SlideShare a Scribd company logo
Graphical Analysis of NHGC Unit
    1 & 2 SCR Performance
    The need to replace catalyst due to
   premature performance degradation
   and no further options for service life
               optimization.
It is important to note that increases
 in ammonia flow can be an direct                     Ammonium Hydroxide Flow Unit 1
 representation of reduced catalyst
 reactivity.                                                       Avg. NH3 Flow

                                               700                                                     Rate of Ammonia use increase
                                               650                                                     was minimized via better control
                                           l   600                                                     and prevention of overfeeding.
                                           b
                                               550
                                           s
                                               500
                                           /
                                               450
                                           h
     Improved/lower levels due to              400
                                           r
     installed catalyst seal                   350
     strips(2/9/09).                           300
                                                     2006   2007    2008       2009   2010   2011




           High levels due to historically high CT
           emissions, flue gas bypassing the          Ammonium Hydroxide Flow Unit 2
           catalyst, and catalyst
           masking/plugging.                                       Avg. NH3 Flow

                                               700
                                                                                                        Rate of Ammonia use increase in
                                               650
                                           l                                                            2011 was minimized via better
                                               600                                                      control and prevention of
                                           b   550                                                      overfeeding on start up.
                                           s
                                               500
                                           /
                                               450
Improved/lower levels due to               h
                                               400
installed catalyst seal strips             r                                                        Further reductions realized due
                                               350
(2/29/08), vacuuming catalyst                                                                       to less cyclic operating profile.
surface, and improved CT                       300
emissions.                                           2006   2007    2008       2009   2010   2011
Environex 2007 SCR Catalyst Evaluation Unit 1




The SCR catalyst in Unit 2 is approaching end of life based on catalyst performance and operating data. By fall
2009, the SCR catalyst will no longer maintain emissions within design limits. Environex 2008 SCR Catalyst Evaluation Unit 2
(Conclusions)




This audit of the New Harquahala Units 1 and 2 SCR catalyst shows that the catalytic potential of the SCR
catalyst, as measured by lab-scale testing, is at the performance threshold. The catalyst performance level is
currently at its end of life condition. Cormetech SCR and CO Catalyst Inspection and Performance Test Report 2009
25
                                                               Unit 1 NOx following start up 2011                                           2.55


                                                                                                                                            2.45

                                                                                                                                     20.9
         20                                                                                                                                 2.35
                                                                                                                                         18.6
                                                                                                                                          2.25
                                                                                                              16.7       16.5     16.9
                                          15.6                               15.7                                           15.7
         15
                               14.4                                                             14.3              14.6 4.6
                                                                                                                     1         14.5         2.15
                                  14          13.9 3.8
                                                 1                                        14 13.7 14.2 13.7
lbs/hr




                                                                    13.6
                                                           13 12.6                12.8 12.5
                                       12.4          12.3        12.3 12.4 2.3 12.7 12.2
                                                                         1                           12.3                                          1st hr NOx lbs
                                                        11.3                                                                                2.05
                                                                             2.03                                                    2.03          lb/hr Limit
         10                    2.00                                                                                     2.00 .00
                                                                                                                           2
                         9.3                                                                                  1.97                 1.97 1.97       1st 3hr Avg ppm
                                                                                                                                          1.95
                                  1.93 1.93                                                                      1.93
                   7.4                                                                 1.90                                   1.90                 3hr ppm Limit
                                                                 1.87                     1.87       1.87
                                                                                                                                            1.85
          5                                   1.83 .83 .83
                                                 1 1                1.83         1.83        1.83 1.83     1.83      1.83
                                                            1.80       1.80         1.80        1.80    1.80
                         1.77          1.77              1.77 1.77        1.77
                                                                                                                                            1.75


          0                                                                                                                                 1.65
                 7/2/2011
                 7/5/2011
                 7/6/2011
                 7/7/2011
                 7/8/2011




                 8/1/2011
                 8/2/2011
                 8/3/2011
                 8/4/2011
                 8/5/2011
                 8/8/2011
                 8/9/2011




                 9/1/2011
                 9/3/2011
                 9/6/2011
                 9/8/2011
                6/22/2011




                7/11/2011
                7/12/2011
                7/13/2011
                7/18/2011
                7/19/2011
                7/20/2011
                7/21/2011




                8/10/2011
                8/11/2011
                8/15/2011
                8/16/2011
                8/17/2011
                8/18/2011
                8/19/2011
                8/22/2011
                8/26/2011
                8/27/2011
                8/29/2011
                8/30/2011
                                                                          Date
              Units 1 and 2 (next page) both show a reduced ability to control NOx emissions during the first few hours after start up. The
              catalyst at this time is within design operating temperatures though it has not yet reached normal operating temperatures
              that optimize the NOx conversion efficiency. To counter act the reduced performance (due both to catalyst degradation and
              transitional temperatures) during this time frame, NHGC must resort to feeding more aqueous ammonia into the SCR. While
              the increased ammonia injection has a short term impact on decreasing stack NOx, in the long run it more negatively impacts
              the emissions control efficiency by slowing the warm up process further hampering catalyst performance. This ultimately
              results in stack emissions excursions. As we approach closer to the permitted emissions limits, the probability of exceeding
              them increases as NHGC struggles to achieve adequate catalyst temperatures while injecting enough ammonia to meet stack
              emission limits. Unit 2 has the most operating hours and worst catalyst performance and is more prone to these excursions.
2.55
                                                     Unit 2 NOx following start up 2011
         25
                                                                                                                                                     2.45
                                                                                                                                              2.40
                                                                                                                                         21.5
                                                                                                                                                2.35
                                                                                                                                           20.5
         20
                                                                                  2.30
                                                                                                                                         2.27
                        17.7                                                                               17.8         17.8                         2.25
                                     16.9                                                 16.8           16.9
                                                                                                           2.20                16.9
                                                                                                                  16.4                          16.4
                                                                                     2.17                            15.9   15.7
         15        15.2        14.9                      15                                                                                          2.15
                      14.3        14.3 13.9                                                                       2.13    14.5    14.6
                                                                                                                                    14.4
lbs/hr




                                                              14             14      14               14.1
                             13.5                                                                   13.6
                                                                                                      2.10                                                  1st hr NOx lbs
                                                  13.1                                      12.7
                                               12.3 12.3
                                            12.2       12.2               12.3 12.2
                                                                        12.1                   12.4
                                                                                                 12.2                                         2.07
                                                                                                              11.9                                   2.05   lb/hr Limit
                        2.03
              11
         10                                                        10                                                                                       1st 3hr Avg ppm
              1.97                   1.97                                                                                         1.97
                                                                                                                                                     1.95   3hr ppm Limit
                                  1.93                                                                                1.93     1.93 1.93
                                                                 1.90                                                       1.90       1.90
                      1.87                                    1.87                              1.87 1.87 1.87           1.87
                                                                                                                                                     1.85
                   1.83    1.83        1.83
                                          1.83                                            1.83
                                                                                             1.83              1.83
          5
                              1.80               1.80 1.80
                                                         1.80           1.80
                                                                           1.80
                                                    1.77                      1.77
                                                                                                                                                     1.75
                                              1.70                                               1.70
          0                                                                                                                                          1.65




                                                                        Date
Following this excursion on                          Optimizing the ammonia feed system included restricting ammonia flow while the system was still in
8/9/2011 caused by overfeeding                       “start up” status to allow faster warm up of the SCR system and SCR catalyst before “online” status is
ammonium hydroxide during start                      achieved and the emissions limits become more restrictive (as identified in the graph above).
up, NHGC optimized the system to                     Also, the flow rate increase of ammonia after “online” status is achieved was reduced to prevent
better prevent an exceedence.                        quenching of the SCR system and a resulting loss of control in NOx emissions.
Addition Pertinent Information
NHGC hired Siemens to tune         Results and situations for 2011
  both Units 1 and 2                 made NHGC decide to do
  Combustion Turbines on             something to remedy
  8/2/2011. An effort was            catalyst performance.
  made to specifically               NHGC knew that catalyst
  improve NOx emissions at           needed to be replaced but
  the inlet to the SCR catalyst.     was hopeful that service life
  Data and trends show that          could be extended. When
  the effort did not have any        test results came back that
  appreciable impact                 catalyst cleaning would
  (increase or decrease)             have a negative impact the
  during and shortly after           effort to replace the catalyst
  start up.                          immediately became
                                     imperative.
Catalyst History/Timeline

  Accelerated Degradation Further
Complicated by CT Exhaust Emissions
90% Fresh Surface area all units

Units 2&3 adequate activity

Silica Fouling on Unit 1 below       Unit 2 Seal Strips Installed
design conversion                     and Catalyst vacuumed
June 2007 ~ Environex                    February 29, 2008


   2007
                                   2008                                          2009
                                          Unit 2 below design conversion of 90%
                                          Avg activity 54% (min 58%)

                                          silica, aluminum, insulation fouling, less
                                          than 90% surface area
                                          AIG free of salt deposits
                                          Unit 2 analysis April 2008 ~ Environex
February 2010
February 2009                                 Unit 3 operating at
                                                92% conversion
  Unit 1 Seal Strips                          (fresh sample 93%)
    Installed and
 Catalyst Vacuumed                               ~ Cormetech


2009                                                    2010


                 September 2009                                     August 2010
              Analysis shows Units 1 & 2 at or                         Units 1 & 2
               below design NOx Reduction                            operating below
                     Efficiency of 90%                                 90% design
                                                                     conversion rate
                Unit 1 shows 25% blockage
                    Unit 2 no plugging                                ~ Cormetech

                       Seal strips in place

                   Units 1 & 2 ~ Cormetech
January 2012
                                                                                    Unit 2 sample shows insufficient
                                                                     93% NOx       NOx conversion margin for reliable
                                                                                             performance.
                                                                     reduction
                                                                     rate needed      Significant surface loss found
February 2011                 August 2011                                               caused by fouling and de-
                                                                     at 35 ppm     lamination of the catalyst affecting
 Unit 3 Operating at   NHGC optimized SCR logic per Fuel                                  catalyst performance
 design conversion      Tech and tuned CT for optimum                                         Unit 2 ~ Environex
                           Catalyst inlet conditions

2011                                                                                 2012



                                     November 2011
                                  Analysis shows Units 1 & 2 at or
                                   below design NOx Reduction
                                         Efficiency of 90%

                                     Unit 3 at design efficiency

                                          Units 1, 2 & 3~
                                           Cormetech

More Related Content

Similar to Catalyst Performance Loss Timeline

Waterproofing New Technology & Appraoch
Waterproofing   New Technology & AppraochWaterproofing   New Technology & Appraoch
Waterproofing New Technology & AppraochARIJIT BASU
 
KTK-AR2011-ENG
KTK-AR2011-ENGKTK-AR2011-ENG
KTK-AR2011-ENGKTK
 
Dispersants & Coupling Agents: New Chemistry for a Mature Industry
Dispersants & Coupling Agents: New Chemistry for a Mature IndustryDispersants & Coupling Agents: New Chemistry for a Mature Industry
Dispersants & Coupling Agents: New Chemistry for a Mature Industry
Total Cray Valley
 
Cansorb p series_brochure
Cansorb p series_brochureCansorb p series_brochure
Cansorb p series_brochure
Distributor Service Incorporated
 
Using new modeling technology to help solve heavy oil processing issues final
Using new modeling technology to help solve heavy oil processing issues finalUsing new modeling technology to help solve heavy oil processing issues final
Using new modeling technology to help solve heavy oil processing issues final
Invensys Operations Management
 
20120209 aqp h1 2012 presentation final
20120209 aqp h1 2012 presentation final20120209 aqp h1 2012 presentation final
20120209 aqp h1 2012 presentation final
springweb
 
Recent Trends and Technologies for Shale Gas Completions
Recent Trends and Technologies for Shale Gas CompletionsRecent Trends and Technologies for Shale Gas Completions
Recent Trends and Technologies for Shale Gas CompletionsSergey Starokadomsky
 
Frito-Lay - Natural Gas Fleet
Frito-Lay - Natural Gas FleetFrito-Lay - Natural Gas Fleet
Frito-Lay - Natural Gas Fleet
Wisconsin Clean Cities
 

Similar to Catalyst Performance Loss Timeline (8)

Waterproofing New Technology & Appraoch
Waterproofing   New Technology & AppraochWaterproofing   New Technology & Appraoch
Waterproofing New Technology & Appraoch
 
KTK-AR2011-ENG
KTK-AR2011-ENGKTK-AR2011-ENG
KTK-AR2011-ENG
 
Dispersants & Coupling Agents: New Chemistry for a Mature Industry
Dispersants & Coupling Agents: New Chemistry for a Mature IndustryDispersants & Coupling Agents: New Chemistry for a Mature Industry
Dispersants & Coupling Agents: New Chemistry for a Mature Industry
 
Cansorb p series_brochure
Cansorb p series_brochureCansorb p series_brochure
Cansorb p series_brochure
 
Using new modeling technology to help solve heavy oil processing issues final
Using new modeling technology to help solve heavy oil processing issues finalUsing new modeling technology to help solve heavy oil processing issues final
Using new modeling technology to help solve heavy oil processing issues final
 
20120209 aqp h1 2012 presentation final
20120209 aqp h1 2012 presentation final20120209 aqp h1 2012 presentation final
20120209 aqp h1 2012 presentation final
 
Recent Trends and Technologies for Shale Gas Completions
Recent Trends and Technologies for Shale Gas CompletionsRecent Trends and Technologies for Shale Gas Completions
Recent Trends and Technologies for Shale Gas Completions
 
Frito-Lay - Natural Gas Fleet
Frito-Lay - Natural Gas FleetFrito-Lay - Natural Gas Fleet
Frito-Lay - Natural Gas Fleet
 

Catalyst Performance Loss Timeline

  • 1. Graphical Analysis of NHGC Unit 1 & 2 SCR Performance The need to replace catalyst due to premature performance degradation and no further options for service life optimization.
  • 2. It is important to note that increases in ammonia flow can be an direct Ammonium Hydroxide Flow Unit 1 representation of reduced catalyst reactivity. Avg. NH3 Flow 700 Rate of Ammonia use increase 650 was minimized via better control l 600 and prevention of overfeeding. b 550 s 500 / 450 h Improved/lower levels due to 400 r installed catalyst seal 350 strips(2/9/09). 300 2006 2007 2008 2009 2010 2011 High levels due to historically high CT emissions, flue gas bypassing the Ammonium Hydroxide Flow Unit 2 catalyst, and catalyst masking/plugging. Avg. NH3 Flow 700 Rate of Ammonia use increase in 650 l 2011 was minimized via better 600 control and prevention of b 550 overfeeding on start up. s 500 / 450 Improved/lower levels due to h 400 installed catalyst seal strips r Further reductions realized due 350 (2/29/08), vacuuming catalyst to less cyclic operating profile. surface, and improved CT 300 emissions. 2006 2007 2008 2009 2010 2011
  • 3. Environex 2007 SCR Catalyst Evaluation Unit 1 The SCR catalyst in Unit 2 is approaching end of life based on catalyst performance and operating data. By fall 2009, the SCR catalyst will no longer maintain emissions within design limits. Environex 2008 SCR Catalyst Evaluation Unit 2 (Conclusions) This audit of the New Harquahala Units 1 and 2 SCR catalyst shows that the catalytic potential of the SCR catalyst, as measured by lab-scale testing, is at the performance threshold. The catalyst performance level is currently at its end of life condition. Cormetech SCR and CO Catalyst Inspection and Performance Test Report 2009
  • 4. 25 Unit 1 NOx following start up 2011 2.55 2.45 20.9 20 2.35 18.6 2.25 16.7 16.5 16.9 15.6 15.7 15.7 15 14.4 14.3 14.6 4.6 1 14.5 2.15 14 13.9 3.8 1 14 13.7 14.2 13.7 lbs/hr 13.6 13 12.6 12.8 12.5 12.4 12.3 12.3 12.4 2.3 12.7 12.2 1 12.3 1st hr NOx lbs 11.3 2.05 2.03 2.03 lb/hr Limit 10 2.00 2.00 .00 2 9.3 1.97 1.97 1.97 1st 3hr Avg ppm 1.95 1.93 1.93 1.93 7.4 1.90 1.90 3hr ppm Limit 1.87 1.87 1.87 1.85 5 1.83 .83 .83 1 1 1.83 1.83 1.83 1.83 1.83 1.83 1.80 1.80 1.80 1.80 1.80 1.77 1.77 1.77 1.77 1.77 1.75 0 1.65 7/2/2011 7/5/2011 7/6/2011 7/7/2011 7/8/2011 8/1/2011 8/2/2011 8/3/2011 8/4/2011 8/5/2011 8/8/2011 8/9/2011 9/1/2011 9/3/2011 9/6/2011 9/8/2011 6/22/2011 7/11/2011 7/12/2011 7/13/2011 7/18/2011 7/19/2011 7/20/2011 7/21/2011 8/10/2011 8/11/2011 8/15/2011 8/16/2011 8/17/2011 8/18/2011 8/19/2011 8/22/2011 8/26/2011 8/27/2011 8/29/2011 8/30/2011 Date Units 1 and 2 (next page) both show a reduced ability to control NOx emissions during the first few hours after start up. The catalyst at this time is within design operating temperatures though it has not yet reached normal operating temperatures that optimize the NOx conversion efficiency. To counter act the reduced performance (due both to catalyst degradation and transitional temperatures) during this time frame, NHGC must resort to feeding more aqueous ammonia into the SCR. While the increased ammonia injection has a short term impact on decreasing stack NOx, in the long run it more negatively impacts the emissions control efficiency by slowing the warm up process further hampering catalyst performance. This ultimately results in stack emissions excursions. As we approach closer to the permitted emissions limits, the probability of exceeding them increases as NHGC struggles to achieve adequate catalyst temperatures while injecting enough ammonia to meet stack emission limits. Unit 2 has the most operating hours and worst catalyst performance and is more prone to these excursions.
  • 5. 2.55 Unit 2 NOx following start up 2011 25 2.45 2.40 21.5 2.35 20.5 20 2.30 2.27 17.7 17.8 17.8 2.25 16.9 16.8 16.9 2.20 16.9 16.4 16.4 2.17 15.9 15.7 15 15.2 14.9 15 2.15 14.3 14.3 13.9 2.13 14.5 14.6 14.4 lbs/hr 14 14 14 14.1 13.5 13.6 2.10 1st hr NOx lbs 13.1 12.7 12.3 12.3 12.2 12.2 12.3 12.2 12.1 12.4 12.2 2.07 11.9 2.05 lb/hr Limit 2.03 11 10 10 1st 3hr Avg ppm 1.97 1.97 1.97 1.95 3hr ppm Limit 1.93 1.93 1.93 1.93 1.90 1.90 1.90 1.87 1.87 1.87 1.87 1.87 1.87 1.85 1.83 1.83 1.83 1.83 1.83 1.83 1.83 5 1.80 1.80 1.80 1.80 1.80 1.80 1.77 1.77 1.75 1.70 1.70 0 1.65 Date Following this excursion on Optimizing the ammonia feed system included restricting ammonia flow while the system was still in 8/9/2011 caused by overfeeding “start up” status to allow faster warm up of the SCR system and SCR catalyst before “online” status is ammonium hydroxide during start achieved and the emissions limits become more restrictive (as identified in the graph above). up, NHGC optimized the system to Also, the flow rate increase of ammonia after “online” status is achieved was reduced to prevent better prevent an exceedence. quenching of the SCR system and a resulting loss of control in NOx emissions.
  • 6. Addition Pertinent Information NHGC hired Siemens to tune Results and situations for 2011 both Units 1 and 2 made NHGC decide to do Combustion Turbines on something to remedy 8/2/2011. An effort was catalyst performance. made to specifically NHGC knew that catalyst improve NOx emissions at needed to be replaced but the inlet to the SCR catalyst. was hopeful that service life Data and trends show that could be extended. When the effort did not have any test results came back that appreciable impact catalyst cleaning would (increase or decrease) have a negative impact the during and shortly after effort to replace the catalyst start up. immediately became imperative.
  • 7. Catalyst History/Timeline Accelerated Degradation Further Complicated by CT Exhaust Emissions
  • 8. 90% Fresh Surface area all units Units 2&3 adequate activity Silica Fouling on Unit 1 below Unit 2 Seal Strips Installed design conversion and Catalyst vacuumed June 2007 ~ Environex February 29, 2008 2007 2008 2009 Unit 2 below design conversion of 90% Avg activity 54% (min 58%) silica, aluminum, insulation fouling, less than 90% surface area AIG free of salt deposits Unit 2 analysis April 2008 ~ Environex
  • 9. February 2010 February 2009 Unit 3 operating at 92% conversion Unit 1 Seal Strips (fresh sample 93%) Installed and Catalyst Vacuumed ~ Cormetech 2009 2010 September 2009 August 2010 Analysis shows Units 1 & 2 at or Units 1 & 2 below design NOx Reduction operating below Efficiency of 90% 90% design conversion rate Unit 1 shows 25% blockage Unit 2 no plugging ~ Cormetech Seal strips in place Units 1 & 2 ~ Cormetech
  • 10. January 2012 Unit 2 sample shows insufficient 93% NOx NOx conversion margin for reliable performance. reduction rate needed Significant surface loss found February 2011 August 2011 caused by fouling and de- at 35 ppm lamination of the catalyst affecting Unit 3 Operating at NHGC optimized SCR logic per Fuel catalyst performance design conversion Tech and tuned CT for optimum Unit 2 ~ Environex Catalyst inlet conditions 2011 2012 November 2011 Analysis shows Units 1 & 2 at or below design NOx Reduction Efficiency of 90% Unit 3 at design efficiency Units 1, 2 & 3~ Cormetech