SlideShare a Scribd company logo
1 of 6
Training Packet
Section 1: Updating a Conceptual Project
1. When calling on a conceptual project, who should I call first?
a. A conceptual project will, usually, have 1-4 contacts in the roles that
you want to call on
b. The best contact to start with, most of the time, will be the developer
i. The developer is usually involved with all aspects of a project,
and they will be able to give you a good amount of
information
ii. If a developer is not listed, the civil engineer and the owner
are other good sources that you’ll want to utilize
2. What information do I want to obtain when calling on a conceptual project?
a. First, when you call a contact, you don’t have to always ask for the
person listed in the roles, because if that particular developer,
engineer, etc. is out of the office, someone else might be able to help
you out
b. The first question you want to ask any contact you call is an updated
timeline (when will construction start?)
c. Second, find out if an architect or a general contractor has been
awarded (don’t say “hired”)
d. Third, make sure to ask for an email address for the contact you’re
calling on if one is not listed (even if the contact is out of the office,
ask the secretary if they have an email address where you can also
reach them)
e. Lastly, ask them when the best time would be to call back and get an
update on the project, and ask them if they are the best person to call
for an update (they may end up giving you a new contact through
asking this question)
3. What information do I need to obtain if an architect or a general contractor
has been awarded?
a. Don’t start out by flat out asking for the architect’s/general
contractor’s contact information
i. Instead, try saying, “that’s great! Who will you be working
with?” or try this, “I’m interested in getting in touch with the
architect/general contractor for future sub contractor bid
opportunities”
b. You always want to get the architect’s or general contractor’s
company name, address, and phone number
c. Try and get that architect’s/general contractor’s name so when an
architect or general contractor reporter calls on this project, they will
know who to speak with
d. If a civil engineer is the only contact listed, still call them and ask the
same questions
i. Since the civil engineer sometimes doesn’t know about the
involvement of an architect or general contractor, ask them if
they “happen to know if either one has been awarded, or will
be in the future”
ii. The civil engineer could know if either role has been
awarded, but don’t assume that they know
4. What if I call on a conceptual project that’s bidding out?
a. You can ask any contact, especially if a general contractor has not
been awarded, if this project will go out for “competitive bidding,”
and also try to find out who will handle the bidding and a possible bid
date
i. “Will the general contractor be negotiated or will you
competitively bid out for one?”
1. If a general contractor will be negotiated, ask if the
general contractor will be in charge of any other bid
opportunities
b. There are 3 important questions to ask when you find out that a
project is bidding out, or will bid out
i. How are you accepting bids (email, fax, snail mail, etc.)? GET
THE ADDRESS FOR WHERE BIDS SHOULD BE SUBMITTED!
ii. When is the deadline for accepting bids?
iii. Are there electronically available plans/docs/specs that we
could add to the project (we can only use PDF copies)?
5. IF YOU CALL ON A PROJECT AND THE CONTACT SAYS THAT IT’S CURRENTLY
UNDER CONSTRUCTION, ASK IF THEY WILL NEED ANY OTHER COMPETITIVE
PRICING FOR ANY TRADES OR IF “ALL TRADES HAVE BEEN LET”
Section 2: What’s the Status?
1. External Status = Conceptual
a. Contacts
i. Owner/Developer
ii. Engineer – Civil (ce)
iii. Consultant
iv. Master Planner
b. Plans, Specs, Docs
i. Site plans for zoning approval
2. External Status = Design
a. Contacts
i. Owner/Developer
ii. Architect
iii. Engineers – Structural, Civil, MEP
b. Plans, Specs, Docs
i. Completed construction schematics
3. External Status = Final Plan
a. Contacts
i. Owner/Developer
ii. Architect
iii. Engineers – Structural, Civil, MEP
b. Plans, Specs, Docs
i. Completed construction documents (working plans)
ii. Specifications
4. External Status = Pre-Construction – Negotiated
a. Contacts
i. Owner/Developer
ii. Architect
iii. Engineers – Structural, Civil, MEP
iv. Negotiated GC (general contractor), CM (construction
manager), or D/B (design/builder)
b. Plans, Specs, Docs
i. Schematics
ii. Construction documents
iii. Specifications
Section Three: How Do I Explain whatBidClerk is?
1. “BidClerk is an online plan room, similar to McGraw-Hill or REED
Construction.”
2. “BidClerk works with local contractors and suppliers in the area for possible
bid opportunities”
3. If they still don’t get BidClerk, you can always try this: “We post projects on
our at site at no charge, and then our subscribers, many of them sub
contractors, pay to view that project and the project details in order to find
bid opportunities in their area.” Try to make them understand that we
aren’t trying to solicit for bids
Section Four: What if they Really Don’tWant to Talk to Me?
1. For starters, don’t get discouraged or upset if someone is short, or even rude
to you, it happens to everyone!
2. Be as polite as possible, no matter what, and gently try to nudge the person
into giving you some information
3. If the person really, really doesn’t want to talk to BidClerk, try going back to
the lead source and getting the information that you need from someone at
the city, who may have other contacts for the project you could call
4. If all of the above fails, try giving the project a few weeks, or even a month,
(unless construction is supposed to start within the next 3 and ½ months)
and then try calling back
a. However, sometimes going to the city will prove more helpfully after
a certain point
Sub Division Questions
When calling on a project that is a sub division, there is different information that you
need to obtain
1. A sub division most likely will not use an architect, so that question isn’t
absolutely necessary
2. Let’s say you call on a developer contact for a sub division
a. First, ask that developer if they will be involved with all stages of
construction for the project, or if the landowner will just be sub
dividing the land and selling the parcels to other developers
b. If the developer will be involved with all aspects of construction, ask
them if they will be worker with a design/home builder
i. A design/home builder usually takes the place of an architect
c. Again, if the developer will be involved with all aspects of construction,
ask them if a general contractor will be used for the project, and if one
will, ask if the general contractor will be competitively bid out or
negotiated
Using CRM
Updating a Conceptual Project in CRM:
1. General Tab:
a. The external status of a conceptual project should be conceptual
b. When do you change the external status of a conceptual project?
i. If you get an architect contact, you change the external status
to design
ii. If you get a general contractor contact, you change the
external status to pre-construction/negotiated
c. The other important thing to change in CRM whenever you get an
architect or general contractor contact on a conceptual project, you
must change the description of the project
i. Change “Preliminary plans,” or “Schematic plans,” to “Design
plans”
2. Roles Tab:
a. Whenever you get a new contact for a project, add that contact to
the roles
i. If the company is not in CRM for the new contact, you must
create a new company in CRM
1. Details to include: company name, address, website (if
applicable), contact number, fax number, email
address (if applicable)
3. Administration Tab:
a. If you call on a project and get an updated construction start time
(that is six months or more than the current start date listed on
project under general tab), you get points for a 6 month status update
i. At the top of the page under the admin tab, there is a section
called publication
1. Whenever you get a status update, or any update, you
changed the 3 sections under publication
2. Internal Status: changes to QA
3. Reported On: changes to the date you updated it
4. Point(s) Type: for a 6 month update, you change the
points type to Update: 6 Mo Update / Status Change
b. If you call on a project and get an architect contact, you get points for
adding the architect
i. Under the publication section in the admin section, change
those 3 tabs
1. Internal Status: changes to QA
2. Reported On: changes to the date you updated it
3. Point(s) Type: change points type to Update: Architect
Added
ii. Whenever you add a architect to a project, you MUST ALWAYS
CHANGE THE ROLE AND LETTER ASSIGNMENT TO: ARCHITACT AND THE
FIRST LETTER OF THE ARCHITECT’S COMPANY NAME
c. If you call on a project and get a general contractor contact, you get
points for adding the general contractor
i. Under the publication section in the admin section, change
those 3 tabs
1. Internal Status: changes to QA
2. Reported On: changes to the date you updated it
3. Point(s) Type: change points type to Update: GC / CM
Added
ii. Whenever you add a general contractor to a project, you
MUST ALWAYS CHANGE THE ROLE AND LETTER ASSIGNMENT
TO: GENERAL CONTRACTOR AND THE FIRST LETTER OF THE
GENERAL CONTRACTOR’S COMPANY NAME
b. After you update all aspects of the project, under the administration
tab, change the follow-up date to about 2 weeks out, unless the project
is supposed to start soon
BidClerk Training Packet Example

More Related Content

Viewers also liked

一起出來玩服務介紹
一起出來玩服務介紹 一起出來玩服務介紹
一起出來玩服務介紹 Bill Lee
 
Controlador de temperatura pid eurotherm 2132i
Controlador de temperatura pid eurotherm 2132iControlador de temperatura pid eurotherm 2132i
Controlador de temperatura pid eurotherm 2132iHudson Costa Gonçalves
 
活動設計與行銷規劃 課程講義
活動設計與行銷規劃 課程講義活動設計與行銷規劃 課程講義
活動設計與行銷規劃 課程講義Bill Lee
 
一起出來玩 夥伴行銷計劃 2015/9-12
一起出來玩   夥伴行銷計劃 2015/9-12一起出來玩   夥伴行銷計劃 2015/9-12
一起出來玩 夥伴行銷計劃 2015/9-12Bill Lee
 
爆紅的秘密,如何編輯好照片,讓你的活動更出色!
爆紅的秘密,如何編輯好照片,讓你的活動更出色!爆紅的秘密,如何編輯好照片,讓你的活動更出色!
爆紅的秘密,如何編輯好照片,讓你的活動更出色!Bill Lee
 
Digital Learning Enviroment
Digital Learning EnviromentDigital Learning Enviroment
Digital Learning EnviromentLisette Hamilton
 

Viewers also liked (10)

January Newsletter
January NewsletterJanuary Newsletter
January Newsletter
 
Patel Bhavika
Patel BhavikaPatel Bhavika
Patel Bhavika
 
一起出來玩服務介紹
一起出來玩服務介紹 一起出來玩服務介紹
一起出來玩服務介紹
 
Controlador de temperatura pid eurotherm 2132i
Controlador de temperatura pid eurotherm 2132iControlador de temperatura pid eurotherm 2132i
Controlador de temperatura pid eurotherm 2132i
 
活動設計與行銷規劃 課程講義
活動設計與行銷規劃 課程講義活動設計與行銷規劃 課程講義
活動設計與行銷規劃 課程講義
 
February Newsletter
February NewsletterFebruary Newsletter
February Newsletter
 
quickrads
quickradsquickrads
quickrads
 
一起出來玩 夥伴行銷計劃 2015/9-12
一起出來玩   夥伴行銷計劃 2015/9-12一起出來玩   夥伴行銷計劃 2015/9-12
一起出來玩 夥伴行銷計劃 2015/9-12
 
爆紅的秘密,如何編輯好照片,讓你的活動更出色!
爆紅的秘密,如何編輯好照片,讓你的活動更出色!爆紅的秘密,如何編輯好照片,讓你的活動更出色!
爆紅的秘密,如何編輯好照片,讓你的活動更出色!
 
Digital Learning Enviroment
Digital Learning EnviromentDigital Learning Enviroment
Digital Learning Enviroment
 

Similar to BidClerk Training Packet Example

Pile Chapter 5 Design Process Ym
Pile Chapter 5   Design Process   YmPile Chapter 5   Design Process   Ym
Pile Chapter 5 Design Process YmGalala University
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryAkshika Mahanama
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfEyobMiteku
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In ConstructionSunil Manjeri
 
How to avoid the cowboy builder
How to avoid the cowboy builderHow to avoid the cowboy builder
How to avoid the cowboy builderZulaiha Amaria
 
How to avoid the cowboy builder
How to avoid the cowboy builderHow to avoid the cowboy builder
How to avoid the cowboy builderPraveen Sudarsan
 
Task 1 Different types Of Briefs
Task 1 Different types Of Briefs Task 1 Different types Of Briefs
Task 1 Different types Of Briefs terry96
 
unit-1-setting-up-practice_compress.pdf
unit-1-setting-up-practice_compress.pdfunit-1-setting-up-practice_compress.pdf
unit-1-setting-up-practice_compress.pdfABHISHEKMOHALKAR
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services Ashok Tundare
 
Organizational research case
Organizational research caseOrganizational research case
Organizational research caseBhooshan Kanani
 
Project CharterProject Title Project Start DateProjected Fi.docx
Project CharterProject Title Project Start DateProjected Fi.docxProject CharterProject Title Project Start DateProjected Fi.docx
Project CharterProject Title Project Start DateProjected Fi.docxwkyra78
 
Architectural Professional Practice - Fees
Architectural Professional Practice - FeesArchitectural Professional Practice - Fees
Architectural Professional Practice - FeesGalala University
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 

Similar to BidClerk Training Packet Example (20)

Pile Chapter 5 Design Process Ym
Pile Chapter 5   Design Process   YmPile Chapter 5   Design Process   Ym
Pile Chapter 5 Design Process Ym
 
Stakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction IndustryStakeholder’s Involvement in Construction Industry
Stakeholder’s Involvement in Construction Industry
 
Construction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdfConstruction Contracts Questions and Answers.pdf
Construction Contracts Questions and Answers.pdf
 
Constructability In Construction
Constructability In ConstructionConstructability In Construction
Constructability In Construction
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
How to avoid the cowboy builder
How to avoid the cowboy builderHow to avoid the cowboy builder
How to avoid the cowboy builder
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
How to avoid the cowboy builder
How to avoid the cowboy builderHow to avoid the cowboy builder
How to avoid the cowboy builder
 
Ici magazine
Ici magazineIci magazine
Ici magazine
 
Task 1 Different types Of Briefs
Task 1 Different types Of Briefs Task 1 Different types Of Briefs
Task 1 Different types Of Briefs
 
Briefs
BriefsBriefs
Briefs
 
unit-1-setting-up-practice_compress.pdf
unit-1-setting-up-practice_compress.pdfunit-1-setting-up-practice_compress.pdf
unit-1-setting-up-practice_compress.pdf
 
Internship report
Internship reportInternship report
Internship report
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
Organizational research case
Organizational research caseOrganizational research case
Organizational research case
 
Bid & spec 101
Bid & spec 101Bid & spec 101
Bid & spec 101
 
Project CharterProject Title Project Start DateProjected Fi.docx
Project CharterProject Title Project Start DateProjected Fi.docxProject CharterProject Title Project Start DateProjected Fi.docx
Project CharterProject Title Project Start DateProjected Fi.docx
 
Architectural Professional Practice - Fees
Architectural Professional Practice - FeesArchitectural Professional Practice - Fees
Architectural Professional Practice - Fees
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 

BidClerk Training Packet Example

  • 1. Training Packet Section 1: Updating a Conceptual Project 1. When calling on a conceptual project, who should I call first? a. A conceptual project will, usually, have 1-4 contacts in the roles that you want to call on b. The best contact to start with, most of the time, will be the developer i. The developer is usually involved with all aspects of a project, and they will be able to give you a good amount of information ii. If a developer is not listed, the civil engineer and the owner are other good sources that you’ll want to utilize 2. What information do I want to obtain when calling on a conceptual project? a. First, when you call a contact, you don’t have to always ask for the person listed in the roles, because if that particular developer, engineer, etc. is out of the office, someone else might be able to help you out b. The first question you want to ask any contact you call is an updated timeline (when will construction start?) c. Second, find out if an architect or a general contractor has been awarded (don’t say “hired”) d. Third, make sure to ask for an email address for the contact you’re calling on if one is not listed (even if the contact is out of the office, ask the secretary if they have an email address where you can also reach them) e. Lastly, ask them when the best time would be to call back and get an update on the project, and ask them if they are the best person to call for an update (they may end up giving you a new contact through asking this question) 3. What information do I need to obtain if an architect or a general contractor has been awarded? a. Don’t start out by flat out asking for the architect’s/general contractor’s contact information i. Instead, try saying, “that’s great! Who will you be working with?” or try this, “I’m interested in getting in touch with the architect/general contractor for future sub contractor bid opportunities” b. You always want to get the architect’s or general contractor’s company name, address, and phone number c. Try and get that architect’s/general contractor’s name so when an architect or general contractor reporter calls on this project, they will know who to speak with
  • 2. d. If a civil engineer is the only contact listed, still call them and ask the same questions i. Since the civil engineer sometimes doesn’t know about the involvement of an architect or general contractor, ask them if they “happen to know if either one has been awarded, or will be in the future” ii. The civil engineer could know if either role has been awarded, but don’t assume that they know 4. What if I call on a conceptual project that’s bidding out? a. You can ask any contact, especially if a general contractor has not been awarded, if this project will go out for “competitive bidding,” and also try to find out who will handle the bidding and a possible bid date i. “Will the general contractor be negotiated or will you competitively bid out for one?” 1. If a general contractor will be negotiated, ask if the general contractor will be in charge of any other bid opportunities b. There are 3 important questions to ask when you find out that a project is bidding out, or will bid out i. How are you accepting bids (email, fax, snail mail, etc.)? GET THE ADDRESS FOR WHERE BIDS SHOULD BE SUBMITTED! ii. When is the deadline for accepting bids? iii. Are there electronically available plans/docs/specs that we could add to the project (we can only use PDF copies)? 5. IF YOU CALL ON A PROJECT AND THE CONTACT SAYS THAT IT’S CURRENTLY UNDER CONSTRUCTION, ASK IF THEY WILL NEED ANY OTHER COMPETITIVE PRICING FOR ANY TRADES OR IF “ALL TRADES HAVE BEEN LET” Section 2: What’s the Status? 1. External Status = Conceptual a. Contacts i. Owner/Developer ii. Engineer – Civil (ce) iii. Consultant iv. Master Planner b. Plans, Specs, Docs i. Site plans for zoning approval 2. External Status = Design a. Contacts i. Owner/Developer ii. Architect
  • 3. iii. Engineers – Structural, Civil, MEP b. Plans, Specs, Docs i. Completed construction schematics 3. External Status = Final Plan a. Contacts i. Owner/Developer ii. Architect iii. Engineers – Structural, Civil, MEP b. Plans, Specs, Docs i. Completed construction documents (working plans) ii. Specifications 4. External Status = Pre-Construction – Negotiated a. Contacts i. Owner/Developer ii. Architect iii. Engineers – Structural, Civil, MEP iv. Negotiated GC (general contractor), CM (construction manager), or D/B (design/builder) b. Plans, Specs, Docs i. Schematics ii. Construction documents iii. Specifications Section Three: How Do I Explain whatBidClerk is? 1. “BidClerk is an online plan room, similar to McGraw-Hill or REED Construction.” 2. “BidClerk works with local contractors and suppliers in the area for possible bid opportunities” 3. If they still don’t get BidClerk, you can always try this: “We post projects on our at site at no charge, and then our subscribers, many of them sub contractors, pay to view that project and the project details in order to find bid opportunities in their area.” Try to make them understand that we aren’t trying to solicit for bids Section Four: What if they Really Don’tWant to Talk to Me? 1. For starters, don’t get discouraged or upset if someone is short, or even rude to you, it happens to everyone! 2. Be as polite as possible, no matter what, and gently try to nudge the person into giving you some information 3. If the person really, really doesn’t want to talk to BidClerk, try going back to the lead source and getting the information that you need from someone at the city, who may have other contacts for the project you could call
  • 4. 4. If all of the above fails, try giving the project a few weeks, or even a month, (unless construction is supposed to start within the next 3 and ½ months) and then try calling back a. However, sometimes going to the city will prove more helpfully after a certain point Sub Division Questions When calling on a project that is a sub division, there is different information that you need to obtain 1. A sub division most likely will not use an architect, so that question isn’t absolutely necessary 2. Let’s say you call on a developer contact for a sub division a. First, ask that developer if they will be involved with all stages of construction for the project, or if the landowner will just be sub dividing the land and selling the parcels to other developers b. If the developer will be involved with all aspects of construction, ask them if they will be worker with a design/home builder i. A design/home builder usually takes the place of an architect c. Again, if the developer will be involved with all aspects of construction, ask them if a general contractor will be used for the project, and if one will, ask if the general contractor will be competitively bid out or negotiated Using CRM Updating a Conceptual Project in CRM: 1. General Tab: a. The external status of a conceptual project should be conceptual b. When do you change the external status of a conceptual project? i. If you get an architect contact, you change the external status to design ii. If you get a general contractor contact, you change the external status to pre-construction/negotiated c. The other important thing to change in CRM whenever you get an architect or general contractor contact on a conceptual project, you must change the description of the project i. Change “Preliminary plans,” or “Schematic plans,” to “Design plans” 2. Roles Tab: a. Whenever you get a new contact for a project, add that contact to the roles
  • 5. i. If the company is not in CRM for the new contact, you must create a new company in CRM 1. Details to include: company name, address, website (if applicable), contact number, fax number, email address (if applicable) 3. Administration Tab: a. If you call on a project and get an updated construction start time (that is six months or more than the current start date listed on project under general tab), you get points for a 6 month status update i. At the top of the page under the admin tab, there is a section called publication 1. Whenever you get a status update, or any update, you changed the 3 sections under publication 2. Internal Status: changes to QA 3. Reported On: changes to the date you updated it 4. Point(s) Type: for a 6 month update, you change the points type to Update: 6 Mo Update / Status Change b. If you call on a project and get an architect contact, you get points for adding the architect i. Under the publication section in the admin section, change those 3 tabs 1. Internal Status: changes to QA 2. Reported On: changes to the date you updated it 3. Point(s) Type: change points type to Update: Architect Added ii. Whenever you add a architect to a project, you MUST ALWAYS CHANGE THE ROLE AND LETTER ASSIGNMENT TO: ARCHITACT AND THE FIRST LETTER OF THE ARCHITECT’S COMPANY NAME c. If you call on a project and get a general contractor contact, you get points for adding the general contractor i. Under the publication section in the admin section, change those 3 tabs 1. Internal Status: changes to QA 2. Reported On: changes to the date you updated it 3. Point(s) Type: change points type to Update: GC / CM Added ii. Whenever you add a general contractor to a project, you MUST ALWAYS CHANGE THE ROLE AND LETTER ASSIGNMENT TO: GENERAL CONTRACTOR AND THE FIRST LETTER OF THE GENERAL CONTRACTOR’S COMPANY NAME b. After you update all aspects of the project, under the administration tab, change the follow-up date to about 2 weeks out, unless the project is supposed to start soon