- 1. RELEASEPLANNING voor SWO 18-8-2011
Customs Flow MIG Publication Publication Testsystem Implementation Release note Comments
Version MIG-Draft MIG-Definitif Availabl date
Douanemanifest
AIS/ICS 12 28-12-10 01-05-2011 25-09-2011* 10/A/IM/Douane/ Postponed, was 19 June 2011
EDI/ICS2312
AES/ECS 12 21-12-10 01-05-2011 25-09-2011* 10/A/IM/Douane/ Postponed, was 19 June 2011
EDI/ECS/2312
Transit
Aangiftesystemen (nieuw)
AGS1 Storage 1.00 01-06-2010 08-07-2010 01-11-2011* 18-12-2011* Increment 1 Postponed was 25 Sept. 11
AGS2 Import Q4 Q1 Increment 2 Replacement Sagitta Import
2011(dec)* 2013 (feb)* Postponed was Q2-2012
AGS3 Export Q4 Increment 3 Replacement Sagitta Export
2013 (dec)*
AGS4 Other 2014* Increment 4
Excise
EMCS 2.10 01-06-2011 07-11-2011* 01-01-2012* Phase FS2
* expected / provisional
Dutch Customs 18-08-2011 Page 1
Software Developers Support Team