Elapsed Time

HOW LONG IS IT REALLY GOING TO TAKE
Resource Proficency Code

 RPC Indicates how proficient a resource will be at
 executing a given task.

 0 ------------------ 1
 Lowest ----------- highest


 Assume RPC = 0.8
 So, Elapsed Time for a 6 hour Task= 6/RPC
 = 6/0.8 = 7.5 hours
Rescource Availability Code

 RAC specifies the availability of the resource to work
 on the task.

 0 ------------------ 1
 Lowest ----------- highest


 Assume RAC = 0.5
 So, Elapsed Time for the 6 hour Task= 6/RPC/RAC
 = (6/0.8)/o.5 = 15 hours
Add Contingency

 Add 20% contingency to allow for any unforeseen
 events/emergencies



 Assume contingency = 20%
 So, Elapsed Time for the 6 hour Task= 6/RPC/RAC
  + contingency
 =( (6/0.8)/o.5 ) + (15%)= 18 hours

Elapsed time

  • 1.
    Elapsed Time HOW LONGIS IT REALLY GOING TO TAKE
  • 2.
    Resource Proficency Code RPC Indicates how proficient a resource will be at executing a given task.  0 ------------------ 1  Lowest ----------- highest  Assume RPC = 0.8  So, Elapsed Time for a 6 hour Task= 6/RPC  = 6/0.8 = 7.5 hours
  • 3.
    Rescource Availability Code RAC specifies the availability of the resource to work on the task.  0 ------------------ 1  Lowest ----------- highest  Assume RAC = 0.5  So, Elapsed Time for the 6 hour Task= 6/RPC/RAC  = (6/0.8)/o.5 = 15 hours
  • 4.
    Add Contingency  Add20% contingency to allow for any unforeseen events/emergencies  Assume contingency = 20%  So, Elapsed Time for the 6 hour Task= 6/RPC/RAC + contingency  =( (6/0.8)/o.5 ) + (15%)= 18 hours