1) Muhammad Taufiq Edy Prayoga is a 28-year-old engineer from Gresik, Indonesia seeking a position in project control or instrumentation.
2) He has over 5 years of experience as an instrumentation and electrical engineer on various oil, gas, and petrochemical projects in Indonesia and Malaysia.
3) His most recent role was as Project Control Engineer on the Sabah Ammonia Urea Project in Malaysia where he was responsible for instrument installation, interface management, and schedule and report production.
Southern-Assessors provide all the documentation needed including a Predicted Energy Assessment (PEA), On Construction Submission and Energy Performance Certificate (EPC) for every dwelling.
Southern-Assessors provide all the documentation needed including a Predicted Energy Assessment (PEA), On Construction Submission and Energy Performance Certificate (EPC) for every dwelling.
1. Page 1
CURRICULUM VITAE
Muhammad Taufiq Edy Prayoga
Place/Date of Birth : Gresik, 6 October 1988
Age : 28 Years Old
Phone : +6281232233237
Education : Degree on Physics Engineering, Institute of
Technology Sepuluh November Surabaya (ITS)
Current Address : JL. Asahan 28, Randuagung Gresik - East Java
Language Spoken : English / Bahasa
Language Written : English / Bahasa
Experience : 5 Years
Mail to: taufiqedy07@gmail.com
PROFESSIONAL/WORK EXPERIENCE
Having more than 5 years’ of work experience, on EPC and Petrochemical Company as Instrument and
electrical engineer. And the last position as Project Control Engineer on Sabah Ammonia Urea
(SAMUR) Project, Malaysia
Responsibility:
Interface of Work, Consist of:
• Develop Document for Instrument such as Hook up Drawing using AutoCAD, Datasheet For field
Instrument, Instrument Index and Cable schedule.
• Installation of Field Instrument Such as Coriolis Flow Meter, Level Transmitter, On/Off Valve,
Control Valve, RTD, Magnetic Flow Meter, Temperature Transmitter.
• Interface to Vendor Package or Mechanical Engineer and Package Instrument Engineer.
• Loop Test Work Using HART Comm 475
• To Operate PLC Using Siemens S7-200 and Allen Bradley 5/40
• To Operate 3D Viewer Using Naviswork
• Trouble Shooting Field Instrument
• Develop Document for Electrical such as Single Line Diagram Drawing using AutoCAD,
Datasheet for Electrical Equipment, Load list And Cable schedule.
• Monitoring of Packages Installation Such as HRSG, Boiler, Demin Water, Raw Water Treatment,
Air Compressor Package, Sulphure Pelletizer and Custody Meter Package.
• Making a Mitigation and Action Plan If Have Bottle Neck Between Construction with
Engineering, Engineering With Vendor or Other Discipline.
• To Make Sure The Installation of Instrument, Mechanical, Building, Civil and Structure in Field
Accordance with Latest Drawing by Engineering,
• Controlling progress of Work in Ammonia Area, Urea Area and Utility Area.
• Scheduling of Work is Make a Spend of Time with Calculate between Quantity Manpower with
Quantity of Remaining Work.
• To Make a schedule using primavera P6 Proffesional R8.1 and Microsoft project.
• Produce Weekly and Monthly Report of Instrument, Mechanical, Building, Structure, Civil and
Pre-commissioning work.
• Produce The Package Presentation for Weekly Report Meeting with Owner Or Internal.
• Monitoring of Mechanical Completion, Punch List and ITP All discipline.
• Develop Close-Out Report Such as Project Lessons Learned, Project Schedule, Man Power
Histogram and EPC (Engineering, Procurement and Construction) status.
2. Page 2
Work Experience :
1. Field Work
Position : Project Control Engineer
Industry : Rekayasa Industri Malaysia SDN BHD
Joined : June 2015 – Dec 2016
Project : Sabah Ammonia Urea (SAMUR) in Petronas Chemical Fertilizer SDN BHD.
Sabah-Malaysia
2. Field Work
Position : Instrument and Electrical Engineer
Industry : PT. Sukses Mulia Indonesia (EPC)
Joined : March 2015 – May 2015
Project : Corn Dryer & Processing Facilities in PT. Hextar Seed Indonesia, Ngadiluwih,
Kediri, East Java, Indonesia
3. Field Work
Position : Instrument Construction Engineer
Industry : PT. Tripatra Engineering and Construction (EPC)
Joined : October 2013 – February 2015
Project : Banyu Urip Central Processing Facility Project, EPC1East Java Indonesia For
180.000 BPD (Barrel Per Day) of Crude Oil Production
4. Field Work
Position : Instrument Construction Engineer
Industry : PT. Sukses Mulia Indonesia (EPC)
Joined : March 2013 – October 2013
Project : Bioethanol 100KL/Day in PT. Perkebunan Nusantara, Gempolkrep Mojokerto
5. Field Work
Position : Student trainee
Industry : PT. Petrokimia Gresik
Joined : December 2011 – January 2012
6. Field Work
Position : Student trainee
Industry : PT. Petrokimia Gresik
Joined : July 2008 – August 2009
COURSE ATTENDING
1. Trainee “ Working At High” Organized By PT. Tripatra
2. Trainee “ Confine Space” Organized By PT. Tripatra
3. Trainee “ Safety Leader” Organized By PT. Tripatra
4. Trainee “ H2S Level 1” Organized By PT. Tripatra
5. Trainee “ H2S Level 2” Organized By PT. Tripatra
Surabaya, 05 Feb 2017
Muhammad Taufiq Edy Prayoga