Embed presentation
Download to read offline














































The document summarizes the renewal of a high-performance water distribution system in Squaw Valley, California over three days in June 2006. Contractors replaced 150 feet of aging cast iron water main with new high-density polyethylene pipe using trenchless pipe bursting techniques. This involved excavating entry and exit pits, attaching a bursting head to the new pipe to pull it through the old line, and fusing new connections at entry/exit points. The project addressed leaks in the existing system and helped ensure continued reliable water service.