The document presents information on two projects, Project S and Project L, including their costs, cash flows over 5 years, and expected returns calculated using NPV, IRR, MIRR, and PI at a 10% cost of capital. Based on the NPV, Project L would be selected. However, based on the IRR, Project S would be selected instead. The document asks which project should actually be selected.