2. Mahadevapura
As of 2001 Mahadevapura had a population of 135,597
Average literacy rate of 73%, higher than the national avg of 59.5%
Male literacy is 79%, and female literacy is 66%
Self sustaining Eco-System
Residential accommodation available in plenty, apartments & Gated communities
Has good health care facilities and super specialty hospitals
Excellent schools both government and private including international schools
Commercial centers - Hotels, Malls & Shopping centers
Railway station, Metro (planned), CONCOR & Regional Transport Center
(planned)
Spiritual wellness – Satya Sri Sai Baba & Sri Sri Ravishankar Ashrams
An Industrial Hub – Mix of Old & New Industries
Vishakhapatnam Steel Plant, Geers & Pinions, Jaico, United Telecom, IFB & Bhoruka
ITPL, GE, SAP, iGate, Tesco, Aviva, TCS, Wipro GE, Cambridge,
It has the essential ingredients for a prosperous community
3. Development Agenda – Roads &Traffic
KR Puram RS
Kadugodi ROB
Rajmane Jn
Hoodi Jn
Hope Farm Jn
Beniganahalli ROB EPIP Jn
Kundanahalli Jn
Varthur Kodi Jn
Marthahalli ORR
5. KR Puram Railway Station Junction
Road should be
widened, guard rails to
be provided along the
road & the Fly-Over
Hawker Stalls to be
removed.
6. Garudachar Palya Junction
The main problem is
the bus-stand which
is just before the
junction.
The pavements are
in a very bad state
The parking is done
on the road, specially
the lorries and 2-
wheelers
7. Garudachar/ESI Junction
Road in very bad
condition
No kerbs and sides dug
up by BWSSB
Key access road from
KR Puram to
Brookfield, AECS
layout, Kundanahalli
Road needs to be
widened and paved
8. Hoodi Junction
Need flyover at Hoodi
junction for traffic to
hope farm junction
Multi storey residential
and commercial
properties at the
junction will significantly
increase traffic density
10. Big Bazaar Junction
Key gateway to KIADB
Need ramp from left
lane for free right turn
to KIADB complex
11. Hope Farm Junction
Need flyover on
Whitefield main road
towards Sai Baba
junction
Key access junction
for Whitefield to
Hoskote &
Devanahalli
12. Varthur Junction
Ozone Mall under
construction
Will significantly increase
traffic at junction
Residential complex
being built on lake
bund
Lake bund road
needs to be widened
Bridge at Varthur
junction needs to be
rebuilt
13. Kundanahalli Gate
Require grade
separator/flyover
for thru traffic to
Varthur
14. Brookfield Road to KIADB
Require flyover from
left lane to turn into
KIADB
This is key entrance to
entire KIADB industrial
complex
During office hours
this junction is big
bottleneck