1. Building Process :
1.) Inception and feasibility
-feasibility
- cost
-design issue
-consultants appointment
2.) Outline proposal & sketch design schematics :
-building outlook
-timing
-costing
3.) Design Development & Production Information:
-specification
-working drawing
4.) Tender Documentation & Tender Action:
-contractors tender for project
-prepare costing based on measurement on drawings and Bill of
Quality
-PAM Form Contract with Quality
-PAM Form Contract without Quality
5.) Project Planning, Operation on Site Completion:
-supervise the progress on site
-certify stage payments to ensure progress on site is monitored
-advising on conduct of the project
-resolving all contract dispute
-as built drawing and equipment operation manual to ensure
comprehension on building operation