SlideShare a Scribd company logo
1 of 16
CfD investor simulation
exercise
21 May 2013
DRAFT – This should not be taken to represent DECC Policy
Agenda for today
2
DRAFT – This should not be taken to represent DECC Policy
Time Presentation Presenter
9:30-9:40am Welcome Jonathan Brearley (DECC)
9:40-10:10am Introduction and scope of session Chris Hemsley (DECC)
10:10-10:25am View from the renewable energy sector Gordon Edge (RUK)
10:25-10:30am Introduction to breakout sessions Ilesh Patel (Redpoint/Baringa)
10:30-10:45am Coffee break
10:45-12:40pm Breakout sessions by technology Facilitated by Baringa
12:40-13:10pm Feedback from breakout groups
13:10-13:20pm Final observations and next steps Chris Hemsley (DECC)
Introduction and scope of
session
DRAFT – This should not be taken to represent DECC Policy
Chris Hemsley
CfD Design Team Lead, DECC
Introduction
4
• Aim of the session:
1. To gain a common understanding of the developer lifecycle for different low
carbon technologies, as well as the CfD lifecycle up to commissioning,
2. To seek views on the degree to which the CfD policy position logically
maps with the developer lifecycle for different low carbon technologies.
• Policy position:
 Largely reflects the November 2012 CfD Operational Framework and
Heads of Terms
 In some areas we have included additional detail or options for the
purposes of discussion – these do not represent firm policy positions
 We will take your views into account in the final policy design
DRAFT – This should not be taken to represent DECC Policy
Scope of this session
5
FOCUS FOR TODAY
The process for applying for and
obtaining a CfD through to
project commissioning
• We welcome views on all aspects of EMR, however today we would
like to focus on the developer journey to obtaining a CfD
NOT A FOCUS FOR TODAY
FID enabling
Level of CfD strike prices
Route to market
Counterparty and credit issues
Other provisions related to the
operational phase (e.g. change of
law, reference price source)
DRAFT – This should not be taken to represent DECC Policy
Key CfD issues to be covered in today’s
breakout sessions
6
Pre-
development
Development Financing
Construction
and
commissioning
• CfD strike price
visibility
• CfD allocation
budget
• Statement of how
much allocation
budget remains
• CfD payment start
date
• Target
Commissioning
Window (TCW) and
Long-Stop Date
• Force majeure
• Substantial financial
commitment (SFC)
• Contractual
obligations, and
consequences
• CfD eligibility
process
• Allocation
mechanisms
• Constrained
allocation process
DRAFT – This should not be taken to represent DECC Policy
Pre-development
7
Pre-
development
Development Financing
Construction
and
commissioning
In the Pre-Development phase, developers will be looking to explore the future opportunity for their
technology in the UK market, and to assess the likelihood of obtaining a CfD.
From a CfD perspective, we anticipate that developers will be most interested in:
• CfD strike price visibility for the anticipated year of commissioning
• CfD allocation budget, including any constraints on budget availability for their low carbon technology
• Statement of how much allocation budget remains in the anticipated commissioning year
DRAFT – This should not be taken to represent DECC Policy
8
Pre-
development
Development Financing
Construction
and
commissioning
Development
In the Development phase, developers will be focused on key issues such as grid connection, planning
and consents, regulatory and licensing, commercial strategy and route to market.
From the perspective of obtaining a CfD, we anticipate that developers will be most interested in:
• The CfD eligibility criteria and process for applying for a CfD
• How CfDs are allocated and how the allocation mechanism may change as more LCF budget is used up
• The process for allocating CfDs when rationing is required to remain within the LCF
DRAFT – This should not be taken to represent DECC Policy
9
Pre-
development
Development Financing
Construction
and
commissioning
Financing
In the Financing phase, developers will be looking to finalise all contracts and licenses to enable
financing to be completed and then for construction to commence.
From the perspective of obtaining and retaining the CfD, we anticipate that developers will be most
interested in:
• Definition of the ‘substantial financial commitment (SFC)’ CfD milestone
• The obligations relating to capacity delivered and the flexibilities/penalties attached to obligations
DRAFT – This should not be taken to represent DECC Policy
Construction and
Commissioning
10
Pre-
development
Development Financing
Construction
and
commissioning
In the Construction and Commissioning phase, developers will be focused on completing construction so
that the project can be commissioned on time in accordance with contractual obligations.
From a CfD perspective, we anticipate that developers will be most interested in:
• Requirements that need to be fulfilled for CfD payments to start (‘Conditions Precedent’)
• Target Commissioning Window (TCW) and Long-Stop Date (LSD), by technology
• Force majeure provisions and other exceptions that allow an extension of the LSD
DRAFT – This should not be taken to represent DECC Policy
Capacity delivered – latest
policy thinking
11
• We are currently exploring the potential to allow a limited degree of flexibility on the
contract quantity
 Flexibility may be offered both at financial commitment milestone as well as at
commissioning (in addition to FM)
 Delivering below this range may lead to a proportionate reduction in the strike price (e.g.
0.5% reduction for each 1% under-delivery)
 There may be a backstop termination clause if the capacity falls below a certain threshold
(e.g. 85%)
• Today we would like to test this thinking as well as the prescribed thresholds
CfD
grant
Evidence
of SFC TCW Long-stop
date
CfD may be terminated if capacity
delivered is below a pre-defined
threshold (e.g. 85%).
Potential strike price reduction for
under-delivery (e.g. between 95 and
85% of adjusted capacity), s.t. FM
DRAFT – This should not be taken to represent DECC Policy
Initial
Application:
100%
Obligation to deliver:
100-95% (of adjusted
capacity)
Can
Adjust:
100-95%
Delivered
capacity
(before strike
price reductions)
Introduction to the Breakout
Sessions
DRAFT – This should not be taken to represent DECC Policy
Ilesh Patel
Redpoint/Baringa Partners
Breakout sessions
• Baringa will facilitate five breakout sessions to explore these issues further
• Breakout sessions are organised by technology:
 Biomass conversion
 Offshore wind (1000 MW)
 Onshore wind and solar (10-15 MW)
 Onshore wind (>50 MW)
 Marine, tidal stream (~20 MW)
• At the end of each section we have included some questions to guide
discussion, but these are by no means exhaustive
• Each group to feedback views at the end of the session
13
Final observations and next
steps
DRAFT – This should not be taken to represent DECC Policy
Emily Bourne
EMR Programme Manager, DECC
Next steps
15
Date Milestone
July 2013 CfD contact terms published
July 2013 Draft delivery plan, including draft renewable CfD strike prices, published
for consultation
July 2013 Further detail on CfD allocation and price setting processes for CCS and
nuclear projects
October 2013
onwards
Government consultations on secondary legislation for EMR
By the end 2013 Energy Bill receives Royal Assent (subject to Parliamentary time/decisions)
By end of 2013 First delivery plan, including final renewable CfD strike prices published
(subject to Royal Assent)
2014 EMR delivery mechanisms up and running
Thank you
DRAFT – This should not be taken to represent DECC Policy

More Related Content

Viewers also liked (8)

Inscript
InscriptInscript
Inscript
 
Choi_Yong_Gyu_My_PF_0
Choi_Yong_Gyu_My_PF_0Choi_Yong_Gyu_My_PF_0
Choi_Yong_Gyu_My_PF_0
 
DECC Headline Impact Indicators
DECC Headline Impact IndicatorsDECC Headline Impact Indicators
DECC Headline Impact Indicators
 
Regulatory affairs consultants vector pharma
Regulatory affairs consultants vector pharmaRegulatory affairs consultants vector pharma
Regulatory affairs consultants vector pharma
 
Inscript
InscriptInscript
Inscript
 
H1 pdf fixed2
H1 pdf fixed2H1 pdf fixed2
H1 pdf fixed2
 
Pylon presentation5 y_pylon
Pylon presentation5 y_pylonPylon presentation5 y_pylon
Pylon presentation5 y_pylon
 
St. Benedicts Customer Service
St. Benedicts Customer ServiceSt. Benedicts Customer Service
St. Benedicts Customer Service
 

Similar to Decc investor simulation workshop intro presentation_v 1

Decc discussion slides investor simulation workshop breakout_onshore small-sc...
Decc discussion slides investor simulation workshop breakout_onshore small-sc...Decc discussion slides investor simulation workshop breakout_onshore small-sc...
Decc discussion slides investor simulation workshop breakout_onshore small-sc...Department of Energy and Climate Change
 
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Department of Energy and Climate Change
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Department of Energy and Climate Change
 
Contracts for difference
Contracts for differenceContracts for difference
Contracts for differenceGeoff White
 
DLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIADLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIARichard Goins
 
MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptxxego1
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmDNVGLEnergy
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Ian Carr SCMP, MCIPS
 
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....RomanaVysatova
 
ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)Giselle Duran
 
Submarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_finalSubmarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_finalDominique Reverdy
 
Submarine cables structuring and financing options
Submarine cables   structuring and financing optionsSubmarine cables   structuring and financing options
Submarine cables structuring and financing optionsAmy Walls
 

Similar to Decc investor simulation workshop intro presentation_v 1 (20)

Decc discussion slides investor simulation workshop breakout_onshore small-sc...
Decc discussion slides investor simulation workshop breakout_onshore small-sc...Decc discussion slides investor simulation workshop breakout_onshore small-sc...
Decc discussion slides investor simulation workshop breakout_onshore small-sc...
 
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...
 
Contracts for difference
Contracts for differenceContracts for difference
Contracts for difference
 
DLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIADLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIA
 
SOC MRV Finance Hackathon Day 2 The Hack: Ingsights from the first session
SOC MRV Finance Hackathon Day 2 The Hack: Ingsights from the first sessionSOC MRV Finance Hackathon Day 2 The Hack: Ingsights from the first session
SOC MRV Finance Hackathon Day 2 The Hack: Ingsights from the first session
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 
PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptx
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
UK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme managementUK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme management
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
 
Science Based Target Setting for Financial Institutions
Science Based Target Setting for Financial InstitutionsScience Based Target Setting for Financial Institutions
Science Based Target Setting for Financial Institutions
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
 
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
Nuclear Sector Deal webinar series 2021. Cost reduction in nuclear new build....
 
ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)
 
Submarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_finalSubmarine cables - Structuring and Financing Options Jan 2015_final
Submarine cables - Structuring and Financing Options Jan 2015_final
 
Submarine cables structuring and financing options
Submarine cables   structuring and financing optionsSubmarine cables   structuring and financing options
Submarine cables structuring and financing options
 

More from Department of Energy and Climate Change (7)

EMR Delivery Plan: Methodology workshop
EMR Delivery Plan: Methodology workshop EMR Delivery Plan: Methodology workshop
EMR Delivery Plan: Methodology workshop
 
Pylon Design Competition Shortlist booklet
Pylon Design Competition Shortlist bookletPylon Design Competition Shortlist booklet
Pylon Design Competition Shortlist booklet
 
Pylon presentation6 totem
Pylon presentation6 totemPylon presentation6 totem
Pylon presentation6 totem
 
Pylon presentation4 plexus
Pylon presentation4 plexusPylon presentation4 plexus
Pylon presentation4 plexus
 
Pylon presentation3 flowertower
Pylon presentation3 flowertowerPylon presentation3 flowertower
Pylon presentation3 flowertower
 
Pylon presentation2 T-Pylon
Pylon presentation2 T-PylonPylon presentation2 T-Pylon
Pylon presentation2 T-Pylon
 
Pylon presentation1 Silhouette
Pylon presentation1 SilhouettePylon presentation1 Silhouette
Pylon presentation1 Silhouette
 

Decc investor simulation workshop intro presentation_v 1

  • 1. CfD investor simulation exercise 21 May 2013 DRAFT – This should not be taken to represent DECC Policy
  • 2. Agenda for today 2 DRAFT – This should not be taken to represent DECC Policy Time Presentation Presenter 9:30-9:40am Welcome Jonathan Brearley (DECC) 9:40-10:10am Introduction and scope of session Chris Hemsley (DECC) 10:10-10:25am View from the renewable energy sector Gordon Edge (RUK) 10:25-10:30am Introduction to breakout sessions Ilesh Patel (Redpoint/Baringa) 10:30-10:45am Coffee break 10:45-12:40pm Breakout sessions by technology Facilitated by Baringa 12:40-13:10pm Feedback from breakout groups 13:10-13:20pm Final observations and next steps Chris Hemsley (DECC)
  • 3. Introduction and scope of session DRAFT – This should not be taken to represent DECC Policy Chris Hemsley CfD Design Team Lead, DECC
  • 4. Introduction 4 • Aim of the session: 1. To gain a common understanding of the developer lifecycle for different low carbon technologies, as well as the CfD lifecycle up to commissioning, 2. To seek views on the degree to which the CfD policy position logically maps with the developer lifecycle for different low carbon technologies. • Policy position:  Largely reflects the November 2012 CfD Operational Framework and Heads of Terms  In some areas we have included additional detail or options for the purposes of discussion – these do not represent firm policy positions  We will take your views into account in the final policy design DRAFT – This should not be taken to represent DECC Policy
  • 5. Scope of this session 5 FOCUS FOR TODAY The process for applying for and obtaining a CfD through to project commissioning • We welcome views on all aspects of EMR, however today we would like to focus on the developer journey to obtaining a CfD NOT A FOCUS FOR TODAY FID enabling Level of CfD strike prices Route to market Counterparty and credit issues Other provisions related to the operational phase (e.g. change of law, reference price source) DRAFT – This should not be taken to represent DECC Policy
  • 6. Key CfD issues to be covered in today’s breakout sessions 6 Pre- development Development Financing Construction and commissioning • CfD strike price visibility • CfD allocation budget • Statement of how much allocation budget remains • CfD payment start date • Target Commissioning Window (TCW) and Long-Stop Date • Force majeure • Substantial financial commitment (SFC) • Contractual obligations, and consequences • CfD eligibility process • Allocation mechanisms • Constrained allocation process DRAFT – This should not be taken to represent DECC Policy
  • 7. Pre-development 7 Pre- development Development Financing Construction and commissioning In the Pre-Development phase, developers will be looking to explore the future opportunity for their technology in the UK market, and to assess the likelihood of obtaining a CfD. From a CfD perspective, we anticipate that developers will be most interested in: • CfD strike price visibility for the anticipated year of commissioning • CfD allocation budget, including any constraints on budget availability for their low carbon technology • Statement of how much allocation budget remains in the anticipated commissioning year DRAFT – This should not be taken to represent DECC Policy
  • 8. 8 Pre- development Development Financing Construction and commissioning Development In the Development phase, developers will be focused on key issues such as grid connection, planning and consents, regulatory and licensing, commercial strategy and route to market. From the perspective of obtaining a CfD, we anticipate that developers will be most interested in: • The CfD eligibility criteria and process for applying for a CfD • How CfDs are allocated and how the allocation mechanism may change as more LCF budget is used up • The process for allocating CfDs when rationing is required to remain within the LCF DRAFT – This should not be taken to represent DECC Policy
  • 9. 9 Pre- development Development Financing Construction and commissioning Financing In the Financing phase, developers will be looking to finalise all contracts and licenses to enable financing to be completed and then for construction to commence. From the perspective of obtaining and retaining the CfD, we anticipate that developers will be most interested in: • Definition of the ‘substantial financial commitment (SFC)’ CfD milestone • The obligations relating to capacity delivered and the flexibilities/penalties attached to obligations DRAFT – This should not be taken to represent DECC Policy
  • 10. Construction and Commissioning 10 Pre- development Development Financing Construction and commissioning In the Construction and Commissioning phase, developers will be focused on completing construction so that the project can be commissioned on time in accordance with contractual obligations. From a CfD perspective, we anticipate that developers will be most interested in: • Requirements that need to be fulfilled for CfD payments to start (‘Conditions Precedent’) • Target Commissioning Window (TCW) and Long-Stop Date (LSD), by technology • Force majeure provisions and other exceptions that allow an extension of the LSD DRAFT – This should not be taken to represent DECC Policy
  • 11. Capacity delivered – latest policy thinking 11 • We are currently exploring the potential to allow a limited degree of flexibility on the contract quantity  Flexibility may be offered both at financial commitment milestone as well as at commissioning (in addition to FM)  Delivering below this range may lead to a proportionate reduction in the strike price (e.g. 0.5% reduction for each 1% under-delivery)  There may be a backstop termination clause if the capacity falls below a certain threshold (e.g. 85%) • Today we would like to test this thinking as well as the prescribed thresholds CfD grant Evidence of SFC TCW Long-stop date CfD may be terminated if capacity delivered is below a pre-defined threshold (e.g. 85%). Potential strike price reduction for under-delivery (e.g. between 95 and 85% of adjusted capacity), s.t. FM DRAFT – This should not be taken to represent DECC Policy Initial Application: 100% Obligation to deliver: 100-95% (of adjusted capacity) Can Adjust: 100-95% Delivered capacity (before strike price reductions)
  • 12. Introduction to the Breakout Sessions DRAFT – This should not be taken to represent DECC Policy Ilesh Patel Redpoint/Baringa Partners
  • 13. Breakout sessions • Baringa will facilitate five breakout sessions to explore these issues further • Breakout sessions are organised by technology:  Biomass conversion  Offshore wind (1000 MW)  Onshore wind and solar (10-15 MW)  Onshore wind (>50 MW)  Marine, tidal stream (~20 MW) • At the end of each section we have included some questions to guide discussion, but these are by no means exhaustive • Each group to feedback views at the end of the session 13
  • 14. Final observations and next steps DRAFT – This should not be taken to represent DECC Policy Emily Bourne EMR Programme Manager, DECC
  • 15. Next steps 15 Date Milestone July 2013 CfD contact terms published July 2013 Draft delivery plan, including draft renewable CfD strike prices, published for consultation July 2013 Further detail on CfD allocation and price setting processes for CCS and nuclear projects October 2013 onwards Government consultations on secondary legislation for EMR By the end 2013 Energy Bill receives Royal Assent (subject to Parliamentary time/decisions) By end of 2013 First delivery plan, including final renewable CfD strike prices published (subject to Royal Assent) 2014 EMR delivery mechanisms up and running
  • 16. Thank you DRAFT – This should not be taken to represent DECC Policy