This document summarizes a construction update meeting held on March 15, 2017 about the Oakland Children's Hospital expansion project. It discusses upcoming construction activities over the next few months, including exterior glass installation, lath and stucco work, roofing, and interior drywall. Weekend work is scheduled in March and April to remove scaffolding, install exterior finishes, and hoist roof materials. Progress photos were also shared. The meeting also included an overview of the Central Utility Plant expansion project, which will construct a new building to house mechanical equipment for hospital renovations. Site logistics and non-working hours were also discussed.