Aggregate Planning in
Supply Chain
LIAQAT JAVED
Chapter 8
Supply Chain Management
Strategy, Planning, and Operation
Sunail Chopra
Pearson
Learning Objectives
the importance of aggregate Planning.
Understand
Information needed and Output of aggregate planing
Know
Trade-offs in creating an aggregate plan
Explain
Skill to prepare an aggregate plan
Develop
Aggregate Planning in the SC
8.1 The Role of Aggregate Planning in a Supply Chain
8.2 The Aggregate Planning Problem
8.3 Aggregate Planning Strategies
8.4 Aggregate Planning at Red Tomato Tools
8.5 Aggregate Planning Using Linear Programming
8.6 Aggregate Planning in Excel
8.7 Building a Rough Master Production Schedule
8.8 The Role of IT in Aggregate Planning
8.9 Implementing Aggregate Planning in Practice
Aggregate Planning
Given the demand forecast for each period in the planning
horizon, determine the production level, inventory level,
capacity level (internal and outsourced), and any backlogs
(unmet demand) for each period
that maximizes the firm’s profit over the planning horizon.
Role of
Aggregate
Planning
Capacity cost and long lead times challenge
Aggregate planning:
◦ Process to determines levels of capacity,
production, subcontracting, inventory, stockouts,
and pricing over a specified time horizon.
◦ Goal is to maximize profit
◦ Decisions at a product family (not SKU) level
◦ Time frame of 3 to 18 months (Planning Horizon)
◦ How can a firm best use the facilities it has?
Aggregate
planning
determines
◦ Production rate
◦ No. of units completed per month or per unit time (regular)
◦ Workforce
◦ Number of workers or units of labour required per month
◦ Overtime
◦ Hours of overtime production planned per month
◦ Machine capacity level
◦ No. of units of machine capacity required / machine hours
◦ Subcontracting
◦ Contracted capacity required per month
◦ Backlog
◦ Demand not able to meet in the demand period but carried over to
the next periods.
◦ Inventory on hand
◦ Planned inventory carried over to next period
Operational parameters over the
time horizon (Planning Cycle)
Given the demand forecast for each period in the
planning horizon, determine the production level, inventory
level, and the capacity level for each period that maximizes
the firm’s (supply chain’s) profit over the planning horizon
Specify the planning horizon (typically 3-18 months)
Specify the duration of each period
Specify key information required to develop an aggregate
plan
Resources and capacity challenges
The Aggregate Planning Problem
Information Needed for an Aggregate Plan
Aggregate demand forecast Ft for each Period t over T periods
Production costs
◦ Labor costs, regular time ($/hr) and overtime ($/hr)
◦ Cost of changing capacity – hiring or layoff ($/worker), adding or reducing machine capacity
($/machine)
◦ Subcontracting costs ($/hr or $/unit)
Labor/machine hours required per unit
Inventory holding cost ($/unit/period)
Stockout or backlog cost ($/unit/period)
Constraints
– Limits overtime, layoffs, capital
available, stockouts, backlogs,
and from suppliers
Information Needed
Constraints
• Limits on overtime
• Limits on layoffs
• Limits on capital available
• Limits on stockouts and backlogs
• Constraints from suppliers to the enterprise
Outputs of Aggregate Planning
•Production quantity from regular time, overtime, and subcontracted time
•Inventory held
•Backlog/stockout quantity
•Machine capacity increase/decrease
A poor aggregate plan can result in
◦ lost sales,
◦ lost profits,
◦ excess inventory,
◦ or excess capacity
Identifying
Aggregate
Units of
Production
Aggregate unit should be
identified in a way that the
resulting production schedule
can be accomplished in practice
Focus on the bottlenecks when
selecting the aggregate unit and
identifying capacity and
production times
Account for activities such as
setups and maintenance
Kg, Tons,
Volume,
Work Hours  Sales
Red Tomato Tools
Family
Material
Cost/ Unit
($)
Revenue/
Unit ($)
Setup
Time/
Batch
(hour)
Average
Batch Size
Production
Time/ Unit
(hour)
Net Production
Time/Unit
(hour)
Percentage
Share of Units
Sold
A 15 54 8 50 5.60 5.76 10%
B 7 30 6 150 3.00 3.04 25%
C 9 39 8 100 3.80 3.88 20%
D 12 49 10 50 4.80 5.00 10%
E 9 36 6 100 3.60 3.66 20%
F 13 48 5 75 4.30 4.37 15%
Red Tomato Tools
•Weighted average approach
Material cost per aggregate unit
= 15 x 0.10 + 7 x 0.25 + 9 x 0.20
+ 12 x 0.10 + 9 x 0.20 + 13 x 0.15
= $10
•Similarly
Revenue per aggregate unit = $40
Net production time per aggregate unit = 4.00 hours
Aggregate Planning Strategies
Trade-off between capacity, inventory, backlog/lost sales
1. Chase strategy – using capacity as the lever
2. Flexibility strategy - workforce Time flexibility –utilization as the lever
3. Level strategy – using inventory as the lever
4. Tailored or hybrid strategy – a combination of strategies
Chase Strategy
Vary machine capacity or hire and lay off workers as demand varies
Often difficult to vary capacity and workforce on short notice
Expensive if cost of varying capacity is high
Negative effect on workforce morale
Results in low levels of inventory
Used when inventory holding costs are high and costs of changing capacity are low
Time Flexibility Strategy
Use excess machine capacity
Workforce stable, number of hours worked varies
Use overtime or a flexible work schedule
Flexible workforce, avoids morale problems
Low levels of inventory, lower utilization
Used when inventory holding costs are high and capacity is relatively inexpensive
Level Strategy
Stable machine capacity and workforce levels, constant output rate
Inventory levels fluctuate over time
Inventories carried over from high to low demand periods
Better for worker morale
Large inventories and backlogs may accumulate
Used when inventory holding and backlog costs are relatively low
Aggregate Planning by Linear Programming
Red Tomato Tools
◦ Highly seasonal demand
◦ Develop a forecast
Month Demand Forecast
January 1,600
February 3,000
March 3,200
April 3,800
May 2,200
June 2,200
Red Tomato Tools
Item Cost
Material cost $10/unit
Inventory holding cost $2/unit/month
Marginal cost of stockout/backlog $5/unit/month
Hiring and training costs $300/worker
Layoff cost $500/worker
Labor hours required 4/unit
Regular time cost $4/hour
Overtime cost $6/hour
Cost of subcontracting $30/unit
Red Tomato Tools
Decision Variables
For t = 1, ..., 6
Wt = Workforce size for month t
Ht = Number of employees hired at the beginning of month
t
Lt = Number of employees laid off at the beginning of
month t
Pt = Production in month t
It = Inventory at the end of month t
St = Number of units stocked out at the end of month t
Ct = Number of units subcontracted for month t
Ot = Number of overtime hours worked in month t
Red Tomato Tools
Objective Function
•Minimize
(Regular-time labor cost + Overtime labor cost + Cost of hiring
and layoffs + Cost of holding inventory + Cost of stocking out +
Cost of subcontracting + Material cost)
Min 640Wt
t=1
6
å + 6Ot
t=1
6
å + 300Ht
t=1
6
å + 500Lt
t=1
6
å
+ 2It
t=1
6
å + 5St
t=1
6
å + 10Pt
t=1
6
å + 30Ct
t=1
6
å
Red Tomato Tools
Constraints
1. Workforce, hiring, and layoff constraints
All for t = 1,..., 6
Wt
=W t–1
+Ht
– Lt
2. Capacity constraints
Pt
£ 40Wt
+
Ot
4
3. Inventory balance constraints
It–1
+ Pt
+Ct
= Dt
+ St–1
+ It
– St
4. Overtime limit constraints
Ot
£10Wt
Red Tomato Tools
Constraints
1. Workforce, hiring, and layoff constraints
All for t = 1,..., 6
Wt
=W t–1
+Ht
– Lt
2. Capacity constraints
Pt
£ 40Wt
+
Ot
4
3. Inventory balance constraints
It–1
+ Pt
+Ct
= Dt
+ St–1
+ It
– St
4. Overtime limit constraints
Ot
£10Wt
Red Tomato Tools
Average inventory =
(I0
+ IT
) / 2+ It
t=1
T –1
å
( )
T
=
(I0
+ IT
) / 2+ It
t=1
T –1
å
( )
T
é
ë
ê
ê
ê
ù
û
ú
ú
ú
Dt
t=1
T –1
å
( )
T
é
ë
ê
ê
ê
ù
û
ú
ú
ú
Average time
in inventory
Red Tomato Tools
Total cost over planning horizon = $422,275
Revenue over planning horizon = 40 x 16,000 = $640,000
Period, t
No.
Hired,
Ht
No.
Laid
Off,
Workforce
Size, Wt
Overtime,
Ot Inventory, Stockout, Subcontract,
Total
Production,
0 0 0 80 0 1,000 0 0
1 0 15 65 0 1,983 0 0 2,583
2 0 0 65 0 1,567 0 0 2,583
3 0 0 65 0 950 0 0 2,583
4 0 0 65 0 0 267 0 2,583
5 0 0 65 0 117 0 0 2,583
6 0 0 65 0 500 0 0 2,583
Red Tomato Tools
=
(I0
+ I6
) / 2+ It
t=1
5
å
( )
T
=
5,367
6
= 895
Average
seasonal
inventory
Average flow time =
895
2,667
= 0.34 = 0.34 months
Red Tomato Tools
Higher demand variability
Month Demand Forecast
January 1,000
February 3,000
March 3,800
April 4,800
May 2,000
June 1,400
=
(I0
+ IT
) / 2+ It
t=1
T –1
å
( )
T
=
6,450
6
=1,075
Average
seasonal
inventory
Red Tomato Tools
Total cost over planning horizon = $432,858
Period, t
No.
Hired,
Ht
No.
Laid
Off,
Workforce
Size, Wt
Overtime,
Ot Inventory, Stockout, Subcontract,
Total
Production,
0 0 0 80 0 1,000 0 0
1 0 15 65 0 2,583 0 0 2,583
2 0 0 65 0 2,167 0 0 2,583
3 0 0 65 0 950 0 0 2,583
4 0 0 65 0 0 1,267 0 2,583
5 0 0 65 0 0 683 0 2,583
6 0 0 65 0 500 0 0 2,583
Average flow time =
1,075
2,667
= 0.40 months
Red Tomato Tools
Lower hiring and layoff costs
=
(I0
+ IT
) / 2+ It
t=1
T –1
å
( )
T
=
2,500
6
= 417
Average
seasonal
inventory
Average flow time =
417
2,667
= 0.16 months
Total cost over planning horizon = $412,688
Red Tomato Tools
Period, t
No.
Hired,
Ht
No.
Laid
Off, Lt
Workforce
Size, Wt
Overtime,
Ot Inventory, It Stockout, St Subcontract, Ct
Total
Production, Pt
0 0 0 80 0 1,000 0 0
1 0 35 45 0 1,200 0 0 2,267
2 0 0 45 0 0 0 0 2,267
3 42 0 87 0 300 0 0 2,267
4 0 0 87 0 0 1,267 0 2,267
5 0 26 61 0 250 683 0 2,267
6 0 0 61 0 500 0 0 2,267
Forecast Error in Aggregate
Plans
Forecast errors must be considered
Safety inventory
Safety capacity
◦ Use overtime as a form of safety capacity
◦ Carry extra workforce permanently as a form of safety
capacity
◦ Use subcontractors as a form of safety capacity
◦ Build and carry extra inventories as a form of safety
inventory
◦ Purchase capacity or product from an open or spot market
as a form of safety capacity
Aggregate Planning In Excel
For t = 1, ..., 6
Wt = Workforce size for Month t
Ht = Number of employees hired at the beginning of Month t
Lt = Number of employees laid off at the beginning of Month t
Pt = Production in Month t
It = Inventory at the end of Month t
St = Number of units stocked out at the end of Month t
Ct = Number of units subcontracted for Month t
Ot = Number of overtime hours worked in Month t
Aggregate Planning In Excel
Aggregate
Planning In
Excel
Aggregate Planning In Excel
Aggregate Planning In Excel
Building a Rough Master Production Schedule
Disaggregate an aggregate plan
Family
Setup
Time/Ba
ch (hour)
Average
Batch Size
Production
Time/Unit
(hour)
Production
Quantity
Number
of
Setup
Time
(hours)
Production
Time (hours)
A 8 50 5.60 258 5 40 1,445
B 6 150 3.00 646 4 24 1,938
C 8 100 3.80 517 5 40 1,965
D 10 50 4.80 258 5 50 1,238
E 6 100 3.60 517 5 30 1,861
F 5 75 4.30 387 5 25 1,664
The Role of IT in
Aggregate Planning
The ability to handle large problems
The ability to handle complex problems (through either nonlinear optimization
or linear approximations)
The ability to interact with other core IT systems such as inventory management
and sourcing
Implementing Aggregate Planning
Think
Think beyond the
enterprise to the
entire supply chain
Make
Make plans flexible
because forecasts
are always
inaccurate
Rerun
Rerun the aggregate
plan as new data
emerge
Use
Use aggregate
planning as capacity
utilization increases

More Related Content

Similar to 08.1 Aggregate Planning in SC. and scope pptx

aggregate planning in the supply chain
aggregate planning in the supply chainaggregate planning in the supply chain
aggregate planning in the supply chainManish Kaushik
 
aggregate planning in the supply chain
aggregate planning in the supply chain aggregate planning in the supply chain
aggregate planning in the supply chain Manish Kaushik
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planningmubarak2009
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning3abooodi
 
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyAggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyIRJET Journal
 
CLO31(1).pptx
CLO31(1).pptxCLO31(1).pptx
CLO31(1).pptxshaikha65
 
Production & Operarions Management Compre Review
Production & Operarions Management Compre ReviewProduction & Operarions Management Compre Review
Production & Operarions Management Compre ReviewRamon Fernandez, MBA
 
Inventory management 091104161506 Phpapp02
Inventory management 091104161506 Phpapp02Inventory management 091104161506 Phpapp02
Inventory management 091104161506 Phpapp02jasonhian
 
Manufacturing's Holy Grail: A Practical Science for Executives and Managers
Manufacturing's Holy Grail: A Practical Science for Executives and ManagersManufacturing's Holy Grail: A Practical Science for Executives and Managers
Manufacturing's Holy Grail: A Practical Science for Executives and ManagersUBMCanon
 
Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.IOSR Journals
 
Manufacture of a Biodegradable Detergent on Small Scale
Manufacture of a Biodegradable Detergent on Small ScaleManufacture of a Biodegradable Detergent on Small Scale
Manufacture of a Biodegradable Detergent on Small ScaleCSCJournals
 
Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityJoanRachelCalansingi
 
Aggregate Planning for industrial engineering
Aggregate Planning for industrial engineeringAggregate Planning for industrial engineering
Aggregate Planning for industrial engineeringashaby
 

Similar to 08.1 Aggregate Planning in SC. and scope pptx (20)

aggregate planning in the supply chain
aggregate planning in the supply chainaggregate planning in the supply chain
aggregate planning in the supply chain
 
aggregate planning in the supply chain
aggregate planning in the supply chain aggregate planning in the supply chain
aggregate planning in the supply chain
 
Sales & Operations Planning
Sales & Operations PlanningSales & Operations Planning
Sales & Operations Planning
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning
 
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyAggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
 
CLO31(1).pptx
CLO31(1).pptxCLO31(1).pptx
CLO31(1).pptx
 
Production & Operarions Management Compre Review
Production & Operarions Management Compre ReviewProduction & Operarions Management Compre Review
Production & Operarions Management Compre Review
 
Inventory management 091104161506 Phpapp02
Inventory management 091104161506 Phpapp02Inventory management 091104161506 Phpapp02
Inventory management 091104161506 Phpapp02
 
Manufacturing's Holy Grail: A Practical Science for Executives and Managers
Manufacturing's Holy Grail: A Practical Science for Executives and ManagersManufacturing's Holy Grail: A Practical Science for Executives and Managers
Manufacturing's Holy Grail: A Practical Science for Executives and Managers
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.
 
ABCD.pptx
ABCD.pptxABCD.pptx
ABCD.pptx
 
Manufacture of a Biodegradable Detergent on Small Scale
Manufacture of a Biodegradable Detergent on Small ScaleManufacture of a Biodegradable Detergent on Small Scale
Manufacture of a Biodegradable Detergent on Small Scale
 
aggregate.ppt
aggregate.pptaggregate.ppt
aggregate.ppt
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of Capacity
 
Unit 3-inventory control
Unit 3-inventory controlUnit 3-inventory control
Unit 3-inventory control
 
Aggregate Planning for industrial engineering
Aggregate Planning for industrial engineeringAggregate Planning for industrial engineering
Aggregate Planning for industrial engineering
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 

Recently uploaded

Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...Sheetaleventcompany
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesPooja Nehwal
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfakankshagupta7348026
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrsaastr
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Delhi Call girls
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyPooja Nehwal
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptssuser319dad
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 

Recently uploaded (20)

Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara ServicesVVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
VVIP Call Girls Nalasopara : 9892124323, Call Girls in Nalasopara Services
 
Motivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdfMotivation and Theory Maslow and Murray pdf
Motivation and Theory Maslow and Murray pdf
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Philippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.pptPhilippine History cavite Mutiny Report.ppt
Philippine History cavite Mutiny Report.ppt
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 

08.1 Aggregate Planning in SC. and scope pptx

  • 1. Aggregate Planning in Supply Chain LIAQAT JAVED
  • 2. Chapter 8 Supply Chain Management Strategy, Planning, and Operation Sunail Chopra Pearson
  • 3. Learning Objectives the importance of aggregate Planning. Understand Information needed and Output of aggregate planing Know Trade-offs in creating an aggregate plan Explain Skill to prepare an aggregate plan Develop
  • 4. Aggregate Planning in the SC 8.1 The Role of Aggregate Planning in a Supply Chain 8.2 The Aggregate Planning Problem 8.3 Aggregate Planning Strategies 8.4 Aggregate Planning at Red Tomato Tools 8.5 Aggregate Planning Using Linear Programming 8.6 Aggregate Planning in Excel 8.7 Building a Rough Master Production Schedule 8.8 The Role of IT in Aggregate Planning 8.9 Implementing Aggregate Planning in Practice
  • 5. Aggregate Planning Given the demand forecast for each period in the planning horizon, determine the production level, inventory level, capacity level (internal and outsourced), and any backlogs (unmet demand) for each period that maximizes the firm’s profit over the planning horizon.
  • 6. Role of Aggregate Planning Capacity cost and long lead times challenge Aggregate planning: ◦ Process to determines levels of capacity, production, subcontracting, inventory, stockouts, and pricing over a specified time horizon. ◦ Goal is to maximize profit ◦ Decisions at a product family (not SKU) level ◦ Time frame of 3 to 18 months (Planning Horizon) ◦ How can a firm best use the facilities it has?
  • 7. Aggregate planning determines ◦ Production rate ◦ No. of units completed per month or per unit time (regular) ◦ Workforce ◦ Number of workers or units of labour required per month ◦ Overtime ◦ Hours of overtime production planned per month ◦ Machine capacity level ◦ No. of units of machine capacity required / machine hours ◦ Subcontracting ◦ Contracted capacity required per month ◦ Backlog ◦ Demand not able to meet in the demand period but carried over to the next periods. ◦ Inventory on hand ◦ Planned inventory carried over to next period Operational parameters over the time horizon (Planning Cycle)
  • 8. Given the demand forecast for each period in the planning horizon, determine the production level, inventory level, and the capacity level for each period that maximizes the firm’s (supply chain’s) profit over the planning horizon Specify the planning horizon (typically 3-18 months) Specify the duration of each period Specify key information required to develop an aggregate plan Resources and capacity challenges The Aggregate Planning Problem
  • 9. Information Needed for an Aggregate Plan Aggregate demand forecast Ft for each Period t over T periods Production costs ◦ Labor costs, regular time ($/hr) and overtime ($/hr) ◦ Cost of changing capacity – hiring or layoff ($/worker), adding or reducing machine capacity ($/machine) ◦ Subcontracting costs ($/hr or $/unit) Labor/machine hours required per unit Inventory holding cost ($/unit/period) Stockout or backlog cost ($/unit/period) Constraints – Limits overtime, layoffs, capital available, stockouts, backlogs, and from suppliers
  • 10. Information Needed Constraints • Limits on overtime • Limits on layoffs • Limits on capital available • Limits on stockouts and backlogs • Constraints from suppliers to the enterprise
  • 11. Outputs of Aggregate Planning •Production quantity from regular time, overtime, and subcontracted time •Inventory held •Backlog/stockout quantity •Machine capacity increase/decrease A poor aggregate plan can result in ◦ lost sales, ◦ lost profits, ◦ excess inventory, ◦ or excess capacity
  • 12. Identifying Aggregate Units of Production Aggregate unit should be identified in a way that the resulting production schedule can be accomplished in practice Focus on the bottlenecks when selecting the aggregate unit and identifying capacity and production times Account for activities such as setups and maintenance Kg, Tons, Volume, Work Hours  Sales
  • 13. Red Tomato Tools Family Material Cost/ Unit ($) Revenue/ Unit ($) Setup Time/ Batch (hour) Average Batch Size Production Time/ Unit (hour) Net Production Time/Unit (hour) Percentage Share of Units Sold A 15 54 8 50 5.60 5.76 10% B 7 30 6 150 3.00 3.04 25% C 9 39 8 100 3.80 3.88 20% D 12 49 10 50 4.80 5.00 10% E 9 36 6 100 3.60 3.66 20% F 13 48 5 75 4.30 4.37 15%
  • 14. Red Tomato Tools •Weighted average approach Material cost per aggregate unit = 15 x 0.10 + 7 x 0.25 + 9 x 0.20 + 12 x 0.10 + 9 x 0.20 + 13 x 0.15 = $10 •Similarly Revenue per aggregate unit = $40 Net production time per aggregate unit = 4.00 hours
  • 15. Aggregate Planning Strategies Trade-off between capacity, inventory, backlog/lost sales 1. Chase strategy – using capacity as the lever 2. Flexibility strategy - workforce Time flexibility –utilization as the lever 3. Level strategy – using inventory as the lever 4. Tailored or hybrid strategy – a combination of strategies
  • 16. Chase Strategy Vary machine capacity or hire and lay off workers as demand varies Often difficult to vary capacity and workforce on short notice Expensive if cost of varying capacity is high Negative effect on workforce morale Results in low levels of inventory Used when inventory holding costs are high and costs of changing capacity are low
  • 17. Time Flexibility Strategy Use excess machine capacity Workforce stable, number of hours worked varies Use overtime or a flexible work schedule Flexible workforce, avoids morale problems Low levels of inventory, lower utilization Used when inventory holding costs are high and capacity is relatively inexpensive
  • 18. Level Strategy Stable machine capacity and workforce levels, constant output rate Inventory levels fluctuate over time Inventories carried over from high to low demand periods Better for worker morale Large inventories and backlogs may accumulate Used when inventory holding and backlog costs are relatively low
  • 19. Aggregate Planning by Linear Programming Red Tomato Tools ◦ Highly seasonal demand ◦ Develop a forecast Month Demand Forecast January 1,600 February 3,000 March 3,200 April 3,800 May 2,200 June 2,200
  • 20. Red Tomato Tools Item Cost Material cost $10/unit Inventory holding cost $2/unit/month Marginal cost of stockout/backlog $5/unit/month Hiring and training costs $300/worker Layoff cost $500/worker Labor hours required 4/unit Regular time cost $4/hour Overtime cost $6/hour Cost of subcontracting $30/unit
  • 21. Red Tomato Tools Decision Variables For t = 1, ..., 6 Wt = Workforce size for month t Ht = Number of employees hired at the beginning of month t Lt = Number of employees laid off at the beginning of month t Pt = Production in month t It = Inventory at the end of month t St = Number of units stocked out at the end of month t Ct = Number of units subcontracted for month t Ot = Number of overtime hours worked in month t
  • 22. Red Tomato Tools Objective Function •Minimize (Regular-time labor cost + Overtime labor cost + Cost of hiring and layoffs + Cost of holding inventory + Cost of stocking out + Cost of subcontracting + Material cost) Min 640Wt t=1 6 å + 6Ot t=1 6 å + 300Ht t=1 6 å + 500Lt t=1 6 å + 2It t=1 6 å + 5St t=1 6 å + 10Pt t=1 6 å + 30Ct t=1 6 å
  • 23. Red Tomato Tools Constraints 1. Workforce, hiring, and layoff constraints All for t = 1,..., 6 Wt =W t–1 +Ht – Lt 2. Capacity constraints Pt £ 40Wt + Ot 4 3. Inventory balance constraints It–1 + Pt +Ct = Dt + St–1 + It – St 4. Overtime limit constraints Ot £10Wt
  • 24. Red Tomato Tools Constraints 1. Workforce, hiring, and layoff constraints All for t = 1,..., 6 Wt =W t–1 +Ht – Lt 2. Capacity constraints Pt £ 40Wt + Ot 4 3. Inventory balance constraints It–1 + Pt +Ct = Dt + St–1 + It – St 4. Overtime limit constraints Ot £10Wt
  • 25. Red Tomato Tools Average inventory = (I0 + IT ) / 2+ It t=1 T –1 å ( ) T = (I0 + IT ) / 2+ It t=1 T –1 å ( ) T é ë ê ê ê ù û ú ú ú Dt t=1 T –1 å ( ) T é ë ê ê ê ù û ú ú ú Average time in inventory
  • 26. Red Tomato Tools Total cost over planning horizon = $422,275 Revenue over planning horizon = 40 x 16,000 = $640,000 Period, t No. Hired, Ht No. Laid Off, Workforce Size, Wt Overtime, Ot Inventory, Stockout, Subcontract, Total Production, 0 0 0 80 0 1,000 0 0 1 0 15 65 0 1,983 0 0 2,583 2 0 0 65 0 1,567 0 0 2,583 3 0 0 65 0 950 0 0 2,583 4 0 0 65 0 0 267 0 2,583 5 0 0 65 0 117 0 0 2,583 6 0 0 65 0 500 0 0 2,583
  • 27. Red Tomato Tools = (I0 + I6 ) / 2+ It t=1 5 å ( ) T = 5,367 6 = 895 Average seasonal inventory Average flow time = 895 2,667 = 0.34 = 0.34 months
  • 28. Red Tomato Tools Higher demand variability Month Demand Forecast January 1,000 February 3,000 March 3,800 April 4,800 May 2,000 June 1,400 = (I0 + IT ) / 2+ It t=1 T –1 å ( ) T = 6,450 6 =1,075 Average seasonal inventory
  • 29. Red Tomato Tools Total cost over planning horizon = $432,858 Period, t No. Hired, Ht No. Laid Off, Workforce Size, Wt Overtime, Ot Inventory, Stockout, Subcontract, Total Production, 0 0 0 80 0 1,000 0 0 1 0 15 65 0 2,583 0 0 2,583 2 0 0 65 0 2,167 0 0 2,583 3 0 0 65 0 950 0 0 2,583 4 0 0 65 0 0 1,267 0 2,583 5 0 0 65 0 0 683 0 2,583 6 0 0 65 0 500 0 0 2,583 Average flow time = 1,075 2,667 = 0.40 months
  • 30. Red Tomato Tools Lower hiring and layoff costs = (I0 + IT ) / 2+ It t=1 T –1 å ( ) T = 2,500 6 = 417 Average seasonal inventory Average flow time = 417 2,667 = 0.16 months Total cost over planning horizon = $412,688
  • 31. Red Tomato Tools Period, t No. Hired, Ht No. Laid Off, Lt Workforce Size, Wt Overtime, Ot Inventory, It Stockout, St Subcontract, Ct Total Production, Pt 0 0 0 80 0 1,000 0 0 1 0 35 45 0 1,200 0 0 2,267 2 0 0 45 0 0 0 0 2,267 3 42 0 87 0 300 0 0 2,267 4 0 0 87 0 0 1,267 0 2,267 5 0 26 61 0 250 683 0 2,267 6 0 0 61 0 500 0 0 2,267
  • 32. Forecast Error in Aggregate Plans Forecast errors must be considered Safety inventory Safety capacity ◦ Use overtime as a form of safety capacity ◦ Carry extra workforce permanently as a form of safety capacity ◦ Use subcontractors as a form of safety capacity ◦ Build and carry extra inventories as a form of safety inventory ◦ Purchase capacity or product from an open or spot market as a form of safety capacity
  • 33. Aggregate Planning In Excel For t = 1, ..., 6 Wt = Workforce size for Month t Ht = Number of employees hired at the beginning of Month t Lt = Number of employees laid off at the beginning of Month t Pt = Production in Month t It = Inventory at the end of Month t St = Number of units stocked out at the end of Month t Ct = Number of units subcontracted for Month t Ot = Number of overtime hours worked in Month t
  • 38. Building a Rough Master Production Schedule Disaggregate an aggregate plan Family Setup Time/Ba ch (hour) Average Batch Size Production Time/Unit (hour) Production Quantity Number of Setup Time (hours) Production Time (hours) A 8 50 5.60 258 5 40 1,445 B 6 150 3.00 646 4 24 1,938 C 8 100 3.80 517 5 40 1,965 D 10 50 4.80 258 5 50 1,238 E 6 100 3.60 517 5 30 1,861 F 5 75 4.30 387 5 25 1,664
  • 39. The Role of IT in Aggregate Planning The ability to handle large problems The ability to handle complex problems (through either nonlinear optimization or linear approximations) The ability to interact with other core IT systems such as inventory management and sourcing
  • 40. Implementing Aggregate Planning Think Think beyond the enterprise to the entire supply chain Make Make plans flexible because forecasts are always inaccurate Rerun Rerun the aggregate plan as new data emerge Use Use aggregate planning as capacity utilization increases