BEST PRACTICES FOR NEW PROJECT
COMMISSIONING
CREATE AN A-TEAM
 The size as well as specialisation of the commissioning team differs from project
to project.
 However, general knowledge of engineering systems and processes, hands-on
experience and understanding of the construction phase are salient features that
are expected to possess by majority of the team members.
BUDGET, SCOPE AND SCHEDULE OF
COMMISSIONING
 Start the commissioning phase prior to the formal beginning of any of the
design phases. Consider commissioning as a formal component of the
project and start assessing project schedules, delivery plan and
commissioning budget.
 Before any actual work starts, prepare and finalise heavily detailed plans.
The scope of the commissioning process helps figure out all the systems to
be commissioned as well as the extent of commissioning, delegate
responsibilities and roles across the design and construction teams, and
stay within the commissioning budget.
 When you take this step early on in the project, the commissioning plan –
including the responsibilities and roles of contractors – can be included in
construction-specific documents and contractual agreement, which helps
ensure that everyone involved in the project stays committed to the plan.
FINALISE AND EXECUTE PROJECT PLANS
 For smaller construction projects, this may be as simple as
creating spread sheets and sharing them with the project team
through emails.
 However, for larger projects today, some advanced type of cloud-
based commissioning management systems software is utilised
by project teams.
 This helps offer every team member access to information in
real-time while improving efficiency with better quality control and
higher degree of collaboration between members of the project
team.
HOLD THE DESIGN PHASE INITIAL MEETING
 The design phase initial meeting helps align the initial understanding of the
requirements of building design with the commissioning plan.
 The number as well as frequency of reviewing design document varies on the
basis of the complexity and size of the project – but there should be minimum
one initial review to discuss the whole project at length.
CONDUCT THE CONSTRUCTION PHASE INITIAL
MEETING
 While all the activities focused towards construction are important, having
buy-in as well as an in-depth understanding of the commissioning phase
from all the contractors involved is perhaps the most crucial one.
 This is not the ideal time to issue instructions, but it’s the time to facilitate
collaboration and nurture mutual respect among different members of the
teams involved – all working towards the prime goal of achieving the best
results possible for the building owner.
 It’s also the time when all the parties involved should be well aware of
(and trained if required) the best commissioning software and process
that will be utilised to communicate and resolve issues.
HAVE PERIODIC COMMISSIONING CHECK-INS
 Given the complexity and high level of details involved to start up and
commission a new building, process is of the essence.
 The project team (and other stakeholders involved, if any) will require
having continuous access to the current information.
 It is true that too many meetings result in wastage and inefficiency when it
is about construction projects, but for the commissioning process, a
dedicated meeting is a must.
 Have commissioning check-ins with key stakeholders and contractors to
see if the necessary communication is occurring, and problems are being
managed and resolved instantly and regularly.
VISIT THE WORK SITE FREQUENTLY
 Regular visits to the site should be a scheduled and recurring element
of your commissioning plan.
 Assess and get involved in important activities as they occur along the
way.
 Simultaneously, review functional test reports, start-up reports, and test
and balance reports, along with any other crucial documents.
 Communicate with contractors about the issues that they would have
faced during high-impact activities.
CONTACT US
 Address: Global Commissioning Management and Software
Ltd, Unit 2, Chestfield Business Park
Whitstable | Kent, CT5 3JB
 https://www.facebook.com/GlobalCxMLtd
 https://twitter.com/_globalltd
 https://www.instagram.com/global_cxm/
 https://www.linkedin.com/company/global-commissioning-
management-software-ltd
Best practices for new project commissioning

More Related Content

Similar to Best practices for new project commissioning

5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
YasirHamour
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
Olivia Wilson
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
Olivia Wilson
 
project influnceing
project influnceingproject influnceing
project influnceing
KUSHVIR SINGH
 
Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016
L Douglas Sargent Jr
 
The spectacular ways of General Contractor Software for monumental constructi...
The spectacular ways of General Contractor Software for monumental constructi...The spectacular ways of General Contractor Software for monumental constructi...
The spectacular ways of General Contractor Software for monumental constructi...
iFieldsmart Technologies
 
Chapter7 database management system.pptx
Chapter7 database management system.pptxChapter7 database management system.pptx
Chapter7 database management system.pptx
MohammedNouh7
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning Phase
Olivia Wilson
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
Amr E. Mohamed
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
MSharmilaDeviITDEPT
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.com
mkhilauria
 
Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docx
gilpinleeanna
 
SEN-22413 - UNIT - V.pptx
SEN-22413 -  UNIT - V.pptxSEN-22413 -  UNIT - V.pptx
SEN-22413 - UNIT - V.pptx
FreefireGarena22
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
Fáber D. Giraldo
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
Mostafa Ewees
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
ssuserc0e4e0
 
Implementing an effective Corporate Real Estate Project Framework in global o...
Implementing an effective Corporate Real Estate Project Framework in global o...Implementing an effective Corporate Real Estate Project Framework in global o...
Implementing an effective Corporate Real Estate Project Framework in global o...
jcquinn
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
IRJET Journal
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
Jaafer Saeed
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
krunalchem
 

Similar to Best practices for new project commissioning (20)

5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
 
Commissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction PhaseCommissioning-Specific Best Practices during the Construction Phase
Commissioning-Specific Best Practices during the Construction Phase
 
project influnceing
project influnceingproject influnceing
project influnceing
 
Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016
 
The spectacular ways of General Contractor Software for monumental constructi...
The spectacular ways of General Contractor Software for monumental constructi...The spectacular ways of General Contractor Software for monumental constructi...
The spectacular ways of General Contractor Software for monumental constructi...
 
Chapter7 database management system.pptx
Chapter7 database management system.pptxChapter7 database management system.pptx
Chapter7 database management system.pptx
 
Importance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning PhaseImportance of Communication during the Commissioning Phase
Importance of Communication during the Commissioning Phase
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.com
 
Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docx
 
SEN-22413 - UNIT - V.pptx
SEN-22413 -  UNIT - V.pptxSEN-22413 -  UNIT - V.pptx
SEN-22413 - UNIT - V.pptx
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
Implementing an effective Corporate Real Estate Project Framework in global o...
Implementing an effective Corporate Real Estate Project Framework in global o...Implementing an effective Corporate Real Estate Project Framework in global o...
Implementing an effective Corporate Real Estate Project Framework in global o...
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 

More from Olivia Wilson

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?
Olivia Wilson
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptx
Olivia Wilson
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko Software
Olivia Wilson
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?
Olivia Wilson
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko Software
Olivia Wilson
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko Software
Olivia Wilson
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdf
Olivia Wilson
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System
Olivia Wilson
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists
Olivia Wilson
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdf
Olivia Wilson
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptx
Olivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
Olivia Wilson
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
Olivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
Olivia Wilson
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
Olivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
Olivia Wilson
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
Olivia Wilson
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
Olivia Wilson
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
Olivia Wilson
 
Important Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and ValidationImportant Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and Validation
Olivia Wilson
 

More from Olivia Wilson (20)

Is a permit to work a safe system of work?
Is a permit to work a safe system of work?Is a permit to work a safe system of work?
Is a permit to work a safe system of work?
 
Is a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptxIs a permit to work a safe system of work.pptx
Is a permit to work a safe system of work.pptx
 
Salient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko SoftwareSalient Features of Gecko Permits - Gecko Software
Salient Features of Gecko Permits - Gecko Software
 
Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?Why Commissioning Authority Should Complete Commissioning Checklists?
Why Commissioning Authority Should Complete Commissioning Checklists?
 
Benefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko SoftwareBenefits of Permit-to-Work Software – Gecko Software
Benefits of Permit-to-Work Software – Gecko Software
 
Best Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko SoftwareBest Practice Commissioning Factors - Gecko Software
Best Practice Commissioning Factors - Gecko Software
 
An Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdfAn Abridged to Permit to Work Systems.pdf
An Abridged to Permit to Work Systems.pdf
 
4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System 4 Key Advantages a Digitised Permit to Work System
4 Key Advantages a Digitised Permit to Work System
 
9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists9 Tips to Improve Construction Site Inspection Checklists
9 Tips to Improve Construction Site Inspection Checklists
 
Commissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdfCommissioning Management Software and its Importance.pdf
Commissioning Management Software and its Importance.pdf
 
Commissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptxCommissioning Management Software and its Importance.pptx
Commissioning Management Software and its Importance.pptx
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning5 Common Misconceptions about Commissioning
5 Common Misconceptions about Commissioning
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANTWHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
WHY ARE PERMIT TO WORK SYSTEMS IMPORTANT
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
Importance of Permit to Work System
Importance of Permit to Work SystemImportance of Permit to Work System
Importance of Permit to Work System
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
 
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UKBEST COMMISSIONING MANAGEMENT SERVICES IN UK
BEST COMMISSIONING MANAGEMENT SERVICES IN UK
 
Important Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and ValidationImportant Factors of Commissioning, Qualification and Validation
Important Factors of Commissioning, Qualification and Validation
 

Recently uploaded

Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based SolutionsRevolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
Excel coatings
 
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) PrincipleMECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
Operational Excellence Consulting
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Satta Matka Dpboss Kalyan Matka Results
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
concepsionchomo153
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
advik4387
 
The Enigmatic Gemini: Unveiling the Dual Personalities
The Enigmatic Gemini: Unveiling the Dual PersonalitiesThe Enigmatic Gemini: Unveiling the Dual Personalities
The Enigmatic Gemini: Unveiling the Dual Personalities
my Pandit
 
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
essorprof62
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
Helen Meek
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
msthrill
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
Eternity Paralegal Services
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Niswey
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
IPLTech Electric
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024
Adnet Communications
 
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fixKalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
satta Matta matka 143 Kalyan chart jodi 6366249026
 
deft. 2024 pricing guide for onboarding
deft.  2024 pricing guide for onboardingdeft.  2024 pricing guide for onboarding
deft. 2024 pricing guide for onboarding
hello960827
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 

Recently uploaded (20)

Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based SolutionsRevolutionizing Surface Protection Xlcoatings Nano Based Solutions
Revolutionizing Surface Protection Xlcoatings Nano Based Solutions
 
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) PrincipleMECE (Mutually Exclusive, Collectively Exhaustive) Principle
MECE (Mutually Exclusive, Collectively Exhaustive) Principle
 
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka ResultsKalyan Chart Satta Matka Dpboss Kalyan Matka Results
Kalyan Chart Satta Matka Dpboss Kalyan Matka Results
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
 
The Enigmatic Gemini: Unveiling the Dual Personalities
The Enigmatic Gemini: Unveiling the Dual PersonalitiesThe Enigmatic Gemini: Unveiling the Dual Personalities
The Enigmatic Gemini: Unveiling the Dual Personalities
 
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
❽❽❻❼❼❻❻❸❾❻ DPBOSS NET SPBOSS SATTA MATKA RESULT KALYAN MATKA GUESSING FREE KA...
 
Kanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR ReportKanban Coaching Exchange with Dave White - Example SDR Report
Kanban Coaching Exchange with Dave White - Example SDR Report
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Pro Tips for Effortless Contract Management
Pro Tips for Effortless Contract ManagementPro Tips for Effortless Contract Management
Pro Tips for Effortless Contract Management
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
Sustainable Logistics for Cost Reduction_ IPLTech Electric's Eco-Friendly Tra...
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024TriStar Gold Corporate Presentation - June 2024
TriStar Gold Corporate Presentation - June 2024
 
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fixKalyan chart 6366249026 India satta Matta Matka 143 jodi fix
Kalyan chart 6366249026 India satta Matta Matka 143 jodi fix
 
deft. 2024 pricing guide for onboarding
deft.  2024 pricing guide for onboardingdeft.  2024 pricing guide for onboarding
deft. 2024 pricing guide for onboarding
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 

Best practices for new project commissioning

  • 1. BEST PRACTICES FOR NEW PROJECT COMMISSIONING
  • 2. CREATE AN A-TEAM  The size as well as specialisation of the commissioning team differs from project to project.  However, general knowledge of engineering systems and processes, hands-on experience and understanding of the construction phase are salient features that are expected to possess by majority of the team members.
  • 3. BUDGET, SCOPE AND SCHEDULE OF COMMISSIONING  Start the commissioning phase prior to the formal beginning of any of the design phases. Consider commissioning as a formal component of the project and start assessing project schedules, delivery plan and commissioning budget.  Before any actual work starts, prepare and finalise heavily detailed plans. The scope of the commissioning process helps figure out all the systems to be commissioned as well as the extent of commissioning, delegate responsibilities and roles across the design and construction teams, and stay within the commissioning budget.  When you take this step early on in the project, the commissioning plan – including the responsibilities and roles of contractors – can be included in construction-specific documents and contractual agreement, which helps ensure that everyone involved in the project stays committed to the plan.
  • 4. FINALISE AND EXECUTE PROJECT PLANS  For smaller construction projects, this may be as simple as creating spread sheets and sharing them with the project team through emails.  However, for larger projects today, some advanced type of cloud- based commissioning management systems software is utilised by project teams.  This helps offer every team member access to information in real-time while improving efficiency with better quality control and higher degree of collaboration between members of the project team.
  • 5. HOLD THE DESIGN PHASE INITIAL MEETING  The design phase initial meeting helps align the initial understanding of the requirements of building design with the commissioning plan.  The number as well as frequency of reviewing design document varies on the basis of the complexity and size of the project – but there should be minimum one initial review to discuss the whole project at length.
  • 6. CONDUCT THE CONSTRUCTION PHASE INITIAL MEETING  While all the activities focused towards construction are important, having buy-in as well as an in-depth understanding of the commissioning phase from all the contractors involved is perhaps the most crucial one.  This is not the ideal time to issue instructions, but it’s the time to facilitate collaboration and nurture mutual respect among different members of the teams involved – all working towards the prime goal of achieving the best results possible for the building owner.  It’s also the time when all the parties involved should be well aware of (and trained if required) the best commissioning software and process that will be utilised to communicate and resolve issues.
  • 7. HAVE PERIODIC COMMISSIONING CHECK-INS  Given the complexity and high level of details involved to start up and commission a new building, process is of the essence.  The project team (and other stakeholders involved, if any) will require having continuous access to the current information.  It is true that too many meetings result in wastage and inefficiency when it is about construction projects, but for the commissioning process, a dedicated meeting is a must.  Have commissioning check-ins with key stakeholders and contractors to see if the necessary communication is occurring, and problems are being managed and resolved instantly and regularly.
  • 8. VISIT THE WORK SITE FREQUENTLY  Regular visits to the site should be a scheduled and recurring element of your commissioning plan.  Assess and get involved in important activities as they occur along the way.  Simultaneously, review functional test reports, start-up reports, and test and balance reports, along with any other crucial documents.  Communicate with contractors about the issues that they would have faced during high-impact activities.
  • 9. CONTACT US  Address: Global Commissioning Management and Software Ltd, Unit 2, Chestfield Business Park Whitstable | Kent, CT5 3JB  https://www.facebook.com/GlobalCxMLtd  https://twitter.com/_globalltd  https://www.instagram.com/global_cxm/  https://www.linkedin.com/company/global-commissioning- management-software-ltd