Year(s) Project Name Project Cost Contractor Project Roll Owner Project Location Unique Condition
2007‐2008 Belle Terre Middle School/Wadsworth Elementary K‐8 Addition $
26,000,000 PPI Senior Project Manager Flagler County School District Palm Coast, FL Shared classroom building fit between 2 schools with shared kitchen & separate cafeterias
2007‐2008 Bunnell K‐8 Addition $
19,700,000 Barton Malow Senior Project Manager Flagler County School District Bunnell, FL 2 story classroom/office building & cafeteria/kitchen built on existing campus
2007‐2008 Rymfire 6‐8 Addition $
14,100,000 Barton Malow Senior Project Manager Flagler County School District Palm Coast, FL 2 story classroom building & gymnasium built on existing campus
2005‐2006 Rymfire Elementary School $
26,200,000 Barton Malow Senior Project Manager Flagler County School District Palm Coast, FL Completed project from foundations to occupancy in 7 months
2004‐2006 New 6‐12 School (Matanzas High School) $
60,000,000 Tower Group Senior Project Manager Flagler County School District Palm Coast, FL Original Design team let go and successor Design team took over
2004‐2008 Belle Terre Elementary School $
14,000,000 PPI Project Manager Flagler County School District Palm Coast, FL Came into project 4 months after construction started. Project completed under budget
2007 Wellness Center $ 1,000,000 KPI Project Manager Flagler County School District Palm Coast, FL Constructed building on active swim & tennis racquet club
2006 Youth Center $ 1,000,000 KPI Senior Project Manager Flagler County School District Bunnell, FL Built on existing active campus
2004 Port Authority Aviation Security Program $ 300,000,000 Project Manager Port Authority of NY & NJ New York City, NY Responsible for coordination and expedition of conceptualization design and implementation of Aviation Security projects
2003‐2004 Newark Airport P4 Parking Garage $ 106,000,000 Tishman Project Manager Port Authority of NY & NJ Newark Airport, NJ Took over Project Manager duties for last year of construction on the P4 parking garage
2003 Administration Building Landscaping $ 1,500,000 Tishman Assistant Project Manager Port Authority of NY & NJ Newark Airport, NJ Landscaping & memorial monument for Newark Airport Administration Building
2003 Demolition of Building 10 $ 2,000,000 Assistant Project Manager Port Authority of NY & NJ Newark Airport, NJ Demolition of old administration building located in middle of airfield at Newark Airport
2000‐2004 Newark Airport Redevelopment Program $ 780,000,000 Tishman/URS/Prismatic Project Manager Port Authority of NY & NJ Newark Airport, NJ Part of a 2 Billion program with Continental Airlines to upgrade facilities at Newark Airport
2000‐2003 Port Authority Administration & Aircraft Rescue Fire Fighting Building $
90,000,000 URS/Prismatic Assistant Project Manager Port Authority of NY & NJ Newark Airport, NJ Cut historic (1935) 35,000 sq‐ft building in 3 sections. Relocated building 1/4 mile away & constructed 60,000 sq‐ft addition
2000‐2003 Newark Airport Terminal A Relifing & Airline Modification $
60,000,000 Tishman Assistant Project Manager Port Authority of NY & NJ Newark Airport, NJ Worked with 5 different airlines to modify ticketing, baggage, gates, & support areas while keeping terminal operational
2000‐2001 Reconstruction of D Street $ 5,000,000 Assistant Project Manager Port Authority of NY & NJ Newark Airport, NJ Replacement of Paving & Utilities on Active Roadway leading to airfield access point at Newark Airport
2000 Two FAA Radio Transmission Buildings with Equipment $ 500,000 Tishman Assistant Project Manager Port Authority of NY & NJ Newark Airport, NJ Construct two hardened radio structures housed with FAA equipment
1999 Westside Highway Project $ 500,000,000 Perini Corporation Engineering Consultant City of NY New York City, NY Supervised tight sheeting installations for underground utility work adjacent to active roadways