Curriculum vitae for BWAMBALE Godfrey Lubangula
CURRICULUM VITAE FOR BWAMBALE GODFREY LUBANGULA
GENERAL INFORMATION
FIRST NAME : BWAMBALE
OTHER NAMES : GODFREY LUBANGULA
PROFESSION : CIVIL & ENVIRONMENTAL ENGINEER
QUALIFICATION : BSc. CIVIL & ENV. ENG
SEX : MALE
DATE OF BIRTH : 10/11/1988
RELIGION : ANGLICAN
NATIONALITY : UGANDAN
DISTRICT OF RESIDENCE : KAMPALA
PERMANENTADDRESS : KASESE
MARITAL STATUS : SINGLE
CONTACTADDRESS (Tel.) : +256 783 691337 / +256 704 482 099
EMAIL : lubz.godie@gmail.com
ACADEMIC BACKGROUND
YEAR INSTITUTION/SCHOOL QUALIFICATION
OBTAINED
STATUS GRADE
CGPA
DATE OF
GRADUATION
2011-
2015
Uganda Christian
University – P.O Box 4,
Mukono, Uganda
Bachelor of Science in
Civil and Environmental
Engineering (Hons)
Honors 2nd
Class
Degree
GGPA
3.22
Graduated on
3rd July, 2015
2009-
2010
Kyambogo College School
–P.O Box 20142, Kampala
Uganda Advanced
Certificate of Education
4-Principle
Passes
Fourteen
(14) Points
Completed in
December,2010
2005-
2008
Nganwa High School –
P.O Box 44, Bushenyi
Uganda Certificate of
Education (U.C.E)
Division
Two (2)
8C’s - 37
Aggregates
Completed in
December,2008
2001-
2004
Mother Care Preparatory
School, Kasese
Primary Leaving
Examinations (P.L.E)
Division
One (1)
11
Aggregates
Completed in
November,2004
OTHER ACADEMIC AWARDS
PERIOD INSTITUTION/ORGANISATION QUALIFICATION OBTAINED
11th -29th August,
2014
Engineering Ministries International
(EMI) - Canada
A certificate in practical applications of
Engineering survey equipment and software
6th -8th May, 2014 Bridge Head 24 Ltd - Uganda A Certificate in the NSSF Career Expo 2014
Sept – Nov 2011 Uganda Christian University A Certificate in Alpha Course & Discipleship
2011 -2014 Uganda Christian University Certificate of participation in Cultural gala
Curriculum vitae for BWAMBALE Godfrey Lubangula
PROFESSIONAL PROFILE/STATUS
GODFREY is a graduate of Uganda Christian University with an Honors Second Class Degree of Science
in Civil and Environmental Engineering. He has proven track record of outstanding performance acquired
from on hand experience in design and construction supervision in the areas of Road works/Highways,
Building Construction, Computer Aided Design of Structures, Research and Report writing/documentation.
GODFREY has been acquainted with vast knowledge and ability to read and interpret architectural and
engineering drawings, specifications, codes, and other material pertinent to construction including working
knowledge of building components and systems, construction materials, means and methods. He has
excellent written and oral communication skills and ability to establish and maintain professional working
relationships. He is a reliable, trustworthy, self-motivated and hard working.
RESEARCH PROJECTS
2014-2015- Investigating the use of Uganda’s local bamboo strips as an alternative to steel for
reinforcement of low cost concrete structures.
PRIOR WORK EXPERIENCE
YEAR COMPANY POSITION PORTFOLIO
Oct, 2015
– To date
FENCON
Consulting
Engineers Ltd,
Seguku –
Entebbe Road
Clerk of
Works
(COW) –
Civil
Engineer
Construction supervision of a 4-storey 40 apartment
units for Masaka Regional Referral Hospital Staff Hostel
o Coordinate, monitor and inspect work of construction
contractor in accordance to specifications and standards.
o Time, Cost and Quality control for assigned project
o Assist the Contractor to come up with onsite workshop
sketches and ensure their approval by the Project Manager.
o Keep a site diary of all site activities, material stock, labour
and equipment.
o Ensure proper record and database for project drawings and
documents.
o Coordinate and attend site meetings and take minutes.
o Prepare monthly reports to the Project Manager
o Assist Contractor to come up with on-site workshop
sketches and ensure they are approved by the PM.
o Coordinating and managing the health and safety aspects
on the construction works on site
Curriculum vitae for BWAMBALE Godfrey Lubangula
May –
Sept 2015
FENCON
Consulting
Engineers Ltd,
Seguku –
Entebbe Road
Graduate
Trainee
Design & Construction supervision | Civil/Road Works |
Bridges | Building | Water | Irrigation & Drainage |
Sanitation, Health & Environment | Master Planning | Oil
& Gas | Transportation | Real Estate Management.
o Preparing the Strategic Investment/Master Plan.
o Bills of Quantities (BoQ’s) and Bar Bending Schedules
o Engineering studies i.e. Planning, Structural analysis
and design, coordination, design/technical report, etc.
o Preparing structural drawings;
o Preparation of Tender documents
o Preparing Architectural drawings and 3D Artistic
impressions;
o Soil/Geotechnical investigations
o Surveying/Field work
o Construction Supervision
May –
September
, 2014
PROME
Consultants
Ltd, Kampala
Internee Construction supervision of Road works to bitumen
standard
o Day to day site inspection of works
o Prepare work registers
o Carryout joint measurements with contractor
o Advise the contractor on the specifications
o Make progress reports and take photographs
May –
September
, 2013
Assured
Engineering
Services Ltd,
Masaka
Internee Participated in construction and rehabilitation works on
Mukeya-Kakira-Mukatete district gravel road project,
Kyenjojo District
May-
September
, 2012
Uganda
Christian
University,
Mukono
Workshop
training
Construction and Maintenance of Civil Works
o Building construction
o Rehabilitation of road works
o Metal works
o Plumbing
o Carpentry
o Water supply, treatment and distribution
Curriculum vitae for BWAMBALE Godfrey Lubangula
o Wastewater treatment and disposal
o Arch CAD, Solid edge and AutoCAD
o Remote Sensing and GIS
REPRESENTATIONS AND RESPONSIBILITIES
2014 – 2015 Student Member (UIPE) Uganda Institute of Professional Engineers
2014 – 2015 Student Member (UCUEA) Uganda Christian University Engineering Association
2013 – 2014 Assistant Chaplain (KAMUSA - UCU) Kasese Mukono Students’ Association
2012 – 2013General Speaker (KAMUSA - UCU) Kasese Mukono Students’ Association
PROFESSIONAL SKILLS AND ABILITIES
LANGUAGE PROFIENCY
S/N Language Speaking Writing Comprehension
1.0 English Excellent Excellent Excellent
2.0 Lukonzo Excellent Good Excellent
3.0 Runyankole Excellent Good Good
4.0 Luganda Good Good Good
5.0 Rutoro Excellent Good Good
6.0 Runyakitara Good Fair Good
7.0 Kiswahili Fair Fair Fair
. COMPUTER AIDED DESIGN AND LITERACY
S/N Computer package Level of expertise
1.0 Revit Architectural 2009, 2014 & 2015 High
2.0 AutoCAD design software Medium
3.0 Microsoft Office |Word Processing|Excel|Power point High
4.0 Microsoft projects Medium
5.0 Prokon (Structural Analysis software) Medium
6.0 Internet and software High
INTERESTS AND HOBBIES
 Passion in structural and Highway design and construction works
 Networking and coordinating with different kinds of people
 Reading newspaper and watching television
 Serving God.
 Playing football
Curriculum vitae for BWAMBALE Godfrey Lubangula
REFERENCES
1. Eng. Fataki Gabriel
C.E.O, FENCON Consulting Engineers Limited,
Block 266, Plot 60
Regnol Fuel Station, Entebbe Road,
P.O Box 24802, Kampala – Uganda
Tel: +256-772988313
Email: fataki.gabriel@yahoo.com; fenconconsult@gmail.com
Website: www.fenconconsulting.com
2. Eng. Fred Kasango
PROME Consultants Ltd,
Innovations House, Plot 7B Babiiha Avenue, Formally Acacia Avenue
P.O Box 24934, Kampala – Uganda
Email: frediekasango@gmail.com, or fkasango@promeconsult.com,
Website: www.promeconsult.com
Cell: +256-782731892
Tel: +256-414345543/4
Fax: +256-414345149
3. Eng. Mugarura Benon
Assured Engineering Services Limited,
Plot 3-5, Baines Terrace Road,
P.O Box 1066, Masaka – Uganda
Tel: +256-771 412810
Fax: +256-481 420508
Email: assured@yahoo.com
DECLARATION
I BWAMBALE GODFREY LUBANGULA, declare and certify that the information provided above is
a true record of my own experience and complete to the best of my knowledge. I understand that any
misrepresentation or material omission made on this document may render my candidature null & void
or lead to termination of employment.
Date: ____________________________ Signature: ___________________________

BG CV

  • 1.
    Curriculum vitae forBWAMBALE Godfrey Lubangula CURRICULUM VITAE FOR BWAMBALE GODFREY LUBANGULA GENERAL INFORMATION FIRST NAME : BWAMBALE OTHER NAMES : GODFREY LUBANGULA PROFESSION : CIVIL & ENVIRONMENTAL ENGINEER QUALIFICATION : BSc. CIVIL & ENV. ENG SEX : MALE DATE OF BIRTH : 10/11/1988 RELIGION : ANGLICAN NATIONALITY : UGANDAN DISTRICT OF RESIDENCE : KAMPALA PERMANENTADDRESS : KASESE MARITAL STATUS : SINGLE CONTACTADDRESS (Tel.) : +256 783 691337 / +256 704 482 099 EMAIL : lubz.godie@gmail.com ACADEMIC BACKGROUND YEAR INSTITUTION/SCHOOL QUALIFICATION OBTAINED STATUS GRADE CGPA DATE OF GRADUATION 2011- 2015 Uganda Christian University – P.O Box 4, Mukono, Uganda Bachelor of Science in Civil and Environmental Engineering (Hons) Honors 2nd Class Degree GGPA 3.22 Graduated on 3rd July, 2015 2009- 2010 Kyambogo College School –P.O Box 20142, Kampala Uganda Advanced Certificate of Education 4-Principle Passes Fourteen (14) Points Completed in December,2010 2005- 2008 Nganwa High School – P.O Box 44, Bushenyi Uganda Certificate of Education (U.C.E) Division Two (2) 8C’s - 37 Aggregates Completed in December,2008 2001- 2004 Mother Care Preparatory School, Kasese Primary Leaving Examinations (P.L.E) Division One (1) 11 Aggregates Completed in November,2004 OTHER ACADEMIC AWARDS PERIOD INSTITUTION/ORGANISATION QUALIFICATION OBTAINED 11th -29th August, 2014 Engineering Ministries International (EMI) - Canada A certificate in practical applications of Engineering survey equipment and software 6th -8th May, 2014 Bridge Head 24 Ltd - Uganda A Certificate in the NSSF Career Expo 2014 Sept – Nov 2011 Uganda Christian University A Certificate in Alpha Course & Discipleship 2011 -2014 Uganda Christian University Certificate of participation in Cultural gala
  • 2.
    Curriculum vitae forBWAMBALE Godfrey Lubangula PROFESSIONAL PROFILE/STATUS GODFREY is a graduate of Uganda Christian University with an Honors Second Class Degree of Science in Civil and Environmental Engineering. He has proven track record of outstanding performance acquired from on hand experience in design and construction supervision in the areas of Road works/Highways, Building Construction, Computer Aided Design of Structures, Research and Report writing/documentation. GODFREY has been acquainted with vast knowledge and ability to read and interpret architectural and engineering drawings, specifications, codes, and other material pertinent to construction including working knowledge of building components and systems, construction materials, means and methods. He has excellent written and oral communication skills and ability to establish and maintain professional working relationships. He is a reliable, trustworthy, self-motivated and hard working. RESEARCH PROJECTS 2014-2015- Investigating the use of Uganda’s local bamboo strips as an alternative to steel for reinforcement of low cost concrete structures. PRIOR WORK EXPERIENCE YEAR COMPANY POSITION PORTFOLIO Oct, 2015 – To date FENCON Consulting Engineers Ltd, Seguku – Entebbe Road Clerk of Works (COW) – Civil Engineer Construction supervision of a 4-storey 40 apartment units for Masaka Regional Referral Hospital Staff Hostel o Coordinate, monitor and inspect work of construction contractor in accordance to specifications and standards. o Time, Cost and Quality control for assigned project o Assist the Contractor to come up with onsite workshop sketches and ensure their approval by the Project Manager. o Keep a site diary of all site activities, material stock, labour and equipment. o Ensure proper record and database for project drawings and documents. o Coordinate and attend site meetings and take minutes. o Prepare monthly reports to the Project Manager o Assist Contractor to come up with on-site workshop sketches and ensure they are approved by the PM. o Coordinating and managing the health and safety aspects on the construction works on site
  • 3.
    Curriculum vitae forBWAMBALE Godfrey Lubangula May – Sept 2015 FENCON Consulting Engineers Ltd, Seguku – Entebbe Road Graduate Trainee Design & Construction supervision | Civil/Road Works | Bridges | Building | Water | Irrigation & Drainage | Sanitation, Health & Environment | Master Planning | Oil & Gas | Transportation | Real Estate Management. o Preparing the Strategic Investment/Master Plan. o Bills of Quantities (BoQ’s) and Bar Bending Schedules o Engineering studies i.e. Planning, Structural analysis and design, coordination, design/technical report, etc. o Preparing structural drawings; o Preparation of Tender documents o Preparing Architectural drawings and 3D Artistic impressions; o Soil/Geotechnical investigations o Surveying/Field work o Construction Supervision May – September , 2014 PROME Consultants Ltd, Kampala Internee Construction supervision of Road works to bitumen standard o Day to day site inspection of works o Prepare work registers o Carryout joint measurements with contractor o Advise the contractor on the specifications o Make progress reports and take photographs May – September , 2013 Assured Engineering Services Ltd, Masaka Internee Participated in construction and rehabilitation works on Mukeya-Kakira-Mukatete district gravel road project, Kyenjojo District May- September , 2012 Uganda Christian University, Mukono Workshop training Construction and Maintenance of Civil Works o Building construction o Rehabilitation of road works o Metal works o Plumbing o Carpentry o Water supply, treatment and distribution
  • 4.
    Curriculum vitae forBWAMBALE Godfrey Lubangula o Wastewater treatment and disposal o Arch CAD, Solid edge and AutoCAD o Remote Sensing and GIS REPRESENTATIONS AND RESPONSIBILITIES 2014 – 2015 Student Member (UIPE) Uganda Institute of Professional Engineers 2014 – 2015 Student Member (UCUEA) Uganda Christian University Engineering Association 2013 – 2014 Assistant Chaplain (KAMUSA - UCU) Kasese Mukono Students’ Association 2012 – 2013General Speaker (KAMUSA - UCU) Kasese Mukono Students’ Association PROFESSIONAL SKILLS AND ABILITIES LANGUAGE PROFIENCY S/N Language Speaking Writing Comprehension 1.0 English Excellent Excellent Excellent 2.0 Lukonzo Excellent Good Excellent 3.0 Runyankole Excellent Good Good 4.0 Luganda Good Good Good 5.0 Rutoro Excellent Good Good 6.0 Runyakitara Good Fair Good 7.0 Kiswahili Fair Fair Fair . COMPUTER AIDED DESIGN AND LITERACY S/N Computer package Level of expertise 1.0 Revit Architectural 2009, 2014 & 2015 High 2.0 AutoCAD design software Medium 3.0 Microsoft Office |Word Processing|Excel|Power point High 4.0 Microsoft projects Medium 5.0 Prokon (Structural Analysis software) Medium 6.0 Internet and software High INTERESTS AND HOBBIES  Passion in structural and Highway design and construction works  Networking and coordinating with different kinds of people  Reading newspaper and watching television  Serving God.  Playing football
  • 5.
    Curriculum vitae forBWAMBALE Godfrey Lubangula REFERENCES 1. Eng. Fataki Gabriel C.E.O, FENCON Consulting Engineers Limited, Block 266, Plot 60 Regnol Fuel Station, Entebbe Road, P.O Box 24802, Kampala – Uganda Tel: +256-772988313 Email: fataki.gabriel@yahoo.com; fenconconsult@gmail.com Website: www.fenconconsulting.com 2. Eng. Fred Kasango PROME Consultants Ltd, Innovations House, Plot 7B Babiiha Avenue, Formally Acacia Avenue P.O Box 24934, Kampala – Uganda Email: frediekasango@gmail.com, or fkasango@promeconsult.com, Website: www.promeconsult.com Cell: +256-782731892 Tel: +256-414345543/4 Fax: +256-414345149 3. Eng. Mugarura Benon Assured Engineering Services Limited, Plot 3-5, Baines Terrace Road, P.O Box 1066, Masaka – Uganda Tel: +256-771 412810 Fax: +256-481 420508 Email: assured@yahoo.com DECLARATION I BWAMBALE GODFREY LUBANGULA, declare and certify that the information provided above is a true record of my own experience and complete to the best of my knowledge. I understand that any misrepresentation or material omission made on this document may render my candidature null & void or lead to termination of employment. Date: ____________________________ Signature: ___________________________