The second prototype of the project includes adjustments to level the base using an adjuster attached to the bottom, fixes to a bad weld, improved quality and strength over the last prototype, increased weight to 20kg with the completed structure, easier and safer use with a flat, strong surface, manufacturing time of 11 hours this week and 19 hours total, the same manufacturing cost as last week, and dimensions and functions matching the CAD model as only one prototype was made.