STATEMENT OF WORK FOR ECONOMIC ANALYSIS
BACKGROUND

The Upper Missouri River Breaks National Monument includes about 375,000 acres of public
land within four counties in north central Montana; Fergus, Chouteau, Blaine, and Phillips
Counties. The economic analysis study area should also include Hill County. Surface ownership
in the five county area includes private, State, Tribal, and Federal.

OBJECTIVES

The Lewistown Field Office of the Bureau of Land Management (BLM) is preparing a resource
management plan (RMP) and environmental impact statement (EIS) for the Upper Missouri River
Breaks National Monument. An economic analysis is needed to provide information to be used in
the course of developing the RMP/EIS.

Specific objectives are to:

1. Characterize the economic conditions and trends for a five county area in north central
   Montana and the relationship to the overall economy in Montana.

2. Describe the degree of dependence on BLM for resources and amenities including what
   portion of the area’s economic activity can be attributable to public land.

3. Characterize impacts to existing conditions and trends based on implementation of a
   reasonable range of management alternatives.

4. Document and report findings for inclusion in a resource management plan and environmental
   impact statement.

STATEMENT OF WORK

The contractor shall:

● Make available, a specialist in economics that has experience in gathering baseline economic
  information, performing an economic impact analysis using accepted analytical methods based
  on a reasonable range of alternatives, writing technical reports, and writing draft and final
  sections for an environmental impact statement. The economic specialist would be a member
  of an interdisciplinary planning team and must be available to attend regularly scheduled team
  meetings on the 2nd Tuesday and Wednesday of each month in Lewistown, Montana,
  beginning in September 2003.

●   Utilize the Economic Profile System (EPS) to characterize baseline economic conditions. The
    economic baseline assessment must interpret information from EPS including trends and the
    degree of dependence on BLM for resources and amenities. EPS was developed by the
    Sonoran Institute under an agreement with the BLM and is public domain. Software, data
    sets, and a user’s manual can be downloaded without charge from the Sonoran Institute’s web
                                                1
site (www.sonoran.org).

● Be committed to the timeframe of this statement of work. Should an unexpected situation
  arise where the economic specialist would not be available to complete the statement of work
  tasks, a substitute must meet the same criteria specified above and meet with the approval of
  the Project Manager from the BLM Lewistown Field Office.

● Provide the economic sections for the Upper Missouri River Breaks National Monument
  Resource Management Plan (RMP) and Environmental Impact Statement (EIS) consistent
  with the Federal Land Policy and Management Act of 1976 and the BLM’s planning
  regulations (43 CFR Part 1600), the National Environmental Policy Act of 1969 and the
  Council of Environmental Quality regulations (40 CFR Parts 1500-1508), the BLM Land Use
  Planning Handbook H-1601-1, and BLM WO IM No. 2002-167 (Social and Economic
  Analysis for Land Use Planning).

STUDY AREA

The study area includes five counties in north central Montana: Fergus, Chouteau, Blaine,
Phillips, and Hill. Four of the counties (Fergus, Chouteau, Blaine, and Phillips) are cooperating
agencies with the BLM in preparation of the RMP/EIS.

COMMUNICATION AND COORDINATION

Frequent open communication and coordination between the Contractor and the BLM will be
required through all phases of the project. Bi-weekly electronic mail contacts documenting
project status and a monthly hard copy progress report are required.

Attendance of the economic specialist is required at regularly scheduled team meetings on the 2nd
Tuesday and Wednesday of each month in Lewistown, Montana.

The primary contact for the Contractor will be the BLM contracting officers’ representative
(COR). The Contractor will not contact other BLM specialists directly for information without
first going through the COR.

Deliverables shall be addressed to the BLM as follows:

Bureau of Land Management
Jerry Majerus, Project Manager
P.O. Box 1160
Lewistown, MT 59457

PERIOD OF PERFORMANCE

Work will take place approximately August 2003 through June 2005. The scheduled due dates in
the deliverables could change based on public comment periods, public review comments, and
unforeseen circumstances. Any change in scheduled due dates will be a modification to the
contract.
                                                 2
DELIVERABLES

•   A draft and final economic baseline assessment of the existing conditions and trends in the five
    county study area along with the study areas relationship to public land and the overall
    economy in Montana. The economic baseline assessment should provide information for
    individual communities where possible, individual counties, five county study area, and a
    complete bibliography. The draft economic baseline assessment is due September 30, 2003.
    The final economic baseline assessment is due November 13, 2003.

•   A draft and final economic section for the affected environment chapter in the draft RMP/EIS.
    This section should be summarized and/or based on information from the final economic
    baseline assessment (approximately 15 pages). The draft economic section is due December
    5, 2003. The final economic section is due January 21, 2004.

•   A draft and final economic section for the environmental consequences chapter of the draft
    RMP/EIS. This section should characterize the economic impacts to existing conditions and
    trends based on the implementation of a reasonable range of alternatives (approximately 20
    pages). A reasonable range of alternatives will be provided by the BLM. The draft economic
    section is due December 29, 2003. The final economic section is due February 11, 2004.

•   Review of the preliminary draft RMP/EIS. Review begins on or about April 1, 2004. Review
    comments are due within 15 workdays.

•   Any necessary revisions to the economic sections of the affected environment and
    environmental consequences chapters based on the BLM and cooperating agencies review of
    the preliminary draft RMP/EIS. Revisions are due May 21, 2004.

•   A summary of the economic comments received from the public on the draft RMP/EIS. The
    summary of economic comments is due October 22, 2004.

•   A draft and final response(s) to all substantive economic comments received from the public
    on the draft RMP/EIS for inclusion in the final RMP/EIS. The draft response(s) is due
    November 30, 2004. The final response(s) is due January 11, 2005.

•   A draft and final economic section of the affected environment chapter for the final RMP/EIS
    based on public comments received on the draft RMP/EIS (approximately 15 pages). The
    draft economic section is due November 30, 2004. The final economic section is due January
    11, 2005.

•   A draft and final economic impact analysis section for the environmental consequences
    chapter based on a reasonable range of alternatives provided by BLM for the final resource
    management plan and environmental impact statement (approximately 20 pages). The draft
    economic section is due November 30, 2004. The final economic section is due January 11,
    2005.
                                                 3
•   Review of the preliminary final RMP/EIS. Review begins on or about February 1, 2005.
    Review comments are due within 15 workdays.

•   Any necessary revisions to the economic sections of the affected environment and
    environmental consequences chapters based on the BLM and cooperating agencies review of
    the preliminary final RMP/EIS. Revisions are due March 25, 2005.

•   All draft and final sections should be formatted using 1-inch margins (top, bottom, right, and
    left), font Times New Roman, font style regular, and size 12.

•   Seven copies of all draft sections should be submitted for BLM’s review with accompanying
    CD in Microsoft Word format.

•   The BLM will turn comments on all drafts around in 15 workdays.

•   Within 15 workdays of receiving comments from BLM on draft economic sections, the
    contractor will submit final reports (one copy) with accompanying CD in Microsoft Word
    format.




                                                 4

More Related Content

What's hot

UWF Public Budgeting Model Research Paper
UWF Public Budgeting Model Research PaperUWF Public Budgeting Model Research Paper
UWF Public Budgeting Model Research Paper
Carlos Tobar
 

What's hot (10)

Performance Budgeting - Key Performance Indicators - Igor YAREMENKO, Russian ...
Performance Budgeting - Key Performance Indicators - Igor YAREMENKO, Russian ...Performance Budgeting - Key Performance Indicators - Igor YAREMENKO, Russian ...
Performance Budgeting - Key Performance Indicators - Igor YAREMENKO, Russian ...
 
Planning History Theory Study Notes
Planning History Theory Study NotesPlanning History Theory Study Notes
Planning History Theory Study Notes
 
Department of Agriculture Preliminary Regulatory Reform Plan
Department of Agriculture Preliminary Regulatory Reform PlanDepartment of Agriculture Preliminary Regulatory Reform Plan
Department of Agriculture Preliminary Regulatory Reform Plan
 
Budget transparency - Didik Kusnaini, Indonesia
Budget transparency - Didik Kusnaini, IndonesiaBudget transparency - Didik Kusnaini, Indonesia
Budget transparency - Didik Kusnaini, Indonesia
 
UWF Public Budgeting Model Research Paper
UWF Public Budgeting Model Research PaperUWF Public Budgeting Model Research Paper
UWF Public Budgeting Model Research Paper
 
National Water Strategy for Azerbaijan
National Water Strategy for AzerbaijanNational Water Strategy for Azerbaijan
National Water Strategy for Azerbaijan
 
NUP Process
NUP ProcessNUP Process
NUP Process
 
Medium term budgetary frameworks - Emil NURGALIEV, Bulgaria
Medium term budgetary frameworks - Emil NURGALIEV, BulgariaMedium term budgetary frameworks - Emil NURGALIEV, Bulgaria
Medium term budgetary frameworks - Emil NURGALIEV, Bulgaria
 
9/9 FRI 08:00 | Large-Area Planning for Florida's Varied Landscapes 1
9/9 FRI 08:00 | Large-Area Planning for Florida's Varied Landscapes 19/9 FRI 08:00 | Large-Area Planning for Florida's Varied Landscapes 1
9/9 FRI 08:00 | Large-Area Planning for Florida's Varied Landscapes 1
 
Reforming the italian budget process: strengthening the allocation function a...
Reforming the italian budget process: strengthening the allocation function a...Reforming the italian budget process: strengthening the allocation function a...
Reforming the italian budget process: strengthening the allocation function a...
 

Similar to (13.5) contracting sow example

Mac Plan 2006
Mac Plan 2006Mac Plan 2006
Mac Plan 2006
darciea
 
Brownfields under trump panel
Brownfields under trump panelBrownfields under trump panel
Brownfields under trump panel
EDR
 
Brownfields Under Trump - Panel
Brownfields Under Trump - PanelBrownfields Under Trump - Panel
Brownfields Under Trump - Panel
EDR
 
Developing a Regional WIP Response
Developing a Regional WIP ResponseDeveloping a Regional WIP Response
Developing a Regional WIP Response
CleanH2O
 
HUB CC final print version english
HUB CC final print version englishHUB CC final print version english
HUB CC final print version english
Cédric van Riel
 
Thomas Clark Resume 11 19 14
Thomas Clark Resume 11 19 14Thomas Clark Resume 11 19 14
Thomas Clark Resume 11 19 14
Thomas Clark
 

Similar to (13.5) contracting sow example (20)

Mac Plan 2006
Mac Plan 2006Mac Plan 2006
Mac Plan 2006
 
GSP Pillar 1 Implementation plan - Liesl Wiese & Dan Pennock
GSP Pillar 1 Implementation plan - Liesl Wiese & Dan PennockGSP Pillar 1 Implementation plan - Liesl Wiese & Dan Pennock
GSP Pillar 1 Implementation plan - Liesl Wiese & Dan Pennock
 
Architecture Town And Planing Lecturee
Architecture Town And Planing LectureeArchitecture Town And Planing Lecturee
Architecture Town And Planing Lecturee
 
Planning Issues Specific To Plumas County
Planning  Issues  Specific To  Plumas CountyPlanning  Issues  Specific To  Plumas County
Planning Issues Specific To Plumas County
 
Sturgeon Valley Phase 1 Growth Framework
Sturgeon Valley Phase 1 Growth FrameworkSturgeon Valley Phase 1 Growth Framework
Sturgeon Valley Phase 1 Growth Framework
 
Eco 370 week 1 d qs
Eco 370 week 1 d qsEco 370 week 1 d qs
Eco 370 week 1 d qs
 
Brownfields under trump panel
Brownfields under trump panelBrownfields under trump panel
Brownfields under trump panel
 
Brownfields Under Trump - Panel
Brownfields Under Trump - PanelBrownfields Under Trump - Panel
Brownfields Under Trump - Panel
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptx
 
Developing a Regional WIP Response
Developing a Regional WIP ResponseDeveloping a Regional WIP Response
Developing a Regional WIP Response
 
Eco 370 entire course
Eco 370 entire courseEco 370 entire course
Eco 370 entire course
 
170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx170280106122_Vegada_Vipul_EIA_Presentation.pptx
170280106122_Vegada_Vipul_EIA_Presentation.pptx
 
charlotte_2010
charlotte_2010charlotte_2010
charlotte_2010
 
Utility-Scale Solar Power on Federal Lands
Utility-Scale Solar Power on Federal LandsUtility-Scale Solar Power on Federal Lands
Utility-Scale Solar Power on Federal Lands
 
spatial planning
spatial planning spatial planning
spatial planning
 
CCCXG Global Forum March 2017 BGB Kenya: Tracking national progress on adapta...
CCCXG Global Forum March 2017 BGB Kenya: Tracking national progress on adapta...CCCXG Global Forum March 2017 BGB Kenya: Tracking national progress on adapta...
CCCXG Global Forum March 2017 BGB Kenya: Tracking national progress on adapta...
 
HUB CC final print version english
HUB CC final print version englishHUB CC final print version english
HUB CC final print version english
 
Thomas Clark Resume 11 19 14
Thomas Clark Resume 11 19 14Thomas Clark Resume 11 19 14
Thomas Clark Resume 11 19 14
 
Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...
Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...
Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...
 
Perspective plan
Perspective planPerspective plan
Perspective plan
 

Recently uploaded

Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
vineshkumarsajnani12
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Recently uploaded (20)

Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
Chennai Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Av...
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 

(13.5) contracting sow example

  • 1. STATEMENT OF WORK FOR ECONOMIC ANALYSIS BACKGROUND The Upper Missouri River Breaks National Monument includes about 375,000 acres of public land within four counties in north central Montana; Fergus, Chouteau, Blaine, and Phillips Counties. The economic analysis study area should also include Hill County. Surface ownership in the five county area includes private, State, Tribal, and Federal. OBJECTIVES The Lewistown Field Office of the Bureau of Land Management (BLM) is preparing a resource management plan (RMP) and environmental impact statement (EIS) for the Upper Missouri River Breaks National Monument. An economic analysis is needed to provide information to be used in the course of developing the RMP/EIS. Specific objectives are to: 1. Characterize the economic conditions and trends for a five county area in north central Montana and the relationship to the overall economy in Montana. 2. Describe the degree of dependence on BLM for resources and amenities including what portion of the area’s economic activity can be attributable to public land. 3. Characterize impacts to existing conditions and trends based on implementation of a reasonable range of management alternatives. 4. Document and report findings for inclusion in a resource management plan and environmental impact statement. STATEMENT OF WORK The contractor shall: ● Make available, a specialist in economics that has experience in gathering baseline economic information, performing an economic impact analysis using accepted analytical methods based on a reasonable range of alternatives, writing technical reports, and writing draft and final sections for an environmental impact statement. The economic specialist would be a member of an interdisciplinary planning team and must be available to attend regularly scheduled team meetings on the 2nd Tuesday and Wednesday of each month in Lewistown, Montana, beginning in September 2003. ● Utilize the Economic Profile System (EPS) to characterize baseline economic conditions. The economic baseline assessment must interpret information from EPS including trends and the degree of dependence on BLM for resources and amenities. EPS was developed by the Sonoran Institute under an agreement with the BLM and is public domain. Software, data sets, and a user’s manual can be downloaded without charge from the Sonoran Institute’s web 1
  • 2. site (www.sonoran.org). ● Be committed to the timeframe of this statement of work. Should an unexpected situation arise where the economic specialist would not be available to complete the statement of work tasks, a substitute must meet the same criteria specified above and meet with the approval of the Project Manager from the BLM Lewistown Field Office. ● Provide the economic sections for the Upper Missouri River Breaks National Monument Resource Management Plan (RMP) and Environmental Impact Statement (EIS) consistent with the Federal Land Policy and Management Act of 1976 and the BLM’s planning regulations (43 CFR Part 1600), the National Environmental Policy Act of 1969 and the Council of Environmental Quality regulations (40 CFR Parts 1500-1508), the BLM Land Use Planning Handbook H-1601-1, and BLM WO IM No. 2002-167 (Social and Economic Analysis for Land Use Planning). STUDY AREA The study area includes five counties in north central Montana: Fergus, Chouteau, Blaine, Phillips, and Hill. Four of the counties (Fergus, Chouteau, Blaine, and Phillips) are cooperating agencies with the BLM in preparation of the RMP/EIS. COMMUNICATION AND COORDINATION Frequent open communication and coordination between the Contractor and the BLM will be required through all phases of the project. Bi-weekly electronic mail contacts documenting project status and a monthly hard copy progress report are required. Attendance of the economic specialist is required at regularly scheduled team meetings on the 2nd Tuesday and Wednesday of each month in Lewistown, Montana. The primary contact for the Contractor will be the BLM contracting officers’ representative (COR). The Contractor will not contact other BLM specialists directly for information without first going through the COR. Deliverables shall be addressed to the BLM as follows: Bureau of Land Management Jerry Majerus, Project Manager P.O. Box 1160 Lewistown, MT 59457 PERIOD OF PERFORMANCE Work will take place approximately August 2003 through June 2005. The scheduled due dates in the deliverables could change based on public comment periods, public review comments, and unforeseen circumstances. Any change in scheduled due dates will be a modification to the contract. 2
  • 3. DELIVERABLES • A draft and final economic baseline assessment of the existing conditions and trends in the five county study area along with the study areas relationship to public land and the overall economy in Montana. The economic baseline assessment should provide information for individual communities where possible, individual counties, five county study area, and a complete bibliography. The draft economic baseline assessment is due September 30, 2003. The final economic baseline assessment is due November 13, 2003. • A draft and final economic section for the affected environment chapter in the draft RMP/EIS. This section should be summarized and/or based on information from the final economic baseline assessment (approximately 15 pages). The draft economic section is due December 5, 2003. The final economic section is due January 21, 2004. • A draft and final economic section for the environmental consequences chapter of the draft RMP/EIS. This section should characterize the economic impacts to existing conditions and trends based on the implementation of a reasonable range of alternatives (approximately 20 pages). A reasonable range of alternatives will be provided by the BLM. The draft economic section is due December 29, 2003. The final economic section is due February 11, 2004. • Review of the preliminary draft RMP/EIS. Review begins on or about April 1, 2004. Review comments are due within 15 workdays. • Any necessary revisions to the economic sections of the affected environment and environmental consequences chapters based on the BLM and cooperating agencies review of the preliminary draft RMP/EIS. Revisions are due May 21, 2004. • A summary of the economic comments received from the public on the draft RMP/EIS. The summary of economic comments is due October 22, 2004. • A draft and final response(s) to all substantive economic comments received from the public on the draft RMP/EIS for inclusion in the final RMP/EIS. The draft response(s) is due November 30, 2004. The final response(s) is due January 11, 2005. • A draft and final economic section of the affected environment chapter for the final RMP/EIS based on public comments received on the draft RMP/EIS (approximately 15 pages). The draft economic section is due November 30, 2004. The final economic section is due January 11, 2005. • A draft and final economic impact analysis section for the environmental consequences chapter based on a reasonable range of alternatives provided by BLM for the final resource management plan and environmental impact statement (approximately 20 pages). The draft economic section is due November 30, 2004. The final economic section is due January 11, 2005. 3
  • 4. Review of the preliminary final RMP/EIS. Review begins on or about February 1, 2005. Review comments are due within 15 workdays. • Any necessary revisions to the economic sections of the affected environment and environmental consequences chapters based on the BLM and cooperating agencies review of the preliminary final RMP/EIS. Revisions are due March 25, 2005. • All draft and final sections should be formatted using 1-inch margins (top, bottom, right, and left), font Times New Roman, font style regular, and size 12. • Seven copies of all draft sections should be submitted for BLM’s review with accompanying CD in Microsoft Word format. • The BLM will turn comments on all drafts around in 15 workdays. • Within 15 workdays of receiving comments from BLM on draft economic sections, the contractor will submit final reports (one copy) with accompanying CD in Microsoft Word format. 4