis of current market conditions and the associated impact
on the proposed Downeast LNG project.” Downeast filed again on February 29, 2016,
requesting the Commission continue to hold the proceedings in abeyance until June 1,
2016, as “discussions with existing and potential investors are still ongoing.” In its
June 2, 2016 request to hold the pre-filing process in abeyance, Downeast asserted that it
was still pursuing investors/customers for its project. While we appreciate the interest an
applicant has in ensuring that its proposed project will be economically feasible before
committing additional resources in furtherance of obtaining regulatory authority to
proceed with the project, the Commission must similarly exercise responsibility in the
expenditure of its resources and has broad discretion in managing its proceedings and
priorities.4
At this point, Downeast’s project has been before the Commission in one
form or another for more than ten years.5
There has been essentially no progress at all
toward completion of an application in the past nine months and Downeast has presented
nothing to persuade us that its situation is likely to change in the immediate future.
Accordingly, we decline to grant Downeast’s request to hold the proceedings in abeyance
until September 30, 2016. Because Downeast has not demonstrated meaningful progress
in the pre-filing review process toward a single, integrated proposal, its pending import
application and bidirectional import/export pre-filing proceedings have become stale and
warrant dismissal and termination without prejudice.
3
The final Environmental Impact Statement on the previously proposed import-
only project was issued over two years ago, on May 15, 2014.
4
See Mobil Oil Explor. & Prod. Serv. v. United Distrib. Cos., 498 U.S. 211, 230
(1991); see also Fla. Mun. Power Agency v. FERC, 315 F.3d 362, 366 (D.C. Cir. 2003)
(citing Telecomm. Resellers Assoc. v. FCC, 141 F.3d 1193, 1196 (D.C. Cir. 1998)
(administrative agencies enjoy broad discretion to manage their own dockets).
5
The pre-filing process for Downeast’s import proposal was initiated on
January 25, 2006; its application for that project was filed December 22, 2006. 72 Fed.
Reg. 766 (Jan. 22, 2007).
20160817-3009 FERC PDF (Unofficial) 08/17/2016
Docket No. PF14-19-000, et al. - 4 -
The Commission orders:
Downeast’s applications for an LNG import terminal and associated take-away
pipeline and pre-filing proceedings for an export terminal are dismissed and terminated
without prejudice to its making a future application.
By the Commission.
( S E A L )
Kimberly D. Bose,
Secretary.
20160817-3009 FERC PDF (Unofficial) 08/17/2016
Document Content(s)
PF14-19-000.DOCX......................................................1-4
20160817-3009 FERC PDF (Unofficial) 08/17/2016

More Related Content

What's hot

Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...
Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...
Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...
Marcellus Drilling News
 
Cliffs Chromite Overview Nov. 2011
Cliffs Chromite Overview Nov. 2011Cliffs Chromite Overview Nov. 2011
Cliffs Chromite Overview Nov. 2011
Cliffs Natural Resources
 
San Jose Water Company Letter 506
San Jose Water Company Letter 506San Jose Water Company Letter 506
San Jose Water Company Letter 506
Rishi Kumar
 
Final EIS Part 1
Final EIS Part 1Final EIS Part 1
Final EIS Part 1
Honolulu Civil Beat
 
FERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion ProjectFERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion Project
Marcellus Drilling News
 
FERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability ProjectFERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability Project
Marcellus Drilling News
 
Ruma lvm
Ruma lvmRuma lvm
Ruma lvm
bgiauque
 
Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...
Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...
Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...
Marcellus Drilling News
 
PennEast Pipeline Open Season Announcement
PennEast Pipeline Open Season AnnouncementPennEast Pipeline Open Season Announcement
PennEast Pipeline Open Season Announcement
Marcellus Drilling News
 
Rachel Hamblin - Case Studies
Rachel Hamblin - Case StudiesRachel Hamblin - Case Studies
Rachel Hamblin - Case Studies
PAS_Team
 
T16a 4-1998
T16a 4-1998T16a 4-1998
T16a 4-1998
jamesmaredmond
 
Example work sample RNChatterjee April 2015
Example work sample RNChatterjee April 2015Example work sample RNChatterjee April 2015
Example work sample RNChatterjee April 2015
Rob Chatterjee
 
Combine coal transshipment project report
Combine coal transshipment project reportCombine coal transshipment project report
Combine coal transshipment project report
shehri_cbe
 
Tehsils sports stadiums after meeting (5)(1)
Tehsils sports stadiums    after meeting (5)(1)Tehsils sports stadiums    after meeting (5)(1)
Tehsils sports stadiums after meeting (5)(1)
hayat alishah
 
Tehsils sports stadiums after meeting (5)
Tehsils sports stadiums    after meeting (5)Tehsils sports stadiums    after meeting (5)
Tehsils sports stadiums after meeting (5)
hayat alishah
 
Document of the world bank
Document of the world bank Document of the world bank
Document of the world bank
Cláudio Carneiro
 
Keystone XL Pipeline- Market Analysis
Keystone XL Pipeline- Market AnalysisKeystone XL Pipeline- Market Analysis
Keystone XL Pipeline- Market Analysis
Dr Dev Kambhampati
 
Example Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment ReportExample Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment Report
Ronald Moore
 
Bartsvphase2
Bartsvphase2Bartsvphase2
Bartsvphase2
Adina Levin
 

What's hot (19)

Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...
Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...
Williams Request for Pre-Filing Review on Transco Northeast Supply Enhancemen...
 
Cliffs Chromite Overview Nov. 2011
Cliffs Chromite Overview Nov. 2011Cliffs Chromite Overview Nov. 2011
Cliffs Chromite Overview Nov. 2011
 
San Jose Water Company Letter 506
San Jose Water Company Letter 506San Jose Water Company Letter 506
San Jose Water Company Letter 506
 
Final EIS Part 1
Final EIS Part 1Final EIS Part 1
Final EIS Part 1
 
FERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion ProjectFERC Approval for ESNG's White Oak Mainline Expansion Project
FERC Approval for ESNG's White Oak Mainline Expansion Project
 
FERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability ProjectFERC Approval for ESNG's System Reliability Project
FERC Approval for ESNG's System Reliability Project
 
Ruma lvm
Ruma lvmRuma lvm
Ruma lvm
 
Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...
Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...
Report to the General Assembly on Pipeline Placement of Natural Gas Gathering...
 
PennEast Pipeline Open Season Announcement
PennEast Pipeline Open Season AnnouncementPennEast Pipeline Open Season Announcement
PennEast Pipeline Open Season Announcement
 
Rachel Hamblin - Case Studies
Rachel Hamblin - Case StudiesRachel Hamblin - Case Studies
Rachel Hamblin - Case Studies
 
T16a 4-1998
T16a 4-1998T16a 4-1998
T16a 4-1998
 
Example work sample RNChatterjee April 2015
Example work sample RNChatterjee April 2015Example work sample RNChatterjee April 2015
Example work sample RNChatterjee April 2015
 
Combine coal transshipment project report
Combine coal transshipment project reportCombine coal transshipment project report
Combine coal transshipment project report
 
Tehsils sports stadiums after meeting (5)(1)
Tehsils sports stadiums    after meeting (5)(1)Tehsils sports stadiums    after meeting (5)(1)
Tehsils sports stadiums after meeting (5)(1)
 
Tehsils sports stadiums after meeting (5)
Tehsils sports stadiums    after meeting (5)Tehsils sports stadiums    after meeting (5)
Tehsils sports stadiums after meeting (5)
 
Document of the world bank
Document of the world bank Document of the world bank
Document of the world bank
 
Keystone XL Pipeline- Market Analysis
Keystone XL Pipeline- Market AnalysisKeystone XL Pipeline- Market Analysis
Keystone XL Pipeline- Market Analysis
 
Example Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment ReportExample Sponsor Development Risk Assessment Report
Example Sponsor Development Risk Assessment Report
 
Bartsvphase2
Bartsvphase2Bartsvphase2
Bartsvphase2
 

Viewers also liked

NGSA Letter to NY DEC re Dominion New Market Project
NGSA Letter to NY DEC re Dominion New Market ProjectNGSA Letter to NY DEC re Dominion New Market Project
NGSA Letter to NY DEC re Dominion New Market Project
Marcellus Drilling News
 
Study: Economic Impact of Kinder Morgan Utopia Pipeline Project
Study: Economic Impact of Kinder Morgan Utopia Pipeline ProjectStudy: Economic Impact of Kinder Morgan Utopia Pipeline Project
Study: Economic Impact of Kinder Morgan Utopia Pipeline Project
Marcellus Drilling News
 
Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...
Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...
Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...
Marcellus Drilling News
 
PA DEP: 2015 Climate Change Action Plan Update
PA DEP: 2015 Climate Change Action Plan UpdatePA DEP: 2015 Climate Change Action Plan Update
PA DEP: 2015 Climate Change Action Plan Update
Marcellus Drilling News
 
U.S. EIA's Drilling Productivity Report - August 2016
U.S. EIA's Drilling Productivity Report - August 2016U.S. EIA's Drilling Productivity Report - August 2016
U.S. EIA's Drilling Productivity Report - August 2016
Marcellus Drilling News
 
Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016
Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016
Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016
Marcellus Drilling News
 
PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...
PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...
PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...
Marcellus Drilling News
 
PA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power Plan
PA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power PlanPA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power Plan
PA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power Plan
Marcellus Drilling News
 
Ohio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake AppalachiaOhio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Marcellus Drilling News
 
PA DEP's 2015 Oil and Gas Annual Report
PA DEP's 2015 Oil and Gas Annual ReportPA DEP's 2015 Oil and Gas Annual Report
PA DEP's 2015 Oil and Gas Annual Report
Marcellus Drilling News
 
Deloitte 2016 Oil and Gas Industry Survey
Deloitte 2016 Oil and Gas Industry SurveyDeloitte 2016 Oil and Gas Industry Survey
Deloitte 2016 Oil and Gas Industry Survey
Marcellus Drilling News
 
What If...Hydraulic Fracturing Was Banned?
What If...Hydraulic Fracturing Was Banned?What If...Hydraulic Fracturing Was Banned?
What If...Hydraulic Fracturing Was Banned?
Marcellus Drilling News
 
SAB Review of EPA's Draft Assessment of Fracking on Drinking Water Resources
SAB Review of EPA's Draft Assessment of Fracking on Drinking Water ResourcesSAB Review of EPA's Draft Assessment of Fracking on Drinking Water Resources
SAB Review of EPA's Draft Assessment of Fracking on Drinking Water Resources
Marcellus Drilling News
 
Revised Virginia Regulations for Fracking Chemical Disclosure
Revised Virginia Regulations for Fracking Chemical DisclosureRevised Virginia Regulations for Fracking Chemical Disclosure
Revised Virginia Regulations for Fracking Chemical Disclosure
Marcellus Drilling News
 
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Marcellus Drilling News
 
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
Marcellus Drilling News
 
PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...
PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...
PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...
Marcellus Drilling News
 
BLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease Sale
BLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease SaleBLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease Sale
BLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease Sale
Marcellus Drilling News
 

Viewers also liked (18)

NGSA Letter to NY DEC re Dominion New Market Project
NGSA Letter to NY DEC re Dominion New Market ProjectNGSA Letter to NY DEC re Dominion New Market Project
NGSA Letter to NY DEC re Dominion New Market Project
 
Study: Economic Impact of Kinder Morgan Utopia Pipeline Project
Study: Economic Impact of Kinder Morgan Utopia Pipeline ProjectStudy: Economic Impact of Kinder Morgan Utopia Pipeline Project
Study: Economic Impact of Kinder Morgan Utopia Pipeline Project
 
Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...
Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...
Wacko Report - A Bridge Too Far: How Appalachian Basin Gas Pipeline Expansion...
 
PA DEP: 2015 Climate Change Action Plan Update
PA DEP: 2015 Climate Change Action Plan UpdatePA DEP: 2015 Climate Change Action Plan Update
PA DEP: 2015 Climate Change Action Plan Update
 
U.S. EIA's Drilling Productivity Report - August 2016
U.S. EIA's Drilling Productivity Report - August 2016U.S. EIA's Drilling Productivity Report - August 2016
U.S. EIA's Drilling Productivity Report - August 2016
 
Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016
Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016
Challenger, Gray & Christmas Mid-Year Job Cut Report - 2016
 
PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...
PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...
PIOGA Comments to EPA re Rule Banning O&G Wastewater at Public Sewage Treatme...
 
PA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power Plan
PA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power PlanPA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power Plan
PA Senate Bill (SB) 1195 - On Plans to Comply with Federal Clean Power Plan
 
Ohio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake AppalachiaOhio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake Appalachia
 
PA DEP's 2015 Oil and Gas Annual Report
PA DEP's 2015 Oil and Gas Annual ReportPA DEP's 2015 Oil and Gas Annual Report
PA DEP's 2015 Oil and Gas Annual Report
 
Deloitte 2016 Oil and Gas Industry Survey
Deloitte 2016 Oil and Gas Industry SurveyDeloitte 2016 Oil and Gas Industry Survey
Deloitte 2016 Oil and Gas Industry Survey
 
What If...Hydraulic Fracturing Was Banned?
What If...Hydraulic Fracturing Was Banned?What If...Hydraulic Fracturing Was Banned?
What If...Hydraulic Fracturing Was Banned?
 
SAB Review of EPA's Draft Assessment of Fracking on Drinking Water Resources
SAB Review of EPA's Draft Assessment of Fracking on Drinking Water ResourcesSAB Review of EPA's Draft Assessment of Fracking on Drinking Water Resources
SAB Review of EPA's Draft Assessment of Fracking on Drinking Water Resources
 
Revised Virginia Regulations for Fracking Chemical Disclosure
Revised Virginia Regulations for Fracking Chemical DisclosureRevised Virginia Regulations for Fracking Chemical Disclosure
Revised Virginia Regulations for Fracking Chemical Disclosure
 
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
Expert Report on Geologic Hazards in the Karst Regions of Virginia and West V...
 
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
 
PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...
PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...
PA DEP Policy for the Replacement or Restoration of Private Water Supplies Im...
 
BLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease Sale
BLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease SaleBLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease Sale
BLM Eastern States Notice of Competitive Oil and Gas Internet-Based Lease Sale
 

Similar to FERC Downeast LNG Rejection Notice

Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...
Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...
Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...
Marcellus Drilling News
 
Millennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade ProjectMillennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade Project
Marcellus Drilling News
 
FERC Certificate Approving Dominion's Clarington Project in WV & OH
FERC Certificate Approving Dominion's Clarington Project in WV & OHFERC Certificate Approving Dominion's Clarington Project in WV & OH
FERC Certificate Approving Dominion's Clarington Project in WV & OH
Marcellus Drilling News
 
Testimony Of ARTBA July 15 EPA Veto Hearing
Testimony Of ARTBA  July 15 EPA Veto HearingTestimony Of ARTBA  July 15 EPA Veto Hearing
Testimony Of ARTBA July 15 EPA Veto Hearing
artba
 
FERC Draft Environmental Impact Statement for Constitution Pipeline
FERC Draft Environmental Impact Statement for Constitution PipelineFERC Draft Environmental Impact Statement for Constitution Pipeline
FERC Draft Environmental Impact Statement for Constitution Pipeline
Marcellus Drilling News
 
Draft FERC EIS for NEXUS Pipeline
Draft FERC EIS for NEXUS PipelineDraft FERC EIS for NEXUS Pipeline
Draft FERC EIS for NEXUS Pipeline
Marcellus Drilling News
 
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...
Marcellus Drilling News
 
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion ProjectFERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
Marcellus Drilling News
 
100814ctcagenda
100814ctcagenda100814ctcagenda
100814ctcagenda
peggydrouet
 
ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...
ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...
ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...
artba
 
Rio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to InterveneRio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to Intervene
Marcellus Drilling News
 
20 town appeal appendix b
20 town appeal appendix b20 town appeal appendix b
20 town appeal appendix b
Kevin Sitlick
 
SJWC A.17 04-001 endorsed application
SJWC A.17 04-001 endorsed applicationSJWC A.17 04-001 endorsed application
SJWC A.17 04-001 endorsed application
Rishi Kumar
 
ARTBA Comments Supporting FHWA and FTA Proposed Streamlining Rule
ARTBA Comments Supporting FHWA and FTA Proposed Streamlining RuleARTBA Comments Supporting FHWA and FTA Proposed Streamlining Rule
ARTBA Comments Supporting FHWA and FTA Proposed Streamlining Rule
artba
 
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationPublic Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
AGC of California
 
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docx
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docxSAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docx
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docx
kenjordan97598
 
Sample Pres. Gov't Center
Sample Pres. Gov't CenterSample Pres. Gov't Center
Sample Pres. Gov't Center
CEQAplanner
 
FERC Draft Environmental Impact Statement for ET Rover Pipeline
FERC Draft Environmental Impact Statement for ET Rover PipelineFERC Draft Environmental Impact Statement for ET Rover Pipeline
FERC Draft Environmental Impact Statement for ET Rover Pipeline
Marcellus Drilling News
 
FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...
FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...
FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...
Marcellus Drilling News
 
FERC Environmental Assessment for the Cove Point Liquefaction Project
FERC Environmental Assessment for the Cove Point Liquefaction ProjectFERC Environmental Assessment for the Cove Point Liquefaction Project
FERC Environmental Assessment for the Cove Point Liquefaction Project
Marcellus Drilling News
 

Similar to FERC Downeast LNG Rejection Notice (20)

Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...
Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...
Mountaineer Gas Case No. 15-1256-G-390P Request to Expand Distribution Lines ...
 
Millennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade ProjectMillennium Pipeline Pre-Filing for Eastern System Upgrade Project
Millennium Pipeline Pre-Filing for Eastern System Upgrade Project
 
FERC Certificate Approving Dominion's Clarington Project in WV & OH
FERC Certificate Approving Dominion's Clarington Project in WV & OHFERC Certificate Approving Dominion's Clarington Project in WV & OH
FERC Certificate Approving Dominion's Clarington Project in WV & OH
 
Testimony Of ARTBA July 15 EPA Veto Hearing
Testimony Of ARTBA  July 15 EPA Veto HearingTestimony Of ARTBA  July 15 EPA Veto Hearing
Testimony Of ARTBA July 15 EPA Veto Hearing
 
FERC Draft Environmental Impact Statement for Constitution Pipeline
FERC Draft Environmental Impact Statement for Constitution PipelineFERC Draft Environmental Impact Statement for Constitution Pipeline
FERC Draft Environmental Impact Statement for Constitution Pipeline
 
Draft FERC EIS for NEXUS Pipeline
Draft FERC EIS for NEXUS PipelineDraft FERC EIS for NEXUS Pipeline
Draft FERC EIS for NEXUS Pipeline
 
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...
US Court of Appeals for DC - EarthReports v Federal Energy Regulatory Commiss...
 
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion ProjectFERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
FERC Approval for Tennessee Gas Pipeline - Connecticut Expansion Project
 
100814ctcagenda
100814ctcagenda100814ctcagenda
100814ctcagenda
 
ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...
ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...
ARTBA Comments on CEQ Draft Guidance Including Climate Change and Greenhouse ...
 
Rio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to InterveneRio Grande LNG Opposition to Motions to Intervene
Rio Grande LNG Opposition to Motions to Intervene
 
20 town appeal appendix b
20 town appeal appendix b20 town appeal appendix b
20 town appeal appendix b
 
SJWC A.17 04-001 endorsed application
SJWC A.17 04-001 endorsed applicationSJWC A.17 04-001 endorsed application
SJWC A.17 04-001 endorsed application
 
ARTBA Comments Supporting FHWA and FTA Proposed Streamlining Rule
ARTBA Comments Supporting FHWA and FTA Proposed Streamlining RuleARTBA Comments Supporting FHWA and FTA Proposed Streamlining Rule
ARTBA Comments Supporting FHWA and FTA Proposed Streamlining Rule
 
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationPublic Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
 
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docx
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docxSAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docx
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITYREQUEST FO.docx
 
Sample Pres. Gov't Center
Sample Pres. Gov't CenterSample Pres. Gov't Center
Sample Pres. Gov't Center
 
FERC Draft Environmental Impact Statement for ET Rover Pipeline
FERC Draft Environmental Impact Statement for ET Rover PipelineFERC Draft Environmental Impact Statement for ET Rover Pipeline
FERC Draft Environmental Impact Statement for ET Rover Pipeline
 
FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...
FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...
FERC Letter to Algonquin Gas Transmission re Wetland Encroachment Along Hudso...
 
FERC Environmental Assessment for the Cove Point Liquefaction Project
FERC Environmental Assessment for the Cove Point Liquefaction ProjectFERC Environmental Assessment for the Cove Point Liquefaction Project
FERC Environmental Assessment for the Cove Point Liquefaction Project
 

More from Marcellus Drilling News

Five facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strongFive facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strong
Marcellus Drilling News
 
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Marcellus Drilling News
 
Access Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 UpdateAccess Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 Update
Marcellus Drilling News
 
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA CountriesDOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
Marcellus Drilling News
 
LSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. ManufacturingLSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. Manufacturing
Marcellus Drilling News
 
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Marcellus Drilling News
 
Report: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental ExternalitiesReport: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental Externalities
Marcellus Drilling News
 
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
Marcellus Drilling News
 
U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015
Marcellus Drilling News
 
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids PlantsVelocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Marcellus Drilling News
 
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
Marcellus Drilling News
 
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
Marcellus Drilling News
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas Operations
Marcellus Drilling News
 
US EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy OutlookUS EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy Outlook
Marcellus Drilling News
 
Northeast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical GuideNortheast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical Guide
Marcellus Drilling News
 
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee AuditPA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
Marcellus Drilling News
 
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Marcellus Drilling News
 
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final ReportClyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Marcellus Drilling News
 
Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...
Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...
Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...
Marcellus Drilling News
 
Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...
Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...
Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...
Marcellus Drilling News
 

More from Marcellus Drilling News (20)

Five facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strongFive facts about shale: it’s coming back, and coming back strong
Five facts about shale: it’s coming back, and coming back strong
 
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
Quarterly legislative action update: Marcellus and Utica shale region (4Q16)
 
Access Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 UpdateAccess Northeast Pipeline Project - Dec 2016 Update
Access Northeast Pipeline Project - Dec 2016 Update
 
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA CountriesDOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
DOE Order Granting Elba Island LNG Right to Export to Non-FTA Countries
 
LSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. ManufacturingLSE Study: Fracking is Revitalizing U.S. Manufacturing
LSE Study: Fracking is Revitalizing U.S. Manufacturing
 
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
Letter From 24 States Asking Trump & Congress to Withdraw the Unlawful Clean ...
 
Report: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental ExternalitiesReport: New U.S. Power Costs: by County, with Environmental Externalities
Report: New U.S. Power Costs: by County, with Environmental Externalities
 
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
U.S. Crude Oil and Natural Gas Proved Reserves, Year-end 2015
 
U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015U.S. EIA's Drilling Productivity Report - December 2015
U.S. EIA's Drilling Productivity Report - December 2015
 
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids PlantsVelocys Plan to "Build the Business" - Gas-to-Liquids Plants
Velocys Plan to "Build the Business" - Gas-to-Liquids Plants
 
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
PA DEP Revised Permit for Natural Gas Compression Stations, Processing Plants...
 
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
PA DEP Permit for Unconventional NatGas Well Site Operations and Remote Piggi...
 
PA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas OperationsPA DEP: Methane Reduction Strategies for Natural Gas Operations
PA DEP: Methane Reduction Strategies for Natural Gas Operations
 
US EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy OutlookUS EIA's December 2016 Short-Term Energy Outlook
US EIA's December 2016 Short-Term Energy Outlook
 
Northeast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical GuideNortheast Gas Association's 2016 Statistical Guide
Northeast Gas Association's 2016 Statistical Guide
 
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee AuditPA PUC Responses to Auditor General's Act 13 Impact Fee Audit
PA PUC Responses to Auditor General's Act 13 Impact Fee Audit
 
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
Pennsylvania Public Utility Commission Act 13/Impact Fees Audit by PA Auditor...
 
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final ReportClyde Mine Discharge/Tenmile Creek Water Quality Final Report
Clyde Mine Discharge/Tenmile Creek Water Quality Final Report
 
Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...
Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...
Sixth Circuit Court of Appeals Decision in Harper v Muskingum Watershed Conse...
 
Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...
Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...
Schedule 13D - Stone Energy Corporation - Largest Shareholder Opposes Bankrup...
 

Recently uploaded

MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
Filippo64
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
Abdul-Hakim Shabazz
 
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
ckn2izdm
 
13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf
FIRST INDIA
 
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
LUMINATIVE MEDIA/PROJECT COUNSEL MEDIA GROUP
 
Youngest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu BiographyYoungest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu Biography
VoterMood
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
CIkumparan
 
Essential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptxEssential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptx
Pragencyuk
 

Recently uploaded (8)

MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)MAGNA CARTA (minimum 40 characters required)
MAGNA CARTA (minimum 40 characters required)
 
Gabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary JudgmentGabriel Whitley's Motion Summary Judgment
Gabriel Whitley's Motion Summary Judgment
 
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
在线办理(latrobe毕业证书)拉筹伯大学毕业证Offer一模一样
 
13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf13062024_First India Newspaper Jaipur.pdf
13062024_First India Newspaper Jaipur.pdf
 
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
Howard Fineman, Veteran Political Journalist and TV Pundit, Dies at 75
 
Youngest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu BiographyYoungest c m in India- Pema Khandu Biography
Youngest c m in India- Pema Khandu Biography
 
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf 2015pmkemenhub163.pdf
 
Essential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptxEssential Tools for Modern PR Business .pptx
Essential Tools for Modern PR Business .pptx
 

FERC Downeast LNG Rejection Notice

  • 1. 156 FERC ¶ 61,114 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Downeast Liquefaction, LLC Downeast LNG, Inc. Downeast Pipeline, LLC Docket Nos. PF14-19-000 CP07-52-000 CP07-53-000 CP07-53-001 CP07-54-000 CP07-55-000 ORDER DISMISSING DOCKETS AND TERMINATING PROCEEDINGS (Issued August 17, 2016) 1. On December 22, 2006, Downeast LNG, Inc. and Downeast Pipeline, LLC (collectively, Downeast), filed applications under sections 3 and 7, respectively, of the Natural Gas Act (NGA) for the siting, construction, and operation of a liquefied natural gas (LNG) import terminal and associated pipeline take-away facilities in Washington County, Maine. On July 22, 2014, Downeast filed a letter requesting the Commission initiate the pre-filing process for the conversion of its proposed import project facilities into a bidirectional import/export LNG terminal and associated pipeline facilities.1 Downeast indicated it would operate the export project on an integrated basis with the import project and stated it intended to submit, by January 2015, an application to amend its pending import project applications so that the Commission could review the proposed import and export projects together as a single project. On August 11, 2014, the Commission approved Downeast’s request to use the Commission’s pre-filing process for the bidirectional import/export project. 1 See 18 C.F.R. §§ 153.12 and 157.21 (2015). 20160817-3009 FERC PDF (Unofficial) 08/17/2016
  • 2. Docket No. PF14-19-000, et al. - 2 - 2. The Commission’s pre-filing process in Downeast has resulted in no significant recent progress toward the development of the bidirectional import/export project application or in stakeholder engagement. On June 2, 2016, Downeast requested the Commission hold the pre-filing process in abeyance until September 30, 2016, while it “pursued discussions with existing and potential investors to optimize the Downeast LNG Project.” As discussed below, because of this lack of progress, we are terminating the pre-filing review process for the bidirectional import/export project and dismissing the pending import project applications. This dismissal is without prejudice to Downeast filing new applications, if it so chooses, in the future when it is in a position to commit to actively pursuing development and authorization of its project. Discussion 3. Downeast entered the Commission’s pre-filing process for its bidirectional import- export LNG terminal and associated pipeline proposal on August 11, 2014. However, no significant, recent progress has been made in that process. Downeast filed initial drafts of Resource Reports 2 (on April 15, 2015), 3 (on June 1, 2015), 8 (on April 14, 2015), and 10 (on August 11, 2014). Downeast’s last environmental submissions were a second draft of Resource Report 1, generally describing the project, filed on August 3, 2015, and a draft Resource Report 5 concerning potential socioeconomic impacts filed on June 6, 2016, in conjunction with Downeast’s latest request that the Commission hold its proceedings in abeyance. There has been no other demonstrable progress on the development of the environmental information needed to prepare an eventual application to be submitted to the Commission since at least October 2015. With no new draft resource reports provided in the last 12 months (other than the revised Resource Reports 1 and 5 referenced above), the parties and the Commission have lost any benefit of the early identification and resolution of environmental and stakeholder issues the pre-filing process was initiated to achieve.2 We are unaware of any ongoing stakeholder outreach by Downeast, and at this point, two years after pre-filing on the liquefaction/export- related components of the project commenced, additional scoping and outreach, including 2 See 18 C.F.R. § 157.21. The Commission’s pre-filing process is intended to facilitate cooperation among applicants and state and local officials, early involvement by public and governmental agencies, and widespread dissemination of information about proposed projects. For example, the regulations provide that the applicant will respond to issues raised during the scoping comment period within 14 days of the end of that period and file draft Resource Reports 1 through 12 within 60 days of the end of the scoping comment period. 18 C.F.R. § 157.21(f)(9) and (10). 20160817-3009 FERC PDF (Unofficial) 08/17/2016
  • 3. Docket No. PF14-19-000, et al. - 3 - surveys and consultation, would likely be required if the Commission were to grant the latest requested delay in processing.3 4. Downeast filed with the Commission on October 30, 2015, to hold its proceedings in abeyance until February 29, 2016, while “Downeast LNG and its investors undertake an economic analysis of current market conditions and the associated impact on the proposed Downeast LNG project.” Downeast filed again on February 29, 2016, requesting the Commission continue to hold the proceedings in abeyance until June 1, 2016, as “discussions with existing and potential investors are still ongoing.” In its June 2, 2016 request to hold the pre-filing process in abeyance, Downeast asserted that it was still pursuing investors/customers for its project. While we appreciate the interest an applicant has in ensuring that its proposed project will be economically feasible before committing additional resources in furtherance of obtaining regulatory authority to proceed with the project, the Commission must similarly exercise responsibility in the expenditure of its resources and has broad discretion in managing its proceedings and priorities.4 At this point, Downeast’s project has been before the Commission in one form or another for more than ten years.5 There has been essentially no progress at all toward completion of an application in the past nine months and Downeast has presented nothing to persuade us that its situation is likely to change in the immediate future. Accordingly, we decline to grant Downeast’s request to hold the proceedings in abeyance until September 30, 2016. Because Downeast has not demonstrated meaningful progress in the pre-filing review process toward a single, integrated proposal, its pending import application and bidirectional import/export pre-filing proceedings have become stale and warrant dismissal and termination without prejudice. 3 The final Environmental Impact Statement on the previously proposed import- only project was issued over two years ago, on May 15, 2014. 4 See Mobil Oil Explor. & Prod. Serv. v. United Distrib. Cos., 498 U.S. 211, 230 (1991); see also Fla. Mun. Power Agency v. FERC, 315 F.3d 362, 366 (D.C. Cir. 2003) (citing Telecomm. Resellers Assoc. v. FCC, 141 F.3d 1193, 1196 (D.C. Cir. 1998) (administrative agencies enjoy broad discretion to manage their own dockets). 5 The pre-filing process for Downeast’s import proposal was initiated on January 25, 2006; its application for that project was filed December 22, 2006. 72 Fed. Reg. 766 (Jan. 22, 2007). 20160817-3009 FERC PDF (Unofficial) 08/17/2016
  • 4. Docket No. PF14-19-000, et al. - 4 - The Commission orders: Downeast’s applications for an LNG import terminal and associated take-away pipeline and pre-filing proceedings for an export terminal are dismissed and terminated without prejudice to its making a future application. By the Commission. ( S E A L ) Kimberly D. Bose, Secretary. 20160817-3009 FERC PDF (Unofficial) 08/17/2016