SlideShare a Scribd company logo
1 of 11
Download to read offline
sid 1 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
Stockholm, 07.06.2009 (2016)
TomaszNajder (Ph.D Civ. Eng.) - Part4
Personalia Date of birth: 1951-08-30
Address: Movägen 3, SE-133 36 Saltsjöbaden (Sweden)
Tel: 0046 (8) 717 57 14, fax: 0046 (8) 717 60 42, mobile: 0046 (0)704 217 012
E-mail: tomasz.najder@hotmail.com
Legal status: married, 2 children (adults).
Experience
Since 07/2005 Najder Engineering®
Stockholm
Senior Consultant within family company.
Activities as Senior Consultant for Norconsult SA (Norway)
07/2008 – 04/2009 for GREATER ISTANBUL WATER SUPPLY PROJECT Stage II MELEN SYSTEM.
Client: MINISTRY OF ENERGY AND NATIONAL RESOURCES, GENERAL DIRECTORATE OF STATE
HYDRAULIC WORKS AND WATER SUPPLY AND SEVERAGE
Tunnel Contractor: Moskovskij Metrostroy Açik A.Ş Tȕrkye Ístanbul
Work programme:
- The TBM tunnel with excavation and segment lining, commenced in February 2008, finished in May 2009.
Project description:
- The TBM tunnel with HERRENKNECHT Earth Pressure Balance Type TBM (shield 6.120 mm diameter):
Total length 3.300m, including ca. 1.500m marine crossing section.
The first tunnel in the world between two continents.
The Bosphorus Tunnel is to provide the connection between Asia and Europe across the Bosphorus channel enabling
the water from the Melen River to be transferred to Istanbul. The tunnel is approximately 5.6 km in length and is
located ca. 15 km to the north of Istanbul.
The Asian section is constructed by drill&blast, roadheader and other mechanical methods.
The European incline and underwater sections are to be excavated by a fully shielded closed (or open) mode TBM.
TBM tunnel is rising (looking from Asian site) at a nominal 0.184% minimum gradient under the Bosphorus Channel.
The tunnel rises at a gradient of approximately 7.439% towards the European side.
The early average temperature is +13.6 °C. The average lowest soil temperature at the ground surface is +9.1 °C.
sid 2 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
Tunnel Geology:
sid 3 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
sid 4 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
sid 5 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
Grouting activities:
 Annulus grouting behind the lining with multi-component mortar (cement, water, fly ash, sand and
additives). Low pressure back filling.
Annulus grouting means the initial grouting to fill the void between a precast concrete segmental lining and
the surrounding rock.
 Proof grouting performed after annulus grouting in the case of voids discovered behind tunnel lining
(cement based grout – moderate pressure back filling).
Proof grouting means pressure grouting to fill the void between a precast concrete segmental lining and the
surrounding rock and which is carried out after annulus grouting.
 Cut-off membranes performed after annulus- and proof grouting to prevent rest-water ingress along the
lining to the cutter head compartment in the inclined section of the tunnel.
Grouting executed with OMG (organo-mineral grout/foam).
 Pre-grouting (with OPC and/or MC, and 2-component PU) to prevent:
1. Large inflow of water to occur at tunnel face which may drown tunnel.
2. Cave-in of tunnel face which may cause long stop to boring.
3. Flowing ground to take place at face which can probably drown the tunnel.
4. Moderate inflow to occur which can hamper TBM loading system.
The actual drilling pattern is 11 horizontal drilling holes (practically within excavation profile) or 6 holes in
conventional 7.5º umbrella.
The ground along the Bosporus tunnel consist of sandstone, mudstone, limestone (partially karstic) with zones of
diabase, fractures, faults of various degrees with possible hydrostatic pressure of ground waters up to 1.4 MPa.
According to the contract pre-grouting is represented as:
(a) "Fissure grouting", which means grouting works undertaken to control ground water
inflows into the Works or for ground strengthening purposes using patterns of grouted
holes, including ahead of the face being excavated, either tunnels or shafts.
(b) “Ground Stabilisation Grouting”, which means grouting works undertaken for the safe
progress of the tunnel or shaft Works.
Bentonite, cementitious or chemical grouts are to be used as the nature of the ground to
be treated and the purpose of the grouting dictates.
 Other types of grouting:
(c) "Cavity grouting", which means grouting to fill any voids at rock/concrete interfaces
around structures (other than precast concrete segmental linings).
(d) "Consolidation grouting", which means the injection of grout into fissured rock around
tunnel linings.
(e) "Cut-off grouting" where used on the drawings means consolidation grouting carried
out in specific locations around tunnel linings to depths greater than the standard
consolidation grouting fans.
(f) "Contact grouting", which means grouting to fill any voids at steel/concrete interfaces.
sid 6 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
sid 7 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
sid 8 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
sid 9 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
sid 10 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
References:
1. Leonid Astrin, Financial Director, MOSMETROSTROY.
Tel: 0 212 286 18 70-73 (Russian Federation).
2. Alexander Kofman – Project Manager, MOSMETROSTROY.
Tel: 0 212 286 18 70-73 (Russian Federation).
3. Arild Palmstrøm, Norconsult AS (Norway)
Tel: 0047 918 29 909 (Norway)
4. H. Ertan Solim, ALKE - STFA Ortak Girişimi
Tel: 0090 532 436 5184 (Turkey).
Ph.D Civ. Eng. Tomasz Najder
sid 11 av 11
Najder engineering®
Movägen 3; SE-133 36 Saltsjöbaden/Sweden
Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012
Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
Anna Elżbieta Najder

More Related Content

Viewers also liked

II Congreso Ecommaster - Big Data y Minería de Datos, Datos y más Datos
II Congreso Ecommaster - Big Data y Minería de Datos, Datos y más DatosII Congreso Ecommaster - Big Data y Minería de Datos, Datos y más Datos
II Congreso Ecommaster - Big Data y Minería de Datos, Datos y más DatosEcommaster
 
Unternehmenspräsentation von Maximilian: freiraum einrichten
Unternehmenspräsentation von Maximilian: freiraum einrichtenUnternehmenspräsentation von Maximilian: freiraum einrichten
Unternehmenspräsentation von Maximilian: freiraum einrichtenandreasblau
 
Fenómenos hipotecarios paranormales
Fenómenos hipotecarios paranormalesFenómenos hipotecarios paranormales
Fenómenos hipotecarios paranormalesSofia Square
 
Jaizkibel ponencia Aranzadi .Lezo.Azaroak.Simposio
Jaizkibel ponencia Aranzadi .Lezo.Azaroak.SimposioJaizkibel ponencia Aranzadi .Lezo.Azaroak.Simposio
Jaizkibel ponencia Aranzadi .Lezo.Azaroak.SimposioJre Joserra
 
Unejambanori xhennetit
Unejambanori xhennetitUnejambanori xhennetit
Unejambanori xhennetitFSstudio
 
Filosofía y poesía, de maría zambrano
Filosofía y poesía, de maría zambranoFilosofía y poesía, de maría zambrano
Filosofía y poesía, de maría zambranoMissael Duarte Somoza
 
Proyecto Final Diseño de Proyectos
Proyecto Final Diseño de ProyectosProyecto Final Diseño de Proyectos
Proyecto Final Diseño de Proyectosclaoeusse
 
Step adivasi chetna 20 1-15
Step adivasi chetna 20 1-15Step adivasi chetna 20 1-15
Step adivasi chetna 20 1-15Jauhar Jauhar
 
Beyond Pre-Booking - Parking Network Nov 2012 Workshop
Beyond Pre-Booking - Parking Network Nov 2012 WorkshopBeyond Pre-Booking - Parking Network Nov 2012 Workshop
Beyond Pre-Booking - Parking Network Nov 2012 WorkshopInventive IT
 
Programa academico congreso ca arquitectura diseño verde
Programa academico congreso ca arquitectura diseño verdePrograma academico congreso ca arquitectura diseño verde
Programa academico congreso ca arquitectura diseño verdeUriel Ramón Cardoza Sánchez
 

Viewers also liked (20)

Nohaycuchara
Nohaycuchara Nohaycuchara
Nohaycuchara
 
II Congreso Ecommaster - Big Data y Minería de Datos, Datos y más Datos
II Congreso Ecommaster - Big Data y Minería de Datos, Datos y más DatosII Congreso Ecommaster - Big Data y Minería de Datos, Datos y más Datos
II Congreso Ecommaster - Big Data y Minería de Datos, Datos y más Datos
 
FAnn Info 2/2007
FAnn Info 2/2007FAnn Info 2/2007
FAnn Info 2/2007
 
Unternehmenspräsentation von Maximilian: freiraum einrichten
Unternehmenspräsentation von Maximilian: freiraum einrichtenUnternehmenspräsentation von Maximilian: freiraum einrichten
Unternehmenspräsentation von Maximilian: freiraum einrichten
 
Fenómenos hipotecarios paranormales
Fenómenos hipotecarios paranormalesFenómenos hipotecarios paranormales
Fenómenos hipotecarios paranormales
 
Secret Transp Publicos Expansao Sp
Secret Transp Publicos Expansao SpSecret Transp Publicos Expansao Sp
Secret Transp Publicos Expansao Sp
 
Abschlusspräsentation Workshop "Social Media"
Abschlusspräsentation Workshop "Social Media"Abschlusspräsentation Workshop "Social Media"
Abschlusspräsentation Workshop "Social Media"
 
Jaizkibel ponencia Aranzadi .Lezo.Azaroak.Simposio
Jaizkibel ponencia Aranzadi .Lezo.Azaroak.SimposioJaizkibel ponencia Aranzadi .Lezo.Azaroak.Simposio
Jaizkibel ponencia Aranzadi .Lezo.Azaroak.Simposio
 
Calendario fotografico 2009 de Alozaina
Calendario fotografico 2009 de AlozainaCalendario fotografico 2009 de Alozaina
Calendario fotografico 2009 de Alozaina
 
Unejambanori xhennetit
Unejambanori xhennetitUnejambanori xhennetit
Unejambanori xhennetit
 
Filosofía y poesía, de maría zambrano
Filosofía y poesía, de maría zambranoFilosofía y poesía, de maría zambrano
Filosofía y poesía, de maría zambrano
 
Page 18
Page 18Page 18
Page 18
 
Manual tratamiento
Manual tratamientoManual tratamiento
Manual tratamiento
 
Mangiare sano
Mangiare sanoMangiare sano
Mangiare sano
 
El teide
El teideEl teide
El teide
 
Proyecto Final Diseño de Proyectos
Proyecto Final Diseño de ProyectosProyecto Final Diseño de Proyectos
Proyecto Final Diseño de Proyectos
 
Step adivasi chetna 20 1-15
Step adivasi chetna 20 1-15Step adivasi chetna 20 1-15
Step adivasi chetna 20 1-15
 
Guia construccion interpretacion indicadores
Guia construccion interpretacion indicadoresGuia construccion interpretacion indicadores
Guia construccion interpretacion indicadores
 
Beyond Pre-Booking - Parking Network Nov 2012 Workshop
Beyond Pre-Booking - Parking Network Nov 2012 WorkshopBeyond Pre-Booking - Parking Network Nov 2012 Workshop
Beyond Pre-Booking - Parking Network Nov 2012 Workshop
 
Programa academico congreso ca arquitectura diseño verde
Programa academico congreso ca arquitectura diseño verdePrograma academico congreso ca arquitectura diseño verde
Programa academico congreso ca arquitectura diseño verde
 

More from Tomasz Najder

ö New Orleans 2012 draft paper 2011.01.27
ö New Orleans 2012 draft paper 2011.01.27ö New Orleans 2012 draft paper 2011.01.27
ö New Orleans 2012 draft paper 2011.01.27Tomasz Najder
 
Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17Tomasz Najder
 
CV Gallery rev. 2013.04.30 compr.
CV Gallery rev. 2013.04.30 compr.CV Gallery rev. 2013.04.30 compr.
CV Gallery rev. 2013.04.30 compr.Tomasz Najder
 
öö Contribution to loading test procedure of ground anchors
öö Contribution to loading test procedure of ground anchorsöö Contribution to loading test procedure of ground anchors
öö Contribution to loading test procedure of ground anchorsTomasz Najder
 
Najder Engineering AB T-bana repairs 2016.03.22 compr.
Najder Engineering AB T-bana repairs 2016.03.22 compr.Najder Engineering AB T-bana repairs 2016.03.22 compr.
Najder Engineering AB T-bana repairs 2016.03.22 compr.Tomasz Najder
 
0 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH30 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH3Tomasz Najder
 
Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)
Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)
Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)Tomasz Najder
 
0 Iceland - pictures from the tunnels 2010.01.09
0 Iceland - pictures from the tunnels 2010.01.090 Iceland - pictures from the tunnels 2010.01.09
0 Iceland - pictures from the tunnels 2010.01.09Tomasz Najder
 
Iceland Hedinsfjordur Tunnel 2010 page 22
Iceland Hedinsfjordur Tunnel 2010 page 22Iceland Hedinsfjordur Tunnel 2010 page 22
Iceland Hedinsfjordur Tunnel 2010 page 22Tomasz Najder
 
0 Iceland An Icelandic struggle (Metrostav) - page 18 to the right
0 Iceland An Icelandic struggle (Metrostav) - page 18 to the right0 Iceland An Icelandic struggle (Metrostav) - page 18 to the right
0 Iceland An Icelandic struggle (Metrostav) - page 18 to the rightTomasz Najder
 
CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016Tomasz Najder
 
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide show0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide showTomasz Najder
 
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide showTomasz Najder
 

More from Tomasz Najder (14)

ö New Orleans 2012 draft paper 2011.01.27
ö New Orleans 2012 draft paper 2011.01.27ö New Orleans 2012 draft paper 2011.01.27
ö New Orleans 2012 draft paper 2011.01.27
 
Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17Paper Aachen- Najder engineering 2008.04.17
Paper Aachen- Najder engineering 2008.04.17
 
CV Gallery rev. 2013.04.30 compr.
CV Gallery rev. 2013.04.30 compr.CV Gallery rev. 2013.04.30 compr.
CV Gallery rev. 2013.04.30 compr.
 
öö Contribution to loading test procedure of ground anchors
öö Contribution to loading test procedure of ground anchorsöö Contribution to loading test procedure of ground anchors
öö Contribution to loading test procedure of ground anchors
 
Najder Engineering AB T-bana repairs 2016.03.22 compr.
Najder Engineering AB T-bana repairs 2016.03.22 compr.Najder Engineering AB T-bana repairs 2016.03.22 compr.
Najder Engineering AB T-bana repairs 2016.03.22 compr.
 
TNa diplomas
TNa diplomasTNa diplomas
TNa diplomas
 
0 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH30 SWECO PP-TNa Report Grouting TH3
0 SWECO PP-TNa Report Grouting TH3
 
Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)
Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)
Water leak in karstic limestone at Theun-Hinboun Laos - 2010 compr. (2)
 
0 Iceland - pictures from the tunnels 2010.01.09
0 Iceland - pictures from the tunnels 2010.01.090 Iceland - pictures from the tunnels 2010.01.09
0 Iceland - pictures from the tunnels 2010.01.09
 
Iceland Hedinsfjordur Tunnel 2010 page 22
Iceland Hedinsfjordur Tunnel 2010 page 22Iceland Hedinsfjordur Tunnel 2010 page 22
Iceland Hedinsfjordur Tunnel 2010 page 22
 
0 Iceland An Icelandic struggle (Metrostav) - page 18 to the right
0 Iceland An Icelandic struggle (Metrostav) - page 18 to the right0 Iceland An Icelandic struggle (Metrostav) - page 18 to the right
0 Iceland An Icelandic struggle (Metrostav) - page 18 to the right
 
CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016CV Tomasz Najder Part 1 2009.09.15 2016
CV Tomasz Najder Part 1 2009.09.15 2016
 
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide show0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 2 slide show
 
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
0. Part 00 EE, Extreme engineering. 2010.02.15 - part 1 slide show
 

CV Tomasz Najder Part 4 2009.06.07 2016

  • 1. sid 1 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/ Stockholm, 07.06.2009 (2016) TomaszNajder (Ph.D Civ. Eng.) - Part4 Personalia Date of birth: 1951-08-30 Address: Movägen 3, SE-133 36 Saltsjöbaden (Sweden) Tel: 0046 (8) 717 57 14, fax: 0046 (8) 717 60 42, mobile: 0046 (0)704 217 012 E-mail: tomasz.najder@hotmail.com Legal status: married, 2 children (adults). Experience Since 07/2005 Najder Engineering® Stockholm Senior Consultant within family company. Activities as Senior Consultant for Norconsult SA (Norway) 07/2008 – 04/2009 for GREATER ISTANBUL WATER SUPPLY PROJECT Stage II MELEN SYSTEM. Client: MINISTRY OF ENERGY AND NATIONAL RESOURCES, GENERAL DIRECTORATE OF STATE HYDRAULIC WORKS AND WATER SUPPLY AND SEVERAGE Tunnel Contractor: Moskovskij Metrostroy Açik A.Ş Tȕrkye Ístanbul Work programme: - The TBM tunnel with excavation and segment lining, commenced in February 2008, finished in May 2009. Project description: - The TBM tunnel with HERRENKNECHT Earth Pressure Balance Type TBM (shield 6.120 mm diameter): Total length 3.300m, including ca. 1.500m marine crossing section. The first tunnel in the world between two continents. The Bosphorus Tunnel is to provide the connection between Asia and Europe across the Bosphorus channel enabling the water from the Melen River to be transferred to Istanbul. The tunnel is approximately 5.6 km in length and is located ca. 15 km to the north of Istanbul. The Asian section is constructed by drill&blast, roadheader and other mechanical methods. The European incline and underwater sections are to be excavated by a fully shielded closed (or open) mode TBM. TBM tunnel is rising (looking from Asian site) at a nominal 0.184% minimum gradient under the Bosphorus Channel. The tunnel rises at a gradient of approximately 7.439% towards the European side. The early average temperature is +13.6 °C. The average lowest soil temperature at the ground surface is +9.1 °C.
  • 2. sid 2 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/ Tunnel Geology:
  • 3. sid 3 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
  • 4. sid 4 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
  • 5. sid 5 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/ Grouting activities:  Annulus grouting behind the lining with multi-component mortar (cement, water, fly ash, sand and additives). Low pressure back filling. Annulus grouting means the initial grouting to fill the void between a precast concrete segmental lining and the surrounding rock.  Proof grouting performed after annulus grouting in the case of voids discovered behind tunnel lining (cement based grout – moderate pressure back filling). Proof grouting means pressure grouting to fill the void between a precast concrete segmental lining and the surrounding rock and which is carried out after annulus grouting.  Cut-off membranes performed after annulus- and proof grouting to prevent rest-water ingress along the lining to the cutter head compartment in the inclined section of the tunnel. Grouting executed with OMG (organo-mineral grout/foam).  Pre-grouting (with OPC and/or MC, and 2-component PU) to prevent: 1. Large inflow of water to occur at tunnel face which may drown tunnel. 2. Cave-in of tunnel face which may cause long stop to boring. 3. Flowing ground to take place at face which can probably drown the tunnel. 4. Moderate inflow to occur which can hamper TBM loading system. The actual drilling pattern is 11 horizontal drilling holes (practically within excavation profile) or 6 holes in conventional 7.5º umbrella. The ground along the Bosporus tunnel consist of sandstone, mudstone, limestone (partially karstic) with zones of diabase, fractures, faults of various degrees with possible hydrostatic pressure of ground waters up to 1.4 MPa. According to the contract pre-grouting is represented as: (a) "Fissure grouting", which means grouting works undertaken to control ground water inflows into the Works or for ground strengthening purposes using patterns of grouted holes, including ahead of the face being excavated, either tunnels or shafts. (b) “Ground Stabilisation Grouting”, which means grouting works undertaken for the safe progress of the tunnel or shaft Works. Bentonite, cementitious or chemical grouts are to be used as the nature of the ground to be treated and the purpose of the grouting dictates.  Other types of grouting: (c) "Cavity grouting", which means grouting to fill any voids at rock/concrete interfaces around structures (other than precast concrete segmental linings). (d) "Consolidation grouting", which means the injection of grout into fissured rock around tunnel linings. (e) "Cut-off grouting" where used on the drawings means consolidation grouting carried out in specific locations around tunnel linings to depths greater than the standard consolidation grouting fans. (f) "Contact grouting", which means grouting to fill any voids at steel/concrete interfaces.
  • 6. sid 6 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
  • 7. sid 7 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
  • 8. sid 8 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
  • 9. sid 9 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/
  • 10. sid 10 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/ References: 1. Leonid Astrin, Financial Director, MOSMETROSTROY. Tel: 0 212 286 18 70-73 (Russian Federation). 2. Alexander Kofman – Project Manager, MOSMETROSTROY. Tel: 0 212 286 18 70-73 (Russian Federation). 3. Arild Palmstrøm, Norconsult AS (Norway) Tel: 0047 918 29 909 (Norway) 4. H. Ertan Solim, ALKE - STFA Ortak Girişimi Tel: 0090 532 436 5184 (Turkey). Ph.D Civ. Eng. Tomasz Najder
  • 11. sid 11 av 11 Najder engineering® Movägen 3; SE-133 36 Saltsjöbaden/Sweden Tel: +46 8 717 5714 Fax: +46 8 717 6042 Mobil: +46 (0)704 217 012 Org. no: 490911-2148 VAT-no: SE490911214801 E-mail: tomasz.najder@hotmail.com http://najder.se/ Anna Elżbieta Najder