REPAIR REPORT
EX401
WELDING REBUILD: Bucket; Boom; Cascade Room;
superstructure; Engine Module;
Date of Rebuild: Feb-March 2016
NDT Technique: Magnetic Particle Test
Weld Rebuild report: Ray Krueger
20th
Sept 2015
2 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
REPAIR COMPLETED FOR FRONT CLAM EX401—340FW2
ChromiumCarbide plates
fittedtoBoth walls in and
outside and alsothe floor.
Buildupadaptor
stationstofit
template
3 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
Cut out worn section of side wall on both sides
and replace with new plate 25mm, weldox 400
or A514 plate.
Refer to Ray for exact position of cut.
REPLACEMENT REAR SIDE WALL SECTIONS FITTED
AND WELDED TO PROCEDURE.
4 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
All barsremovedandreplaced
withchromiumCarbide after
all cracks repaired
Replace complete impactbar
across back of Jaw
Cracks repaired,
new chromium
carbide fittedand
new impactblock
New ChromiumCarbide
floor
New cornerblocks,new wear
package on outside walls
5 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
COMPLETED FRONT CLAM
BACK WALL OF BUCKET REPAIRS
WEAR PACKAGE FITTED, CRACKS REPAIRED
6 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
COMPLETED BUCKET
EX401 BOOM REPAIR:
Major cracks continually developing from the man hole.
Complete removal of
stressed section and
fully weld in position.
7 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
Fullyweldedand back gouged from inside and
fullyweldedbothsides.Full pre heat and quality
weldswith stressrelievingpeening.
FINISHED REPAIR TO
MANHOLE AND FULL
REPAIRS TO ALL PADS.
8 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
POOR QUALITY WELDING ON BLOCKS ON
BOOM, THAT HAVE LED TO CRACKS.
COMPLETE REPAIR OF CRACKS AND
REWELDING OF PADS TO CORRECT
STANDARD FOLLOWING ALL WELD
PROCEDURES.
BOOM CONTINUED
9 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
Superstructure repairs
10 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
COMPLETE FULLY GOUGE AND REWELD
CASCADE ROOM REPAIRS:
MULTIPLE CRACKS IN WALLS
AND AROUND MOUNTING
BLOCKS.
11 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
GOUGING ANDWELDING ALL CRACKS AND BACK GOUGEDAND WELDED FROM
INSIDE WHERE POSSIBLE.
FULLY WELDED AND BLENDED
12 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
EX401 ENGINE MODULE
ALL CRACKED SECTIONS REMOVED AND REPAIRED.
13 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y
REPAIR REPORT
NDT Technician - Comments
1.
2.
3.
4.
5.
Welding Supervisor - Comments
1.
2.
3.
4.
5.
Condition Monitoring & Reliability - Comments
1.
2.
3.
4.
5.

More Related Content

What's hot

Plano y modelado grifería Mónica Cadena
Plano y modelado grifería  Mónica CadenaPlano y modelado grifería  Mónica Cadena
Plano y modelado grifería Mónica CadenaMónica Cadena
 
Sequence erection segment 2 r and 2l layout2
Sequence erection segment 2 r and 2l layout2Sequence erection segment 2 r and 2l layout2
Sequence erection segment 2 r and 2l layout2ahaniif
 
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 UAnchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 UCS Unitec
 
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 VAnchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 VCS Unitec
 
Activity on Arrow Diagram
Activity on Arrow DiagramActivity on Arrow Diagram
Activity on Arrow DiagramWaleed Liaqat
 

What's hot (8)

Plano y modelado grifería Mónica Cadena
Plano y modelado grifería  Mónica CadenaPlano y modelado grifería  Mónica Cadena
Plano y modelado grifería Mónica Cadena
 
EX7-72-2
EX7-72-2EX7-72-2
EX7-72-2
 
Sequence erection segment 2 r and 2l layout2
Sequence erection segment 2 r and 2l layout2Sequence erection segment 2 r and 2l layout2
Sequence erection segment 2 r and 2l layout2
 
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 UAnchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 U
 
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 VAnchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 V
 
560 000-st-i-027
560 000-st-i-027560 000-st-i-027
560 000-st-i-027
 
Activity on Arrow Diagram
Activity on Arrow DiagramActivity on Arrow Diagram
Activity on Arrow Diagram
 
1CO3
1CO3 1CO3
1CO3
 

Viewers also liked

Bicentario festividades de diferentes provincias
Bicentario festividades de diferentes provinciasBicentario festividades de diferentes provincias
Bicentario festividades de diferentes provinciasFranco Malmesi
 
Синтаксис сложного предложения в современном русском языке
Синтаксис сложного предложения в современном русском языкеСинтаксис сложного предложения в современном русском языке
Синтаксис сложного предложения в современном русском языкеozlmgouru
 
Introduction to culture 2016 2017
Introduction to culture 2016 2017Introduction to culture 2016 2017
Introduction to culture 2016 2017Megan Gabbert
 
家鄉的節慶與民俗活動
家鄉的節慶與民俗活動家鄉的節慶與民俗活動
家鄉的節慶與民俗活動awcc
 
10 Mandamentos - Aula 07 - 6º mandamento
10 Mandamentos - Aula 07 - 6º mandamento10 Mandamentos - Aula 07 - 6º mandamento
10 Mandamentos - Aula 07 - 6º mandamentoElder Moraes
 
觀測月亮
觀測月亮觀測月亮
觀測月亮awcc
 
DDoS Mitigation on the Front Line with RedShield
DDoS Mitigation on the Front Line with RedShieldDDoS Mitigation on the Front Line with RedShield
DDoS Mitigation on the Front Line with RedShieldSam Pickles
 
Front page of Nishat mills LTD
Front page of Nishat mills LTDFront page of Nishat mills LTD
Front page of Nishat mills LTDMehmood Ul Hassan
 

Viewers also liked (11)

Bicentario festividades de diferentes provincias
Bicentario festividades de diferentes provinciasBicentario festividades de diferentes provincias
Bicentario festividades de diferentes provincias
 
Синтаксис сложного предложения в современном русском языке
Синтаксис сложного предложения в современном русском языкеСинтаксис сложного предложения в современном русском языке
Синтаксис сложного предложения в современном русском языке
 
Introduction to culture 2016 2017
Introduction to culture 2016 2017Introduction to culture 2016 2017
Introduction to culture 2016 2017
 
家鄉的節慶與民俗活動
家鄉的節慶與民俗活動家鄉的節慶與民俗活動
家鄉的節慶與民俗活動
 
10 Mandamentos - Aula 07 - 6º mandamento
10 Mandamentos - Aula 07 - 6º mandamento10 Mandamentos - Aula 07 - 6º mandamento
10 Mandamentos - Aula 07 - 6º mandamento
 
觀測月亮
觀測月亮觀測月亮
觀測月亮
 
DDoS Mitigation on the Front Line with RedShield
DDoS Mitigation on the Front Line with RedShieldDDoS Mitigation on the Front Line with RedShield
DDoS Mitigation on the Front Line with RedShield
 
Front page of Nishat mills LTD
Front page of Nishat mills LTDFront page of Nishat mills LTD
Front page of Nishat mills LTD
 
Sports Codes 2012 Brand In Trend
 Sports Codes 2012 Brand In Trend Sports Codes 2012 Brand In Trend
Sports Codes 2012 Brand In Trend
 
Suresh Profile
Suresh ProfileSuresh Profile
Suresh Profile
 
CV_Satish_Gupta_2016
CV_Satish_Gupta_2016CV_Satish_Gupta_2016
CV_Satish_Gupta_2016
 

Similar to 160316 EX401 rebuild welding report

160709 EX403 UNDERCARRIAGE REPAIRING REPORT
160709 EX403 UNDERCARRIAGE REPAIRING REPORT160709 EX403 UNDERCARRIAGE REPAIRING REPORT
160709 EX403 UNDERCARRIAGE REPAIRING REPORTSospeter Lugembe
 
FLUID FILM BEARING DETECTION.pdf
FLUID FILM BEARING DETECTION.pdfFLUID FILM BEARING DETECTION.pdf
FLUID FILM BEARING DETECTION.pdfssuserb5b999
 
1. completion sequance
1. completion sequance1. completion sequance
1. completion sequanceElsayed Amer
 
2007 Porsche Cayman Service Repair Manual
2007 Porsche Cayman Service Repair Manual2007 Porsche Cayman Service Repair Manual
2007 Porsche Cayman Service Repair Manualjkmsmmkem8u
 
Andron design portfolio final
Andron design portfolio finalAndron design portfolio final
Andron design portfolio finalpartymarty
 
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...IRJET Journal
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521fjjskekfsemmd
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521fujdjjksekmem
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521fjjskekkdkoepll
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521fjjskekkdkoepll
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521fjjskekfsemmd
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521fujdjjksekmem
 

Similar to 160316 EX401 rebuild welding report (14)

160709 EX403 UNDERCARRIAGE REPAIRING REPORT
160709 EX403 UNDERCARRIAGE REPAIRING REPORT160709 EX403 UNDERCARRIAGE REPAIRING REPORT
160709 EX403 UNDERCARRIAGE REPAIRING REPORT
 
FLUID FILM BEARING DETECTION.pdf
FLUID FILM BEARING DETECTION.pdfFLUID FILM BEARING DETECTION.pdf
FLUID FILM BEARING DETECTION.pdf
 
1. completion sequance
1. completion sequance1. completion sequance
1. completion sequance
 
2007 Porsche Cayman Service Repair Manual
2007 Porsche Cayman Service Repair Manual2007 Porsche Cayman Service Repair Manual
2007 Porsche Cayman Service Repair Manual
 
Andron design portfolio final
Andron design portfolio finalAndron design portfolio final
Andron design portfolio final
 
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...IRJET- 	 A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
IRJET- A Case Study: In-Situ Weld Repair of Steel Casting of Grade C12A AST...
 
Wellhead basics
Wellhead basicsWellhead basics
Wellhead basics
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 4 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
Jcb 3 cx t4f backhoe loader service repair manual from 02254521 to 02274521
 
Z (30)
Z (30)Z (30)
Z (30)
 

160316 EX401 rebuild welding report

  • 1. 1 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT EX401 WELDING REBUILD: Bucket; Boom; Cascade Room; superstructure; Engine Module; Date of Rebuild: Feb-March 2016 NDT Technique: Magnetic Particle Test Weld Rebuild report: Ray Krueger 20th Sept 2015
  • 2. 2 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT REPAIR COMPLETED FOR FRONT CLAM EX401—340FW2 ChromiumCarbide plates fittedtoBoth walls in and outside and alsothe floor. Buildupadaptor stationstofit template
  • 3. 3 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT Cut out worn section of side wall on both sides and replace with new plate 25mm, weldox 400 or A514 plate. Refer to Ray for exact position of cut. REPLACEMENT REAR SIDE WALL SECTIONS FITTED AND WELDED TO PROCEDURE.
  • 4. 4 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT All barsremovedandreplaced withchromiumCarbide after all cracks repaired Replace complete impactbar across back of Jaw Cracks repaired, new chromium carbide fittedand new impactblock New ChromiumCarbide floor New cornerblocks,new wear package on outside walls
  • 5. 5 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT COMPLETED FRONT CLAM BACK WALL OF BUCKET REPAIRS WEAR PACKAGE FITTED, CRACKS REPAIRED
  • 6. 6 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT COMPLETED BUCKET EX401 BOOM REPAIR: Major cracks continually developing from the man hole. Complete removal of stressed section and fully weld in position.
  • 7. 7 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT Fullyweldedand back gouged from inside and fullyweldedbothsides.Full pre heat and quality weldswith stressrelievingpeening. FINISHED REPAIR TO MANHOLE AND FULL REPAIRS TO ALL PADS.
  • 8. 8 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT POOR QUALITY WELDING ON BLOCKS ON BOOM, THAT HAVE LED TO CRACKS. COMPLETE REPAIR OF CRACKS AND REWELDING OF PADS TO CORRECT STANDARD FOLLOWING ALL WELD PROCEDURES. BOOM CONTINUED
  • 9. 9 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT Superstructure repairs
  • 10. 10 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT COMPLETE FULLY GOUGE AND REWELD CASCADE ROOM REPAIRS: MULTIPLE CRACKS IN WALLS AND AROUND MOUNTING BLOCKS.
  • 11. 11 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT GOUGING ANDWELDING ALL CRACKS AND BACK GOUGEDAND WELDED FROM INSIDE WHERE POSSIBLE. FULLY WELDED AND BLENDED
  • 12. 12 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT EX401 ENGINE MODULE ALL CRACKED SECTIONS REMOVED AND REPAIRED.
  • 13. 13 | P a g e G G M A s s e t M a n a g e m e n t & R e l i a b i l i t y REPAIR REPORT NDT Technician - Comments 1. 2. 3. 4. 5. Welding Supervisor - Comments 1. 2. 3. 4. 5. Condition Monitoring & Reliability - Comments 1. 2. 3. 4. 5.