SlideShare a Scribd company logo
1 of 21
WELDING IN WORKBENCH
Bruce Russell
1
HISTORY
 In 1941 Orange Fowler Merwin sold
equipment to grain Millers
 Common complaints of stray metal in the
grain
 Devised a non-electric magnetic
separator in 1942
 Worked well enough, it developed into
product used today for the food industry
 130,000ft2 facility serves as
Headquarters in Erie, Pennsylvania
 Has sales offices all across the United
States and over 80 international markets
2
Product: How it works
3
Metal detector housing
4
• Stainless steel
• Welded together
• Hollow walls aside from coil
• Rigid metal structure
• Hollow cavity filled with
foam and marbles
• Weighs 2400lbs
Problem
• Fill material cures, and
shrinks during the
curing process
• When end plate is
welded on, heat causes
foam to separate from
housing
• Rigid Metal zone is
compromised –
deflection of housing
registers as a false
metal detection.
5
Problem – HOUSING
6
• Initial weld on outer housing
• Causes thermal expansion of housing and foam
Housing Temperature
7
Problem – FOAM
8
• Heat transfer from welding arc is disbursed into the housing, and
then into the foam
• Properties of foam are compromised due to heat of weld
Foam Temperature
9
Problem – PRESSURE FROM WELD
10
• Weld increases negative pressure inside of housing
• Negative pressure increases likelihood of foam separating from
housing
Workbench Weld Command
D=.5 ! Desired length of weld
SP=-3.5 ! Start point of weld in axis
LL=6 ! Total length of weld
TTI=1 ! Time spent on current weld area
XYZ=Y ! Chose Plane that weld is in either X,Y or Z LEAVE QUOTES
Weld_1=Weld_A ! Enter Named Selection of Elements for Weld LEAVE QUOTES
! DO NOT ENTER OR CHANGE ANY DATA BELOW
CMSEL,S,Weld_1
eplot
EKILL,ALL
allsel
BFUNIF,TEMP,71.6 ! uniform initial TEMP
BFUNIF,HGEN,0 ! uniform intial heat generation
/PBF,HGEN,1
eplot
/USER
TIMINT,OFF ! 1st solve is steady-state to establish initial conditions
Time,0.001 ! for short duration (1 millisecond)
NSUBST,2 ! 02/26/2106 - use 2 substeps
solve
11
Ansys Result - Current Fill Process
12
• Simplified – all foam/marbles are in place initially (no weld
considered)
• Shows foam wants to pull away at the top of the housing
Contact Pressure, negative shows separation likely
Current Solution
13
• Attach grease fitting
• Drill two pressure relief holes
• Pump full of epoxy until epoxy leaves pressure relief holes
Downsides
• New grease gun each housing – epoxy ruins grease gun
• Significant post processing – extra expenses
Goal: Eliminate possibility of foam
retracting from metal housing
How?
 Non-metal bracing inside housing (trusses/splints/ribs)
 Change the filling process of the housing
 Cool the marbles before filling process
 Heat the housing before/during the filling process
 Weld end plate with hole in it after 1st shot, instead of
at the end of the shot process
14
Non-metal bracing inside
housing (trusses/splints/ribs)
 Adds rigidity to the housing
 Larger surface area for foam to adhere
to
 Has to be non-metallic
 Bracing will be slightly press fit into
housing
 Foam will hold bracing into place
 Investigate welding process
15
Change the filling process of the housing
Current Process:
 Foam shots typically 15 seconds in duration
 Post foam shots executed randomly
 Random amount of marbles used per shot
Concept Process:
 Foam shots done one after another in strict equal intervals
 Foam shots done before previous shot is cured
 Equal amounts of marbles per shot
16
Cool the marbles before filling process
 Will lower the chemical reaction temperature of the foam
 Without marbles, reaction temperature reaches 250 degrees
Fahrenheit
 With marbles, reaction temperature reaches 150 degrees
17
Why wont cooling the marbles work?
• Proper cure temperature of foam is 78⁰F ambient temperature
• Expands housing larger than desired dimensions
• Once cooled, will conform to cured foam, creating
compression in the foam
• Slow the cure process of the foam
• Foam and Housing will shrink uniformly
Heat the housing before the filling process
18
• Heat distribution of weld will be done
before foam is affected
• Perform shots through small hole in
the end plate
• Heat of weld to cap the hole will be
significantly less than entire end
plate
Weld end plate on after 1st shot,
instead of at the end of the shot
process
19
Weld Analysis on end hole
20
QUESTIONS?
21

More Related Content

What's hot

Manufacturing and testing of Insulators at BHEL Jagdishpur
Manufacturing and testing of Insulators at BHEL JagdishpurManufacturing and testing of Insulators at BHEL Jagdishpur
Manufacturing and testing of Insulators at BHEL JagdishpurAnushreya Gupta
 
Moisture Management - Step 6 of The Seven Steps of Building a Synergy Home
Moisture Management - Step 6 of The Seven Steps of Building a Synergy HomeMoisture Management - Step 6 of The Seven Steps of Building a Synergy Home
Moisture Management - Step 6 of The Seven Steps of Building a Synergy HomeSynergy Airflow and Ventilation
 
Step 5 Pressure Balancing of The Seven Steps of Building a Synergy Home
Step 5 Pressure Balancing of The Seven Steps of Building a Synergy HomeStep 5 Pressure Balancing of The Seven Steps of Building a Synergy Home
Step 5 Pressure Balancing of The Seven Steps of Building a Synergy HomeSynergy Airflow and Ventilation
 
Product Catalog
Product CatalogProduct Catalog
Product CatalogJack Lee
 
Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plantPrashant Kumar
 
Fresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy Home
Fresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy HomeFresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy Home
Fresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy HomeSynergy Airflow and Ventilation
 
Step 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy Home
Step 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy HomeStep 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy Home
Step 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy HomeSynergy Airflow and Ventilation
 
Industrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution ControlIndustrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution ControlJohn Kleinfelter
 
Steel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSteel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSuman Sourabh
 
Training at sail bokaro
Training at sail bokaroTraining at sail bokaro
Training at sail bokaroGAURAV VERMA
 
PSC Flammable Storage Safety Cabinets
PSC Flammable Storage Safety CabinetsPSC Flammable Storage Safety Cabinets
PSC Flammable Storage Safety CabinetsProject Sales Corp
 
CIB-PVF Line Card Rev 111
CIB-PVF Line Card Rev 111CIB-PVF Line Card Rev 111
CIB-PVF Line Card Rev 111jeyramyadielis
 
Sinter Plant (Vizag Steel Plant)
Sinter Plant (Vizag Steel Plant)Sinter Plant (Vizag Steel Plant)
Sinter Plant (Vizag Steel Plant)Vishal Bhaskar
 
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy HomeAirtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy HomeTodd Witt
 
500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANT500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANTGuo ke
 

What's hot (20)

Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plant
 
Sintering plant
Sintering plantSintering plant
Sintering plant
 
Manufacturing and testing of Insulators at BHEL Jagdishpur
Manufacturing and testing of Insulators at BHEL JagdishpurManufacturing and testing of Insulators at BHEL Jagdishpur
Manufacturing and testing of Insulators at BHEL Jagdishpur
 
Moisture Management - Step 6 of The Seven Steps of Building a Synergy Home
Moisture Management - Step 6 of The Seven Steps of Building a Synergy HomeMoisture Management - Step 6 of The Seven Steps of Building a Synergy Home
Moisture Management - Step 6 of The Seven Steps of Building a Synergy Home
 
Step 5 Pressure Balancing of The Seven Steps of Building a Synergy Home
Step 5 Pressure Balancing of The Seven Steps of Building a Synergy HomeStep 5 Pressure Balancing of The Seven Steps of Building a Synergy Home
Step 5 Pressure Balancing of The Seven Steps of Building a Synergy Home
 
Product Catalog
Product CatalogProduct Catalog
Product Catalog
 
Ppt on bokaro steel plant
Ppt on bokaro steel plantPpt on bokaro steel plant
Ppt on bokaro steel plant
 
Fresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy Home
Fresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy HomeFresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy Home
Fresh Air Ventilation -Step 2 of The Seven Steps of Building a Synergy Home
 
Step 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy Home
Step 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy HomeStep 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy Home
Step 3 - Improved Thermal Systems of the Seven Steps of Building a Synergy Home
 
Industrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution ControlIndustrial Ventilation and Air Pollution Control
Industrial Ventilation and Air Pollution Control
 
sail bokaro
sail bokarosail bokaro
sail bokaro
 
Steel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaroSteel Authority of India Ltd bokaro
Steel Authority of India Ltd bokaro
 
Training at sail bokaro
Training at sail bokaroTraining at sail bokaro
Training at sail bokaro
 
PSC Flammable Storage Safety Cabinets
PSC Flammable Storage Safety CabinetsPSC Flammable Storage Safety Cabinets
PSC Flammable Storage Safety Cabinets
 
CIB-PVF Line Card Rev 111
CIB-PVF Line Card Rev 111CIB-PVF Line Card Rev 111
CIB-PVF Line Card Rev 111
 
Sinter Plant (Vizag Steel Plant)
Sinter Plant (Vizag Steel Plant)Sinter Plant (Vizag Steel Plant)
Sinter Plant (Vizag Steel Plant)
 
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy HomeAirtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
 
500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANT500 TPD Mn ORE SINTER PLANT
500 TPD Mn ORE SINTER PLANT
 
Cosworth process
Cosworth processCosworth process
Cosworth process
 
Casting & Forming through Hot Isostatic Press [HIP]
Casting & Forming through Hot Isostatic Press [HIP]Casting & Forming through Hot Isostatic Press [HIP]
Casting & Forming through Hot Isostatic Press [HIP]
 

Similar to ANSYS Presentation

Heat Treatment Defects and their Remedies
Heat Treatment Defects and their RemediesHeat Treatment Defects and their Remedies
Heat Treatment Defects and their RemediesMiraj Patel
 
SpohnHome presentation @ 2021 HVACR Symposium
SpohnHome presentation @ 2021 HVACR SymposiumSpohnHome presentation @ 2021 HVACR Symposium
SpohnHome presentation @ 2021 HVACR SymposiumBill Spohn
 
Sarvesh energy audit_final_presentation
Sarvesh energy audit_final_presentationSarvesh energy audit_final_presentation
Sarvesh energy audit_final_presentationSarvesh Dandekar
 
Recognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresRecognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresFluxtrol Inc.
 
Post-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.pptPost-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.pptvipinverma125286
 
Machines and furnaces used in foundry
Machines and furnaces used in foundryMachines and furnaces used in foundry
Machines and furnaces used in foundryMuhammadFarooq466
 
Ref failur e analysis tip casting & retainer area f
Ref failur e analysis tip casting & retainer area  fRef failur e analysis tip casting & retainer area  f
Ref failur e analysis tip casting & retainer area fpradeepdeepi
 
Everything about Forging
Everything about ForgingEverything about Forging
Everything about ForgingRamtarun AVN
 
EM-Unit-IV- case hardening
EM-Unit-IV- case hardeningEM-Unit-IV- case hardening
EM-Unit-IV- case hardeningMohanumar S
 
Project 8 Summary
Project 8 SummaryProject 8 Summary
Project 8 SummaryCallum Lamb
 
Acrolab Thermal Management System - Case study thermoset injection molding
Acrolab Thermal Management System - Case study thermoset injection moldingAcrolab Thermal Management System - Case study thermoset injection molding
Acrolab Thermal Management System - Case study thermoset injection moldingAcrolab Ltd.
 
Special casting process (1.5)
Special casting process (1.5)Special casting process (1.5)
Special casting process (1.5)Pravinkumar
 
Selective Hardening process
Selective Hardening processSelective Hardening process
Selective Hardening processAbin Basil
 

Similar to ANSYS Presentation (20)

Heat Treatment Defects and their Remedies
Heat Treatment Defects and their RemediesHeat Treatment Defects and their Remedies
Heat Treatment Defects and their Remedies
 
SpohnHome presentation @ 2021 HVACR Symposium
SpohnHome presentation @ 2021 HVACR SymposiumSpohnHome presentation @ 2021 HVACR Symposium
SpohnHome presentation @ 2021 HVACR Symposium
 
case hardening
case hardeningcase hardening
case hardening
 
Heat pipes
Heat pipesHeat pipes
Heat pipes
 
Sarvesh energy audit_final_presentation
Sarvesh energy audit_final_presentationSarvesh energy audit_final_presentation
Sarvesh energy audit_final_presentation
 
Recognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresRecognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator Failures
 
Post-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.pptPost-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.ppt
 
Machines and furnaces used in foundry
Machines and furnaces used in foundryMachines and furnaces used in foundry
Machines and furnaces used in foundry
 
Ref failur e analysis tip casting & retainer area f
Ref failur e analysis tip casting & retainer area  fRef failur e analysis tip casting & retainer area  f
Ref failur e analysis tip casting & retainer area f
 
Everything about Forging
Everything about ForgingEverything about Forging
Everything about Forging
 
Case hardening
Case hardeningCase hardening
Case hardening
 
2 case hardening
2 case hardening2 case hardening
2 case hardening
 
EM-Unit-IV- case hardening
EM-Unit-IV- case hardeningEM-Unit-IV- case hardening
EM-Unit-IV- case hardening
 
Case Hardening
Case HardeningCase Hardening
Case Hardening
 
Case hardening
Case hardeningCase hardening
Case hardening
 
Project 8 Summary
Project 8 SummaryProject 8 Summary
Project 8 Summary
 
2 case hardening
2 case hardening2 case hardening
2 case hardening
 
Acrolab Thermal Management System - Case study thermoset injection molding
Acrolab Thermal Management System - Case study thermoset injection moldingAcrolab Thermal Management System - Case study thermoset injection molding
Acrolab Thermal Management System - Case study thermoset injection molding
 
Special casting process (1.5)
Special casting process (1.5)Special casting process (1.5)
Special casting process (1.5)
 
Selective Hardening process
Selective Hardening processSelective Hardening process
Selective Hardening process
 

ANSYS Presentation

  • 2. HISTORY  In 1941 Orange Fowler Merwin sold equipment to grain Millers  Common complaints of stray metal in the grain  Devised a non-electric magnetic separator in 1942  Worked well enough, it developed into product used today for the food industry  130,000ft2 facility serves as Headquarters in Erie, Pennsylvania  Has sales offices all across the United States and over 80 international markets 2
  • 3. Product: How it works 3
  • 4. Metal detector housing 4 • Stainless steel • Welded together • Hollow walls aside from coil • Rigid metal structure • Hollow cavity filled with foam and marbles • Weighs 2400lbs
  • 5. Problem • Fill material cures, and shrinks during the curing process • When end plate is welded on, heat causes foam to separate from housing • Rigid Metal zone is compromised – deflection of housing registers as a false metal detection. 5
  • 6. Problem – HOUSING 6 • Initial weld on outer housing • Causes thermal expansion of housing and foam
  • 8. Problem – FOAM 8 • Heat transfer from welding arc is disbursed into the housing, and then into the foam • Properties of foam are compromised due to heat of weld
  • 10. Problem – PRESSURE FROM WELD 10 • Weld increases negative pressure inside of housing • Negative pressure increases likelihood of foam separating from housing
  • 11. Workbench Weld Command D=.5 ! Desired length of weld SP=-3.5 ! Start point of weld in axis LL=6 ! Total length of weld TTI=1 ! Time spent on current weld area XYZ=Y ! Chose Plane that weld is in either X,Y or Z LEAVE QUOTES Weld_1=Weld_A ! Enter Named Selection of Elements for Weld LEAVE QUOTES ! DO NOT ENTER OR CHANGE ANY DATA BELOW CMSEL,S,Weld_1 eplot EKILL,ALL allsel BFUNIF,TEMP,71.6 ! uniform initial TEMP BFUNIF,HGEN,0 ! uniform intial heat generation /PBF,HGEN,1 eplot /USER TIMINT,OFF ! 1st solve is steady-state to establish initial conditions Time,0.001 ! for short duration (1 millisecond) NSUBST,2 ! 02/26/2106 - use 2 substeps solve 11
  • 12. Ansys Result - Current Fill Process 12 • Simplified – all foam/marbles are in place initially (no weld considered) • Shows foam wants to pull away at the top of the housing Contact Pressure, negative shows separation likely
  • 13. Current Solution 13 • Attach grease fitting • Drill two pressure relief holes • Pump full of epoxy until epoxy leaves pressure relief holes Downsides • New grease gun each housing – epoxy ruins grease gun • Significant post processing – extra expenses
  • 14. Goal: Eliminate possibility of foam retracting from metal housing How?  Non-metal bracing inside housing (trusses/splints/ribs)  Change the filling process of the housing  Cool the marbles before filling process  Heat the housing before/during the filling process  Weld end plate with hole in it after 1st shot, instead of at the end of the shot process 14
  • 15. Non-metal bracing inside housing (trusses/splints/ribs)  Adds rigidity to the housing  Larger surface area for foam to adhere to  Has to be non-metallic  Bracing will be slightly press fit into housing  Foam will hold bracing into place  Investigate welding process 15
  • 16. Change the filling process of the housing Current Process:  Foam shots typically 15 seconds in duration  Post foam shots executed randomly  Random amount of marbles used per shot Concept Process:  Foam shots done one after another in strict equal intervals  Foam shots done before previous shot is cured  Equal amounts of marbles per shot 16
  • 17. Cool the marbles before filling process  Will lower the chemical reaction temperature of the foam  Without marbles, reaction temperature reaches 250 degrees Fahrenheit  With marbles, reaction temperature reaches 150 degrees 17 Why wont cooling the marbles work? • Proper cure temperature of foam is 78⁰F ambient temperature
  • 18. • Expands housing larger than desired dimensions • Once cooled, will conform to cured foam, creating compression in the foam • Slow the cure process of the foam • Foam and Housing will shrink uniformly Heat the housing before the filling process 18
  • 19. • Heat distribution of weld will be done before foam is affected • Perform shots through small hole in the end plate • Heat of weld to cap the hole will be significantly less than entire end plate Weld end plate on after 1st shot, instead of at the end of the shot process 19
  • 20. Weld Analysis on end hole 20

Editor's Notes

  1. Stray metal such as bits of wire, nails, bolts, and even horseshoes
  2. Product on conveyor moves through housing Food and drinks Housing holds electronic components to detect any type of metal Coil around chamber generates an electromagnetic field Metal passing through electromagnetic field registers on the display screen
  3. Rigid metal structure is required because if metal moves within the electromagnetic field, it effects the field and generates an alarm.
  4. Reaction of 250 degrees with out marbles Reaction of 150 degrees with marbles Cross hatching is exaggerated display of the retraction
  5. Reaction of 250 degrees with out marbles Reaction of 150 degrees with marbles Cross hatching is exaggerated display of the retraction
  6. Reaction of 250 degrees with out marbles Reaction of 150 degrees with marbles Cross hatching is exaggerated display of the retraction
  7. Reaction of 250 degrees with out marbles Reaction of 150 degrees with marbles Cross hatching is exaggerated display of the retraction
  8. Shows the shrinkage of the foam with and without marbles
  9. Fill process: 250degrees and its 150degrees when using marbles Have tried gravel, sand
  10. 15 second shot only fills portion of housing Secondary/after shots wait 45minutes. Sometimes takes longer just bc the employee is busy or on lunch Try to make marble to foam 50/50 mixture