Don’t we all think that we get more done if we stay busy? We feel good and efficient. We may even get a pat on the back or even a promotion.
But is this good for the company? Is it good for our customers? Are we really optimizing for the whole or are we just keeping ourselves busy?
3. Good work!
Keep it up.
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
4. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
5. Everyone is busy but
we seem to be very
slow getting things
to our customers!
How are
we doing?
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
6. Håkan Forss
Lean Coach, Delivery Assistance
Hakan.forss@netent.com
@hakanforss
Flow Sensei / The Plumber
International Speaker
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
7. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
8. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
9. I’m a huge LEGO fan!
DISCLAIMER
LEGO® is a trademark of the LEGO Group,
which does not sponsor, authorize or
endorse this presentation.
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
10. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
11. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
12. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
13. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
14. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
15. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
16. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
17. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
18. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
19. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
20. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
21. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
22. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
23. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
24. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
25. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
26. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
27. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
28. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
29. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
30. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
31. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
32. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
33. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
34. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
35. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
36. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
37. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
38. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
39. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
40. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
41. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
42. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
43. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
44. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
45. > 1000 hours < 60 hours
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
46. A Question of focus
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
47. Strategy to increase utilization
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
48. Strategy to fulfill needs a.s.a.p.
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
49. Niklas Modig
Stockholm School of Economics
@LeanOnMyself
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
51. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
52. Strategy to fulfill needs a.s.a.p.
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
53. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
54. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
55. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
56. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
57. Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
58. Non value adding: Wait time
Non value adding: Required waste
Value adding: Actual demand
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
59. Which process is most expensive?
≥
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
61. Flow efficiency
Green + Yellow
Green + Yellow + Red
Flow efficiency =
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
62. Flow efficiency in numbers
Usually 1-5% value added of
total lead-time
20% value added is a high
number
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
63. How many
and
bricks do you have?
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
64. The three ”Laws”
Little’s Law
Law of bottlenecks
Law of variation
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
84. The three ”Laws”
Little’s Law
Law of bottlenecks
Law of variation
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
85. Law of Bottlenecks
Every process has one
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
86. Capacity = 6 Capacity = 4 Capacity = 6
Throughput = 4
You can’t go faster than your bottleneck
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
87. Full use of a higher capacity in front of the bottleneck will make
lead-time go up
You can’t go faster than your bottleneck
Capacity = 6 Capacity = 4 Capacity > 4
Throughput = 4
Created by Håkan Forss @hakanforss http://hakanforss.wordpress.com
88. The three ”Laws”
Little’s Law
Law of bottlenecks
Law of variation