©2016 KBR, Inc. All Rights Reserved 2
Moving To New AVEVA Technology
Implementing AVEVA Engage and AVEVA E3D
©2016 KBR, Inc. All Rights Reserved 3
Presentation Agenda
 About KBR
 What KBR do
 KBR and AVEVA collaborations
 Recent example – AVEVA ENGAGE
 Implementing AVEVA E3D at KBR
 Important considerations
 KBR Plan – Stages One, Two and Three
 Summary
 Questions
©2016 KBR, Inc. All Rights Reserved 4
About KBR
 KBR is a global provider of differentiated professional services and technologies across the asset and program life cycle
within the Hydrocarbons and Government Services Sectors. KBR employs over 31,000 people worldwide, with customers
in more than 80 countries, and operations in 40 countries, across three synergistic global businesses:
 Government Services, serving government customers globally, including capabilities that cover the full life-cycle of
defence, space, aviation and other government programs and missions from research and development, through systems
engineering, test and evaluation, program management, to operations, maintenance, and field logistics
 Technology & Consulting, including proprietary technology focused on the monetization of hydrocarbons (especially
natural gas and natural gas liquids) in ethylene and petrochemicals; ammonia, nitric acid and fertilizers; oil refining;
gasification; oil and gas consulting; integrity management; naval architecture and proprietary hulls; and downstream
consulting
 Engineering & Construction, including onshore oil and gas; LNG (liquefaction and regasification)/GTL; oil refining;
petrochemicals; chemicals; fertilizers; differentiated EPC; maintenance services (Brown & Root Industrial Services);
offshore oil and gas; fixed solutions (shallow-water, deep-water, subsea); floating solutions (FPU, FPSO, FLNG & FSRU); and
program management
 KBR is proud to work with its customers across the globe to provide technology, value-added services, integrated EPC
delivery and long term operations and maintenance services to ensure consistent delivery with predictable results.
©2016 KBR, Inc. All Rights Reserved 5
Offshore Oil and Gas – Fixed Solutions
Shallow Water, Deep Water and Subsea
Offshore Oil and Gas – Floating Solutions
FPU, FPSO, FLNG and FSRU
What KBR do
©2016 KBR, Inc. All Rights Reserved 6
Onshore - Oil and Gas, LNG/GTL, Oil Refining,
Petrochemicals, Chemicals, Fertilizers
What KBR do
©2016 KBR, Inc. All Rights Reserved 7
Onshore/Offshore Mega Projects
What KBR do
©2016 KBR, Inc. All Rights Reserved 8
KBR and AVEVA collaborations
 Users of PDMS for 40 years, recent average of 650 users globally (peaked at 1250 users)
 SPOOLING/SPOOLER – need arose from alliance type profit share projects
 GLOBAL– early recognition of multi location mega projects
 CLASH MANAGER (Model Management Suite) – inclusion of key KBR functionality and work flows
into AVEVA products
 Application Installs – creation of silent installs and standardisation across all application installs
 E3D SUPPORTS – following feedback from large work share project usage i.e. too many clicks,
reliance on ATTA placement in PIPE’s
 Other developments such as Data Access Control, Status Control, Distributed Attributes…
 Attendance of AVEVA ERG’s (External Reference Groups)
©2016 KBR, Inc. All Rights Reserved 9
 Request: a live current KBR project in AVEVA ENGAGE
 4 week window from request to required by date
 PDMS 12.1 project, not running E3D and not running AVEVA Net
 Involved the import of :
– 80,606 Engineering Tags (exported from Data Warehouse)
– 224,925 Document to Tag References (exported from Data Warehouse)
– 8,316 Isometrics (exported from Documentum)
– 2,539 Engineering Documents (exported from Documentum)
– 5,781 Supplier Documents (exported from Documentum)
– Plus the entire 3D topsides and jacket model (database size 6.56 GB)
 All achieved in 3 weeks which included the generation of a video
Recent example – AVEVA ENGAGE
©2016 KBR, Inc. All Rights Reserved 10
 KBR’s experience was almost “Plug and Play”
 Understand the hardware requirements
 Bring in the experts to expedite initial setup (AVEVA Net)
 A well defined information and data model greatly helps
 Easy to expand, start simple and add capability/value
 Visual Query – simple and easy to use value add tool
 Can be introduced at any stage of a project
 No user training required
AVEVA Engage key points summary
©2016 KBR, Inc. All Rights Reserved 11
Implementing E3D at KBR
 Use AVEVA for knowledge gathering workshops
 Prioritise requirements (identify quick or easy wins to help
justify business case)
 Define the scope (very important)
 Create a detailed plan (dates, resources, dependencies)
 Use AVEVA services if you need to accelerate schedule or require
particular new technology skills/expertise
 Make no assumptions, expect the unexpected
 Do not rush in unplanned, this is a major change
©2016 KBR, Inc. All Rights Reserved 12
Important considerations
 Hardware (Workstations - graphics cards, RAM, monitors, OS / Servers - disk space, RAM, OS /
New - touch and mobile devices )
 PDMS only, E3D only or mixed PDMS/E3D projects
 PDMS and E3D very different environments and have many inter-dependencies
– Environmental variable changes, new data and folder structures
– MDS (SECTIONS/MDS/MDU) vs SUPPORTS (GENSECS/ACP/APS)
– STEELWORK/STRUCTURES (Changes SECTIONS/GENSECS, new catalogues, new GUI’s)
– PDMSDFLTS/AVEVA_DESIGN_DFLTS, PDMSUI/PMLUI and PMLIB/E3DLIB
– Project changes MAS/ACP and SAM/APS
– DRAFT/DRAW library decisions
– Company specific catalogues and customised PML applications
©2016 KBR, Inc. All Rights Reserved 13
Important considerations (continued)
 E3D transition is not just about one application, it’s about many, but how many (defining the scope)?
– E3D (MODEL, DRAW, ISODRAFT, SPOOL)
– ADMINISTRATION (ADMIN, LEXICON replacing PDMS ADMIN and LEXICON)
– CATALOGUE (PARAGON, PROPCON replacing PDMS PARAGON and PROPCON)
– Cache Service
– Application Service
– E3D INSIGHT
– ENGAGE (and AVEVA Net?)
– GCD Creator
 Upgrade Training
©2016 KBR, Inc. All Rights Reserved 14
KBR Plan - Stage One (Complete)
 Mixed PDMS and E3D project environment
 Skip E3D 1.1 minimal benefit but E3D 2.1 adds immediate value
 Start with introduction of E3D 2.1 “out of the box”
– Create KBR silent installs and mixed heterogeneous environment
 Take advantage of new functionality:
– Improved working with laser data (BubbleView and HyperBubble)
– Make available the easier to use DRAW
– Use the database cache service to improve performance
 Provides quick and early access to E3D, INSIGHT and ENGAGE
©2016 KBR, Inc. All Rights Reserved 15
KBR Plan - Stage One (Complete)
©2016 KBR, Inc. All Rights Reserved 16
KBR Plan - Stage Two (In Progress)
 Use AVEVA services for preparing key dependencies:
– MDS support catalogue conversion (KBR support standards)
– Structural steelwork catalogue (KBR offshore joints and fittings standards)
– Structural fittings catalogue (KBR penetration standards)
 Use new functionality included in E3D to replace legacy KBR and AVEVA applications:
– Hole Management (replace KBR Penetrations)
– Status Control/Data Grid (replace VPE and Model Object Manager)
– Draw/Data Grid or Engineering (replace Deliverable Manager)
 Once stage two is completed:
– Enable new E3D SUPPORTS (replace KBR MDS) and E3D STRUCTURES to be used
– Replacement of the legacy Model Management Suite 

©2016 KBR, Inc. All Rights Reserved 17
KBR Plan - Stage Three (Future)
 Test, certify and release all remaining KBR value add
customisations and add-on applications written in PML for use
with E3D
 This statement doesn’t sound like much does it but…
 This process is expedited by having established test plans and
test reports for each of these minor applications
 Once stage three is completed, option to switch to using E3D
only
 Last but not least update KBR SRO Documentation
©2016 KBR, Inc. All Rights Reserved 18
©2016 KBR, Inc. All Rights Reserved 19
KBR Plan - Stage Three (Future)
 This process is expedited by having
established test plans and test reports for
each of these minor applications
 Once stage three is completed, option to
switch to using E3D only
 Last but not least update KBR SRO
Documentation
©2016 KBR, Inc. All Rights Reserved 20
 Knowledge gather thoroughly first
 Define scope
 Make a detailed plan
 Consider bringing in the experts to expedite
 Allow for contingencies
 Use established test plans and reports for add-on apps
 Don’t forget about the training and documentation
AVEVA E3D key points summary
©2016 KBR, Inc. All Rights Reserved 21
avevaworld.com
@aveva
/aveva

More Related Content

What's hot

OilGasDigitalTransformationWhitePaper
OilGasDigitalTransformationWhitePaperOilGasDigitalTransformationWhitePaper
OilGasDigitalTransformationWhitePaper
Andre Vieira
 
Asset Lifecycle Conceptual Models
Asset Lifecycle Conceptual ModelsAsset Lifecycle Conceptual Models
Asset Lifecycle Conceptual Models
Alex Chatha
 
Introduction to Capella and Arcadia with a Simple System
Introduction to Capella and Arcadia with a Simple SystemIntroduction to Capella and Arcadia with a Simple System
Introduction to Capella and Arcadia with a Simple System
Obeo
 

What's hot (20)

Variability management with Capella and pure::variants
Variability management with Capella and pure::variantsVariability management with Capella and pure::variants
Variability management with Capella and pure::variants
 
OilGasDigitalTransformationWhitePaper
OilGasDigitalTransformationWhitePaperOilGasDigitalTransformationWhitePaper
OilGasDigitalTransformationWhitePaper
 
Case study successfully planning and executing a p6 eppm implementation roa...
Case study   successfully planning and executing a p6 eppm implementation roa...Case study   successfully planning and executing a p6 eppm implementation roa...
Case study successfully planning and executing a p6 eppm implementation roa...
 
PLM-ERP Integration
PLM-ERP IntegrationPLM-ERP Integration
PLM-ERP Integration
 
Overview of Model Based Systems Engineering Using Innoslate
Overview of Model Based Systems Engineering Using InnoslateOverview of Model Based Systems Engineering Using Innoslate
Overview of Model Based Systems Engineering Using Innoslate
 
Project Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesProject Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation Slides
 
Building Adaptive Systems with Wardley Mapping, Domain-Driven Design, and Tea...
Building Adaptive Systems with Wardley Mapping, Domain-Driven Design, and Tea...Building Adaptive Systems with Wardley Mapping, Domain-Driven Design, and Tea...
Building Adaptive Systems with Wardley Mapping, Domain-Driven Design, and Tea...
 
IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service StrategyIT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
IT Portfolio Management Using Enterprise Architecture and ITIL® Service Strategy
 
Transform Procurement with the SAP S/4HANA Digital Core and SAP Ariba Solutions
Transform Procurement with the SAP S/4HANA Digital Core and SAP Ariba SolutionsTransform Procurement with the SAP S/4HANA Digital Core and SAP Ariba Solutions
Transform Procurement with the SAP S/4HANA Digital Core and SAP Ariba Solutions
 
Sprinting to Value in Industry 4.0
Sprinting to Value in Industry 4.0Sprinting to Value in Industry 4.0
Sprinting to Value in Industry 4.0
 
Architecture Document Template
Architecture Document TemplateArchitecture Document Template
Architecture Document Template
 
[EclipseCon France 2018 - Unconference] Capella Workshop
[EclipseCon France 2018 - Unconference] Capella Workshop[EclipseCon France 2018 - Unconference] Capella Workshop
[EclipseCon France 2018 - Unconference] Capella Workshop
 
Asset Lifecycle Conceptual Models
Asset Lifecycle Conceptual ModelsAsset Lifecycle Conceptual Models
Asset Lifecycle Conceptual Models
 
Introduction to Capella and Arcadia with a Simple System
Introduction to Capella and Arcadia with a Simple SystemIntroduction to Capella and Arcadia with a Simple System
Introduction to Capella and Arcadia with a Simple System
 
Togaf 9.1 ADM summary
Togaf 9.1 ADM summaryTogaf 9.1 ADM summary
Togaf 9.1 ADM summary
 
AVEVA’s BIM History and Vision by AVEVA
AVEVA’s BIM History and Vision by AVEVAAVEVA’s BIM History and Vision by AVEVA
AVEVA’s BIM History and Vision by AVEVA
 
Mro spare parts optimisation and inventory reduction uk 2017 11
Mro spare parts optimisation and inventory reduction uk 2017 11Mro spare parts optimisation and inventory reduction uk 2017 11
Mro spare parts optimisation and inventory reduction uk 2017 11
 
Modeling Big Data with the ArchiMate 3.0 Language
Modeling Big Data with the ArchiMate 3.0 LanguageModeling Big Data with the ArchiMate 3.0 Language
Modeling Big Data with the ArchiMate 3.0 Language
 
MBSE and the Business of Engineering
MBSE and the Business of EngineeringMBSE and the Business of Engineering
MBSE and the Business of Engineering
 
Capability-based planning with TOGAF & ArchiMate
Capability-based planning with TOGAF & ArchiMateCapability-based planning with TOGAF & ArchiMate
Capability-based planning with TOGAF & ArchiMate
 

Viewers also liked

Viewers also liked (20)

Trusted Living Point Cloud for Owner/Operators and EPCs
Trusted Living Point Cloud for Owner/Operators and EPCsTrusted Living Point Cloud for Owner/Operators and EPCs
Trusted Living Point Cloud for Owner/Operators and EPCs
 
Data-Centric Approach for Project Delivery
Data-Centric Approach for Project DeliveryData-Centric Approach for Project Delivery
Data-Centric Approach for Project Delivery
 
A Journey to E3D
A Journey to E3DA Journey to E3D
A Journey to E3D
 
The Revolution of Brownfield Project Engineering
The Revolution of Brownfield Project EngineeringThe Revolution of Brownfield Project Engineering
The Revolution of Brownfield Project Engineering
 
Integrated Engineering Deployment in a New Engineering Office
Integrated Engineering Deployment in a New Engineering OfficeIntegrated Engineering Deployment in a New Engineering Office
Integrated Engineering Deployment in a New Engineering Office
 
A Journey into the Digital World
A Journey into the Digital WorldA Journey into the Digital World
A Journey into the Digital World
 
Making Data Work Better
Making Data Work BetterMaking Data Work Better
Making Data Work Better
 
Schematics: Let’s share…
Schematics: Let’s share…Schematics: Let’s share…
Schematics: Let’s share…
 
Optimizing Your Information through Interoperability
Optimizing Your Information through Interoperability Optimizing Your Information through Interoperability
Optimizing Your Information through Interoperability
 
The Right Time for the Right Tool
The Right Time for the Right ToolThe Right Time for the Right Tool
The Right Time for the Right Tool
 
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction CostsWhy 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
 
Data integrity and consistency
Data integrity and consistencyData integrity and consistency
Data integrity and consistency
 
Template Design for SAGD
Template Design for SAGDTemplate Design for SAGD
Template Design for SAGD
 
Information Governance
Information GovernanceInformation Governance
Information Governance
 
Integrated Data Requirements by Tedd Weitzman, Southern Company
Integrated Data Requirements by Tedd Weitzman, Southern CompanyIntegrated Data Requirements by Tedd Weitzman, Southern Company
Integrated Data Requirements by Tedd Weitzman, Southern Company
 
Working Together to Minimize Claims; Maximize Performance
Working Together to Minimize Claims; Maximize PerformanceWorking Together to Minimize Claims; Maximize Performance
Working Together to Minimize Claims; Maximize Performance
 
Bring the power of the sun to Earth with AVEVA by Fabien Berruyer and Guilla...
Bring the power of the sun to Earth with AVEVA by Fabien Berruyer and Guilla...Bring the power of the sun to Earth with AVEVA by Fabien Berruyer and Guilla...
Bring the power of the sun to Earth with AVEVA by Fabien Berruyer and Guilla...
 
Eastman Chemical Company introduces SEIGA
Eastman Chemical Company introduces SEIGA Eastman Chemical Company introduces SEIGA
Eastman Chemical Company introduces SEIGA
 
Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...Transformational Change in Managing Assets for Operational Excellence by Jan ...
Transformational Change in Managing Assets for Operational Excellence by Jan ...
 
Delivering Asset Management for Infrastructure Projects by Liam Gallagher, Ja...
Delivering Asset Management for Infrastructure Projects by Liam Gallagher, Ja...Delivering Asset Management for Infrastructure Projects by Liam Gallagher, Ja...
Delivering Asset Management for Infrastructure Projects by Liam Gallagher, Ja...
 

Similar to Moving To New AVEVA Technology

IWSM2014 MEGSUS14 - GQM on energy for SaaS - CETIC
IWSM2014   MEGSUS14 - GQM on energy for SaaS - CETICIWSM2014   MEGSUS14 - GQM on energy for SaaS - CETIC
IWSM2014 MEGSUS14 - GQM on energy for SaaS - CETIC
Nesma
 
Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...
Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...
Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...
Inflectra
 

Similar to Moving To New AVEVA Technology (20)

Application Modernisation with PKS
Application Modernisation with PKSApplication Modernisation with PKS
Application Modernisation with PKS
 
Application Modernisation with PKS
Application Modernisation with PKSApplication Modernisation with PKS
Application Modernisation with PKS
 
Gas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation BrazilGas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation Brazil
 
IWSM2014 MEGSUS14 - GQM on energy for SaaS - CETIC
IWSM2014   MEGSUS14 - GQM on energy for SaaS - CETICIWSM2014   MEGSUS14 - GQM on energy for SaaS - CETIC
IWSM2014 MEGSUS14 - GQM on energy for SaaS - CETIC
 
ILAP (held at the 3rd Digital Oilfield Summit)
ILAP (held at the 3rd Digital Oilfield Summit)ILAP (held at the 3rd Digital Oilfield Summit)
ILAP (held at the 3rd Digital Oilfield Summit)
 
Faster, more Secure Application Modernization and Replatforming with PKS - Ku...
Faster, more Secure Application Modernization and Replatforming with PKS - Ku...Faster, more Secure Application Modernization and Replatforming with PKS - Ku...
Faster, more Secure Application Modernization and Replatforming with PKS - Ku...
 
ISC Cloud13 Sill - Crossing organizational boundaries in cloud computing
ISC Cloud13 Sill - Crossing organizational boundaries in cloud computingISC Cloud13 Sill - Crossing organizational boundaries in cloud computing
ISC Cloud13 Sill - Crossing organizational boundaries in cloud computing
 
Hlb private cloud rules of engagement idc
Hlb private cloud rules of engagement   idcHlb private cloud rules of engagement   idc
Hlb private cloud rules of engagement idc
 
OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]
OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]
OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]
 
OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]
OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]
OOW16 - Planning Your Upgrade to Oracle E-Business Suite 12.2 [CON1423]
 
CON6324_EBS_122_Beyond_Online_Patching_OOW2017_PUBLISHED.pdf
CON6324_EBS_122_Beyond_Online_Patching_OOW2017_PUBLISHED.pdfCON6324_EBS_122_Beyond_Online_Patching_OOW2017_PUBLISHED.pdf
CON6324_EBS_122_Beyond_Online_Patching_OOW2017_PUBLISHED.pdf
 
Application Engineered Routing: Allowing Applications to Program the Network
Application Engineered Routing: Allowing Applications to Program the NetworkApplication Engineered Routing: Allowing Applications to Program the Network
Application Engineered Routing: Allowing Applications to Program the Network
 
Resume Maumita Biswas
Resume Maumita BiswasResume Maumita Biswas
Resume Maumita Biswas
 
BrightTalk session-The right SDS for your OpenStack Cloud
BrightTalk session-The right SDS for your OpenStack CloudBrightTalk session-The right SDS for your OpenStack Cloud
BrightTalk session-The right SDS for your OpenStack Cloud
 
Building Business on Top of Open Source
Building Business on Top of Open SourceBuilding Business on Top of Open Source
Building Business on Top of Open Source
 
Mass Scale Networking
Mass Scale NetworkingMass Scale Networking
Mass Scale Networking
 
Carrier Grade OCP: Open Solutions for Telecom Data Centers
Carrier Grade OCP: Open Solutions for Telecom Data CentersCarrier Grade OCP: Open Solutions for Telecom Data Centers
Carrier Grade OCP: Open Solutions for Telecom Data Centers
 
Reducing Database Pain & Costs with Postgres
Reducing Database Pain & Costs with PostgresReducing Database Pain & Costs with Postgres
Reducing Database Pain & Costs with Postgres
 
Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...
Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...
Alternatives to Legacy Tech Solutions: The Case of Micro Focus Webinar Presen...
 
MPLS/SDN 2013 Intercloud Standardization and Testbeds - Sill
MPLS/SDN 2013 Intercloud Standardization and Testbeds - SillMPLS/SDN 2013 Intercloud Standardization and Testbeds - Sill
MPLS/SDN 2013 Intercloud Standardization and Testbeds - Sill
 

More from AVEVA Group plc

More from AVEVA Group plc (15)

Why AVEVA ProCon should be on your radar
Why AVEVA ProCon should be on your radarWhy AVEVA ProCon should be on your radar
Why AVEVA ProCon should be on your radar
 
AVEVA presents at the Rice Global Forum 2017
AVEVA presents at the Rice Global Forum 2017AVEVA presents at the Rice Global Forum 2017
AVEVA presents at the Rice Global Forum 2017
 
Maximizing efficiency using AVEVA & SDS/2 in the real world
Maximizing efficiency using AVEVA & SDS/2 in the real worldMaximizing efficiency using AVEVA & SDS/2 in the real world
Maximizing efficiency using AVEVA & SDS/2 in the real world
 
Managing contracts with AVEVA ProCon
Managing contracts with AVEVA ProCon Managing contracts with AVEVA ProCon
Managing contracts with AVEVA ProCon
 
The End of Handover by AVEVA & Fiatech
The End of Handover by AVEVA & FiatechThe End of Handover by AVEVA & Fiatech
The End of Handover by AVEVA & Fiatech
 
改扩建项目的革新
改扩建项目的革新改扩建项目的革新
改扩建项目的革新
 
The Data Centric Approach to Project Execution
The Data Centric Approach to Project ExecutionThe Data Centric Approach to Project Execution
The Data Centric Approach to Project Execution
 
Improving Integration and Automation of AVEVA Design Tools
Improving Integration and Automation of AVEVA Design ToolsImproving Integration and Automation of AVEVA Design Tools
Improving Integration and Automation of AVEVA Design Tools
 
AVEVA Integrated Engineering & Design Developments
AVEVA Integrated Engineering & Design DevelopmentsAVEVA Integrated Engineering & Design Developments
AVEVA Integrated Engineering & Design Developments
 
Transformation Time - AVEVA World UK User Meeting
Transformation Time - AVEVA World UK User MeetingTransformation Time - AVEVA World UK User Meeting
Transformation Time - AVEVA World UK User Meeting
 
AVEVA - Helping You Win and Deliver BIM Projects
AVEVA - Helping You Win and Deliver BIM ProjectsAVEVA - Helping You Win and Deliver BIM Projects
AVEVA - Helping You Win and Deliver BIM Projects
 
Digital Asset Management for Rail Networks
Digital Asset Management for Rail NetworksDigital Asset Management for Rail Networks
Digital Asset Management for Rail Networks
 
Effectively Managing Contracts
Effectively Managing ContractsEffectively Managing Contracts
Effectively Managing Contracts
 
AVEVA’s ERM, Efficient Planning and Management of Project Resources
AVEVA’s ERM, Efficient Planning and Management of Project Resources AVEVA’s ERM, Efficient Planning and Management of Project Resources
AVEVA’s ERM, Efficient Planning and Management of Project Resources
 
RT332: Measuring Progress and Productivity in Model-based Engineering
RT332: Measuring Progress and Productivity in Model-based EngineeringRT332: Measuring Progress and Productivity in Model-based Engineering
RT332: Measuring Progress and Productivity in Model-based Engineering
 

Recently uploaded

Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
Medical / Health Care (+971588192166) Mifepristone and Misoprostol tablets 200mg
 

Recently uploaded (20)

WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
WSO2Con2024 - Simplified Integration: Unveiling the Latest Features in WSO2 L...
 
WSO2CON 2024 - Architecting AI in the Enterprise: APIs and Applications
WSO2CON 2024 - Architecting AI in the Enterprise: APIs and ApplicationsWSO2CON 2024 - Architecting AI in the Enterprise: APIs and Applications
WSO2CON 2024 - Architecting AI in the Enterprise: APIs and Applications
 
WSO2CON 2024 - Does Open Source Still Matter?
WSO2CON 2024 - Does Open Source Still Matter?WSO2CON 2024 - Does Open Source Still Matter?
WSO2CON 2024 - Does Open Source Still Matter?
 
AzureNativeQumulo_HPC_Cloud_Native_Benchmarks.pdf
AzureNativeQumulo_HPC_Cloud_Native_Benchmarks.pdfAzureNativeQumulo_HPC_Cloud_Native_Benchmarks.pdf
AzureNativeQumulo_HPC_Cloud_Native_Benchmarks.pdf
 
WSO2CON 2024 - How to Run a Security Program
WSO2CON 2024 - How to Run a Security ProgramWSO2CON 2024 - How to Run a Security Program
WSO2CON 2024 - How to Run a Security Program
 
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
Abortion Pill Prices Tembisa [(+27832195400*)] 🏥 Women's Abortion Clinic in T...
 
WSO2CON 2024 - Not Just Microservices: Rightsize Your Services!
WSO2CON 2024 - Not Just Microservices: Rightsize Your Services!WSO2CON 2024 - Not Just Microservices: Rightsize Your Services!
WSO2CON 2024 - Not Just Microservices: Rightsize Your Services!
 
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
 
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
 
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
 
Announcing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK SoftwareAnnouncing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK Software
 
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
WSO2Con2024 - GitOps in Action: Navigating Application Deployment in the Plat...
 
%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in soweto%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in soweto
 
WSO2CON 2024 - Software Engineering for Digital Businesses
WSO2CON 2024 - Software Engineering for Digital BusinessesWSO2CON 2024 - Software Engineering for Digital Businesses
WSO2CON 2024 - Software Engineering for Digital Businesses
 
WSO2CON 2024 - Designing Event-Driven Enterprises: Stories of Transformation
WSO2CON 2024 - Designing Event-Driven Enterprises: Stories of TransformationWSO2CON 2024 - Designing Event-Driven Enterprises: Stories of Transformation
WSO2CON 2024 - Designing Event-Driven Enterprises: Stories of Transformation
 
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
WSO2Con2024 - Facilitating Broadband Switching Services for UK Telecoms Provi...
 
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
 
WSO2CON2024 - It's time to go Platformless
WSO2CON2024 - It's time to go PlatformlessWSO2CON2024 - It's time to go Platformless
WSO2CON2024 - It's time to go Platformless
 
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
 
WSO2Con2024 - Unleashing the Financial Potential of 13 Million People
WSO2Con2024 - Unleashing the Financial Potential of 13 Million PeopleWSO2Con2024 - Unleashing the Financial Potential of 13 Million People
WSO2Con2024 - Unleashing the Financial Potential of 13 Million People
 

Moving To New AVEVA Technology

  • 1.
  • 2. ©2016 KBR, Inc. All Rights Reserved 2 Moving To New AVEVA Technology Implementing AVEVA Engage and AVEVA E3D
  • 3. ©2016 KBR, Inc. All Rights Reserved 3 Presentation Agenda  About KBR  What KBR do  KBR and AVEVA collaborations  Recent example – AVEVA ENGAGE  Implementing AVEVA E3D at KBR  Important considerations  KBR Plan – Stages One, Two and Three  Summary  Questions
  • 4. ©2016 KBR, Inc. All Rights Reserved 4 About KBR  KBR is a global provider of differentiated professional services and technologies across the asset and program life cycle within the Hydrocarbons and Government Services Sectors. KBR employs over 31,000 people worldwide, with customers in more than 80 countries, and operations in 40 countries, across three synergistic global businesses:  Government Services, serving government customers globally, including capabilities that cover the full life-cycle of defence, space, aviation and other government programs and missions from research and development, through systems engineering, test and evaluation, program management, to operations, maintenance, and field logistics  Technology & Consulting, including proprietary technology focused on the monetization of hydrocarbons (especially natural gas and natural gas liquids) in ethylene and petrochemicals; ammonia, nitric acid and fertilizers; oil refining; gasification; oil and gas consulting; integrity management; naval architecture and proprietary hulls; and downstream consulting  Engineering & Construction, including onshore oil and gas; LNG (liquefaction and regasification)/GTL; oil refining; petrochemicals; chemicals; fertilizers; differentiated EPC; maintenance services (Brown & Root Industrial Services); offshore oil and gas; fixed solutions (shallow-water, deep-water, subsea); floating solutions (FPU, FPSO, FLNG & FSRU); and program management  KBR is proud to work with its customers across the globe to provide technology, value-added services, integrated EPC delivery and long term operations and maintenance services to ensure consistent delivery with predictable results.
  • 5. ©2016 KBR, Inc. All Rights Reserved 5 Offshore Oil and Gas – Fixed Solutions Shallow Water, Deep Water and Subsea Offshore Oil and Gas – Floating Solutions FPU, FPSO, FLNG and FSRU What KBR do
  • 6. ©2016 KBR, Inc. All Rights Reserved 6 Onshore - Oil and Gas, LNG/GTL, Oil Refining, Petrochemicals, Chemicals, Fertilizers What KBR do
  • 7. ©2016 KBR, Inc. All Rights Reserved 7 Onshore/Offshore Mega Projects What KBR do
  • 8. ©2016 KBR, Inc. All Rights Reserved 8 KBR and AVEVA collaborations  Users of PDMS for 40 years, recent average of 650 users globally (peaked at 1250 users)  SPOOLING/SPOOLER – need arose from alliance type profit share projects  GLOBAL– early recognition of multi location mega projects  CLASH MANAGER (Model Management Suite) – inclusion of key KBR functionality and work flows into AVEVA products  Application Installs – creation of silent installs and standardisation across all application installs  E3D SUPPORTS – following feedback from large work share project usage i.e. too many clicks, reliance on ATTA placement in PIPE’s  Other developments such as Data Access Control, Status Control, Distributed Attributes…  Attendance of AVEVA ERG’s (External Reference Groups)
  • 9. ©2016 KBR, Inc. All Rights Reserved 9  Request: a live current KBR project in AVEVA ENGAGE  4 week window from request to required by date  PDMS 12.1 project, not running E3D and not running AVEVA Net  Involved the import of : – 80,606 Engineering Tags (exported from Data Warehouse) – 224,925 Document to Tag References (exported from Data Warehouse) – 8,316 Isometrics (exported from Documentum) – 2,539 Engineering Documents (exported from Documentum) – 5,781 Supplier Documents (exported from Documentum) – Plus the entire 3D topsides and jacket model (database size 6.56 GB)  All achieved in 3 weeks which included the generation of a video Recent example – AVEVA ENGAGE
  • 10. ©2016 KBR, Inc. All Rights Reserved 10  KBR’s experience was almost “Plug and Play”  Understand the hardware requirements  Bring in the experts to expedite initial setup (AVEVA Net)  A well defined information and data model greatly helps  Easy to expand, start simple and add capability/value  Visual Query – simple and easy to use value add tool  Can be introduced at any stage of a project  No user training required AVEVA Engage key points summary
  • 11. ©2016 KBR, Inc. All Rights Reserved 11 Implementing E3D at KBR  Use AVEVA for knowledge gathering workshops  Prioritise requirements (identify quick or easy wins to help justify business case)  Define the scope (very important)  Create a detailed plan (dates, resources, dependencies)  Use AVEVA services if you need to accelerate schedule or require particular new technology skills/expertise  Make no assumptions, expect the unexpected  Do not rush in unplanned, this is a major change
  • 12. ©2016 KBR, Inc. All Rights Reserved 12 Important considerations  Hardware (Workstations - graphics cards, RAM, monitors, OS / Servers - disk space, RAM, OS / New - touch and mobile devices )  PDMS only, E3D only or mixed PDMS/E3D projects  PDMS and E3D very different environments and have many inter-dependencies – Environmental variable changes, new data and folder structures – MDS (SECTIONS/MDS/MDU) vs SUPPORTS (GENSECS/ACP/APS) – STEELWORK/STRUCTURES (Changes SECTIONS/GENSECS, new catalogues, new GUI’s) – PDMSDFLTS/AVEVA_DESIGN_DFLTS, PDMSUI/PMLUI and PMLIB/E3DLIB – Project changes MAS/ACP and SAM/APS – DRAFT/DRAW library decisions – Company specific catalogues and customised PML applications
  • 13. ©2016 KBR, Inc. All Rights Reserved 13 Important considerations (continued)  E3D transition is not just about one application, it’s about many, but how many (defining the scope)? – E3D (MODEL, DRAW, ISODRAFT, SPOOL) – ADMINISTRATION (ADMIN, LEXICON replacing PDMS ADMIN and LEXICON) – CATALOGUE (PARAGON, PROPCON replacing PDMS PARAGON and PROPCON) – Cache Service – Application Service – E3D INSIGHT – ENGAGE (and AVEVA Net?) – GCD Creator  Upgrade Training
  • 14. ©2016 KBR, Inc. All Rights Reserved 14 KBR Plan - Stage One (Complete)  Mixed PDMS and E3D project environment  Skip E3D 1.1 minimal benefit but E3D 2.1 adds immediate value  Start with introduction of E3D 2.1 “out of the box” – Create KBR silent installs and mixed heterogeneous environment  Take advantage of new functionality: – Improved working with laser data (BubbleView and HyperBubble) – Make available the easier to use DRAW – Use the database cache service to improve performance  Provides quick and early access to E3D, INSIGHT and ENGAGE
  • 15. ©2016 KBR, Inc. All Rights Reserved 15 KBR Plan - Stage One (Complete)
  • 16. ©2016 KBR, Inc. All Rights Reserved 16 KBR Plan - Stage Two (In Progress)  Use AVEVA services for preparing key dependencies: – MDS support catalogue conversion (KBR support standards) – Structural steelwork catalogue (KBR offshore joints and fittings standards) – Structural fittings catalogue (KBR penetration standards)  Use new functionality included in E3D to replace legacy KBR and AVEVA applications: – Hole Management (replace KBR Penetrations) – Status Control/Data Grid (replace VPE and Model Object Manager) – Draw/Data Grid or Engineering (replace Deliverable Manager)  Once stage two is completed: – Enable new E3D SUPPORTS (replace KBR MDS) and E3D STRUCTURES to be used – Replacement of the legacy Model Management Suite  
  • 17. ©2016 KBR, Inc. All Rights Reserved 17 KBR Plan - Stage Three (Future)  Test, certify and release all remaining KBR value add customisations and add-on applications written in PML for use with E3D  This statement doesn’t sound like much does it but…  This process is expedited by having established test plans and test reports for each of these minor applications  Once stage three is completed, option to switch to using E3D only  Last but not least update KBR SRO Documentation
  • 18. ©2016 KBR, Inc. All Rights Reserved 18
  • 19. ©2016 KBR, Inc. All Rights Reserved 19 KBR Plan - Stage Three (Future)  This process is expedited by having established test plans and test reports for each of these minor applications  Once stage three is completed, option to switch to using E3D only  Last but not least update KBR SRO Documentation
  • 20. ©2016 KBR, Inc. All Rights Reserved 20  Knowledge gather thoroughly first  Define scope  Make a detailed plan  Consider bringing in the experts to expedite  Allow for contingencies  Use established test plans and reports for add-on apps  Don’t forget about the training and documentation AVEVA E3D key points summary
  • 21. ©2016 KBR, Inc. All Rights Reserved 21 avevaworld.com @aveva /aveva