2. Public Works Contract for Building Works Designed by the Employer (CF1 version 1.8 dated 04/09/2012)
Copyright Notice / Disclaimer
________________________________________________
Copyright Notice
All rights reserved. This guide is the copyright of Tomás Murphy. No part of this guide
may be reproduced or transmitted in any form or by any means, including recording or
photocopying, without the written permission of the copyright holder, application for
which should be addressed directly to Tomás Murphy.
Ownership / Copyright of the contract wording are held by the Department of Public
Expenditure and Reform and as such are acknowledged by the author.
Disclaimer
While considerable effort has been made to check the accuracy of the information given
in this guide, readers should always make their own checks. No liability is accepted for
any errors, omissions, inaccuracies, misstatements, misunderstandings or loss occasioned
to any person or body acting or refraining from acting as a result of any material in this
guide. Reliance should not be placed on any material contained in this guide without
seeking and obtaining professional advice.
This document is not to be taken as a legal interpretation of the provisions of the form of
contract. All parties must rely exclusively on their own skills and judgement or upon
those of their advisors when making use of this document. The author does not assume
any liability to anyone for any loss or damage caused by any error or omission, whether
such error or omission is the result of negligence or any other cause. Any and all such
liability is disclaimed.
Tomás Murphy MSCSI MRICS
Chartered & Registered Quantity Surveyor
________________________________________________
Crannagh, Gort, Co. Galway
Tel: M 087 6787738 W 091 742433 H 091 635073
Email: tomas.murphy@gmit.ie
Using this Guide
________________________________________________
This guide is produced for training purposes only and should not be used as a substitute
for professional or legal advice.
The guide is split into the main areas of the contract eg health & safety, time, payments,
claims, insurances, administration, disputes etc. The user can go directly to the relevant
section of interest. Each flowchart is generally read from top to bottom working from left
to right.
Orange ‘text boxes’ are not extracts from the contract but rather a personal comment by
the author. Bold and/or underlined words and phrases are simply the authors own
emphasis and not that of the contract. On occasion, the order of wording in the contract is
rearranged by the author to make for ease of understanding. The reader should, however,
always check the form of contract wording.
In some instances flowcharts use less phrases, reduced wording or extracts from that
contained in the actual contract. All textboxes, however, refer to the contract clause(s) in
question to enable easy reference to the full contract text where required.
This training document attempts to schedule, assemble and summarise the wording of
many separate yet related clauses in the contract for greater consideration of the bigger
picture. “Interpretation” of the contract and its wording is another matter entirely and can
only truly be understood in tandem with knowledge of common law, contract law and
related matters. This is one reason why professional legal advice is so essential.
It is the intention to update and expanded this guide on a regular basis. User’s comments
and ideas are welcome for consideration in this process.
Tomás Murphy MSCSI MRICS
Chartered & Registered Quantity Surveyor
________________________________________________
Crannagh, Gort, Co. Galway
Tel: M 087 6787738 W 091 742433 H 091 635073
Email: tomas.murphy@gmit.ie
3. Public Works Contract for Building Works Designed by the Employer (CF1 version 1.8 dated 04/09/2012)
Contents Flowchart No.
____________________________________________________________________________________
OVERALL AGREEMENT
Overall Agreement (1 of 3)……………………………………………………1
(2 of 3)……………………………………………………2
(3 of 3)……………………………………………………3
Background Information………………………………………………………….. 4
Ethics in Public Office ……………………………………………………………..5
Legal Opinion……………………………………………………………………….6
Infringement of Property Rights…………………………………………………..7
Contract Documents & Precedence………………………………………………. 8
GENERAL ISSUES
Communications…………………………………………………………………… 9
Works Requirements (General)…………………………………………………10
(Standard Forms)………………………………………. 11
(Procedures / Obligations)……………………………... 12
Contractor’s Documents…………………………………………………………... 13
Works Proposals……………………………………………………………………14
Contractor’s Things……………………………………………………………….. 15
HEALTH & SAFETY
Project Supervisor…………………………………………………………………. 16
Health & Safety Obligations……………………………………………………….17
Security & Safety of the Site and Nuisance……………………………………….18
LOSS, DAMAGE AND INJURY
Allocation of Responsibility for the Works and other Risk Items……………… 19
Insurance of the Works and other Risk Items……………………………………20
Timing (Insurance of the Works and other Risk Items)…………………………21
Indemnity for 3rd
Parties & 3rd
Party Property…………………………………..22
Public Liability Insurance………………………………………………………….23
Employers Liability Insurance…………………………………………………….24
Existing Facilities & Use or Occupation by Employer (Allocation of Risk)…… 25
Professional Indemnity Insurance………………………………………………... 26
Insurance (General Requirements)………………………………………………..27
Contents Flowchart No.
____________________________________________________________________________________
CONTRACTOR’S PERSONNEL / MANAGEMENT
Contractors Personnel / Management (1 of 5)………………………………. 28
(2 of 5)………………………………. 29
(3 of 5)………………………………. 30
(4 of 5)………………………………. 31
(5 of 5)………………………………. 32
Programming (General)………………………………………………………..33
(Revisions)……………………………………………………... 34
Progress Reports……………………………………………………………………35
Inspections and Tests……………………………………………………………… 36
EMPLOYER’S PERSONNEL
Employer’s Personnel (1 of 2)……………………………………………………37
(2 of 2)……………………………………………………38
Employer’s Representative………………………………………………………...39
ADMINISTRATION
ER Communications / Instructions………………………………………………..40
Required Contractor Submissions………………………………………………...41
Dispute regarding and Instruction (Direction or Change Order?)…………….. 42
Proposed Instructions………………………………………………………………43
Value Engineering…………………………………………………………………. 44
TIME
Time (Overview)……………………………………………………………..45
(Initial Dates)………………………………………………………….46
Programme Contingency (Generally)……………………………………….. 47
(Application)….…………………………………..48
Suspension by Employer…………………………………………………………...49
Taking Over Part of the Works……………………………………………………50
Delay and Extension of Time………………………………………………………51
Substantial Completion (Definition)………………………………………..52
(Application 1 of 2)……………………………….53
(Application 2 of 2)……………………………….54
(Implications 1 of 2)……………………………... 55
(Implications 2 of 2)……………………………... 56
4. Public Works Contract for Building Works Designed by the Employer (CF1 version 1.8 dated 04/09/2012)
Contents Flowchart No.
____________________________________________________________________________________
TIME (Continued)
Liquidated Damages………………………………………………………………..57
Defects Period (1 of 2)………………………………………………………….. 58
(2 of 2)………………………………………………………….. 59
CLAIMS
Occurrence of a Delaying Event…………………………………………………...60
Occurrence of a Compensation Event……………………………………………. 61
ER’s Determination………………………………………………………………...62
Delay Cost…………………………………………………………………………...63
Adjustments to the Contract Sum (for a Compensation Event)………………... 64
Employers Claims…………………………………………………………………..65
PAYMENT
Payment (Process)……………………………………………………………….66
(Valuation)…………………………………………………………….67
Interim Payment (Deductions)…………………………………………………….68
Non Payment Implications…………………………………………………………69
VAT and Tax………………………………………………………………………..70
TERMINATION
Termination on Contractor Default (Non Compliance)………………………… 71
(Insolvency)……………………………….. 72
Consequences of Contractor Default Termination (Non Compliance & Insolvency)… 73
Termination by the Contractor & at Employers Election……………………….74
Consequences of Termination by Contractor or at Employers Election………. 75
DISPUTES
Conciliation (1 of 2)………………………………………………………………... 76
Conciliation (2 of 2) and Arbitration……………………………………………...77
Abbreviations
________________________________________________
E = Employer (E’s = Employer’s)
ER = Employer’s Representative
QS = Quantity Surveyor
C = Contractor (C’s = Contractor’s)
CR = Contractor’s Representative
CS = Contractor’s Supervisor
SC = Substantial Completion
EOT = Extension of Time
LD = Liquidated Damages
Wkg = Working (as in Working Days)
Additional Services
________________________________________________
In addition to this flowchart booklet, further training is available on all or any
aspect of this guide and the form of contract (CF1). The author is also available to
execute research on specifically appointed topics, comment on tender and/or
contract documentation, act as an aid in construction disputes and other contractual
and administrative activities
Tomás Murphy MSCSI MRICS
Chartered & Registered Quantity Surveyor
________________________________________________
Crannagh, Gort, Co. Galway
Tel: M 087 6787738 W 091 742433 H 091 635073
Email: tomas.murphy@gmit.ie