SlideShare a Scribd company logo
1 of 2
Download to read offline
POST-TENSIONING/PRESTRESSING
(Photo: Plymouth University.)




                                                                                                                                Marine
                                                                                                                                Centre,
                                                                                                                                Plymouth




                                Marine Building, Plymouth                                                                elimination of construction loading on the tank at
                                University.                                                                              ground floor. This was to allow the installation and
                                                                 Richard Gaskill of Structural Systems
                                                                 Limited (SSL) looks at the post-tensioning              finishing works of the tank to proceed unhindered by the
                                                                                                                         construction above. This restriction ruled out traditional
                                                                 work carried out on a new marine research               in-situ formwork options and favoured a prefabricated
                                                                 facility building in Plymouth.                          off-site approach. The structural system decided upon
                                                                                                                         was precast post-tensioned beams spanning 16m with
                                                                                                                         secondary spanning 100mm-deep wide-slab precast
                                                                                                                         units incorporating a 125mm structural screed. The
                                                                   he £19 million marine building at Plymouth            beams are designed to work compositely with the

                                                             T     University will accommodate modern research
                                                                   facilities, including the most technically advanced
                                                             wave tank and testing facilities in Europe, capable of
                                                                                                                         structural screed in order to reduce the deflection which
                                                                                                                         was the critical design criterion.

                                                             simulating coastal and ocean environments, while            Designing the beams
                                                             generating currents and creating waves in excess of         The 32 beams are 500 × 750mm deep at mid-span,
                                                             1m high. Due to open in spring 2012, it will place the      reducing to 400 × 690mm deep some 3.4m from each
                                                             university as a global centre for marine energy research.   column, in order to accommodate a crane fixed to
                                                               Plymouth University is the largest in south-west          the underside of the beams. Each beam comprised
                                                             England and is one of the biggest employers in the          of two BBR CONA CMI 706 (ETAG 013- and BS EN
                                                             region. Investment in the marine building is being          13391-compliant(1–2)) bonded multi-strand anchors
                                                             part-funded by the South West Regional Development          with single-end stressing. Total prestress in the beams
                                                             Agency, Department of Business, Innovation and              was an average of 5MPa, which is close to the limit of
                                                             Skills, Department of Energy and Climate Change, and        allowable prestress for a structural concrete element.
                                                             the Higher Education Funding Council for England.           Even with this large amount of prestress, deflection was
                                                             The investment from BIS and DECC is part of £19.5m          still an issue with a final calculated long-term deflection
                                                             pledged to south-west England in 2009 to deliver the        of 80mm under dead and live loading. This deflection is
                                                             Low Carbon Economic Area initiative.                        outside normal construction tolerances and was taken
                                                                                                                         into special consideration when designing the internal
                                                             The ocean and coastal wave tanks                            partitions and details of equipment fixed to the floor.
                                                             Two giant 48 × 16m ocean and coastal wave tanks –              The long span and large deflections raised concerns
                                                             nearly the size of an Olympic swimming pool –– will         over the vibrational response of the floor under an
                                                             contain 225,000 litres of water and be suspended from       exciting force. A full-scale finite-element vibration
                                                             the floor above, making it one of the most complex and      analysis of the structure was undertaken by SSL and
                                                             exciting construction schemes in the south-west today.      confirmed a response factor of 3, which was acceptable to
                                                               Part of the client brief during construction was the      the building client for the intended use of the structure.


                                42   concrete          JUNE 2012 www.concrete.org.uk
POST-TENSIONING/PRESTRESSING


Right: Design development
  CAD images of one of the
   16m-span precast post-
         tensioned beams.




❝
                                 Lifting                                                         under the beam self weight. Under full-load stress,
                                 The beam reinforcement was fixed in a yard off-site             reversal took place and the tensile stresses in the bottom
                                 and cast in a custom-made steel mould. Using steel as           of the beam took on their maximum value.
The beams                        the formwork ensured a consistent finish to all beams,             The on-site column reinforcement was fitted with
weighed 13 tonnes                resulting in an aesthetically pleasing concrete. The            couplers at the underside level of the beam in order to
and were some                    beam was then lifted out of the mould and allowed to            receive H32 continuity reinforcement bars threaded
of the largest                   cure.                                                           through 6 × 60mm vertical ducts formed in the enlarged
precast beams to                    Once the concrete reached the required design                hammer head end section of the beam. A fitting
                                 strength the beam was stressed using a multi-strand             tolerance of 11mm horizontally was required in order
be used in building
                                 jack and stored in the yard until required on-site.             to achieve coupling of the column reinforcement. This
construction in                  Transporting the 16.3m beams to site was a logistical           is less than the typical construction allowance and was
the UK.



❞
                                 feat in itself and required a specialised trailer and a large   achieved by paying close attention to the short-term
                                 crane on-site to lift the beams into position. The beams        shrinkage characteristics of the prestressed concrete
                                 weighed 13 tonnes and were some of the largest precast          and fixing reinforcement in the yard and on-site to very
                                 beams to be used in building construction in the UK. In         tight tolerances.
                                 order to lift and place them onto the columns over the             Once the beams were lifted into place the underside
                                 50m building length a special high-load-capacity crane          of the beam was grouted to achieve a uniform bearing
                                 was imported from Asia.                                         surface. The bars were threaded and secured to the
                                                                                                 couplers and finally the ducts were grouted to secure the
                                                                                                 beam permanently in position.

                                                                                                 Supporting the beams
                                                                                                 Supporting the beams on a relatively small column
                                                                                                 width meant that the traditional recess provided for
                                                                                                 the multi-strand anchor interfered with the anchorage
                                                                                                 length for the support reinforcement. Placing the
                                                                                                 anchor-bearing plate on the external face of the beam
                                                                                                 removed the recess requirement but left the anchor
                                                                                                 exposed. The architect accepted the detail once a plastic
                                                                                                 end cap was sourced to minimise the impact of the
                                                                                                 protrusion on the building space.
                                                                                                   SSL (UK) also undertook the in-situ prestressing of
                                                                                                 two beams providing support for one of the suspended
                                                                                                 coastal tanks. The beams were 800 wide × 1000mm
                                                                                                 deep and carried the 300-tonne tank over a 16m span.
                                                                                                 These beams were cast in-situ at mezzanine level
                                                                                                 using traditional formwork construction. Use of two
                                                                                                 BBR CONA CMI 706 multi-strand anchors for each
                                                                                                 beam eliminated three layers of congested bottom
                                                                                                 reinforcement and provided a crack-free structure,
                                                                                                 increasing the durability and design life of the tank. ●




           Above: The beam          Design of the beam had to consider the different
   reinforcement and post-
  tensioning was fixed and
                                 permutations involved in the lifting process. The initial
      installed in an off-site   lift out of the mould occurred without the prestress
                                                                                                  References
     concrete precast yard.      applied so it was crucial that sufficient reinforcement
                                 was provided to enable this lift to occur without                1. EUROPEAN ORGANISATION FOR TECHNICAL APPROVALS, ETAG
                                 damaging the beam. During the lifting process for                   013. Guideline for European Technical Approval of Post-Tensioning
                                                                                                     Kits for Prestressing of Structures. EOTA, Brussels, 2002.
                                 transport to site the tensile stress in the top of the beam      2. BRITISH STANDARDS INSTITUTION, BS EN 13391. Mechanical
                                 was at its maximum due to the combined beam prestress               tests for post-tensioning systems. BSI, London, 2004.
                                 and the moment arising from the lifting point locations


44   concrete             JUNE 2012 www.concrete.org.uk

More Related Content

Similar to Marine Centre Plymouth

Substation Design - Anholt Offshore Wind Farm
Substation Design - Anholt Offshore Wind FarmSubstation Design - Anholt Offshore Wind Farm
Substation Design - Anholt Offshore Wind Farmpbnrambollcom
 
The management of the flood hazard of the River Derwent
The management of the flood hazard of the River DerwentThe management of the flood hazard of the River Derwent
The management of the flood hazard of the River DerwentA Hamill
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_agefyra-rion
 
IRJET- A Review on: Amphibious House
IRJET-  	  A Review on: Amphibious HouseIRJET-  	  A Review on: Amphibious House
IRJET- A Review on: Amphibious HouseIRJET Journal
 
Offshore cabeling: Cabling maintenance planning processes
Offshore cabeling: Cabling maintenance planning processesOffshore cabeling: Cabling maintenance planning processes
Offshore cabeling: Cabling maintenance planning processesTorben Haagh
 
Ppt report on offshore Platform Designs
Ppt report on offshore Platform DesignsPpt report on offshore Platform Designs
Ppt report on offshore Platform DesignsSUBHAM DEY
 
Evaluation of Mechanical Properties of Concrete Hollow Block Masonry Units
Evaluation of Mechanical Properties of Concrete Hollow Block Masonry UnitsEvaluation of Mechanical Properties of Concrete Hollow Block Masonry Units
Evaluation of Mechanical Properties of Concrete Hollow Block Masonry UnitsEditorIJAERD
 
Seismic retrofitting techniques of rcc
Seismic retrofitting techniques of rccSeismic retrofitting techniques of rcc
Seismic retrofitting techniques of rccKorrapati Pratyusha
 
IRJET- Design and Analysis of Floating Residence
IRJET- Design and Analysis of Floating ResidenceIRJET- Design and Analysis of Floating Residence
IRJET- Design and Analysis of Floating ResidenceIRJET Journal
 
Stonecutters island plant
Stonecutters island plantStonecutters island plant
Stonecutters island plantbumatech
 
7 - Planning of an Offshore Wind Farm in the Mediterranean Sea - Gkoumas
7 - Planning of an Offshore Wind Farm in the  Mediterranean Sea - Gkoumas7 - Planning of an Offshore Wind Farm in the  Mediterranean Sea - Gkoumas
7 - Planning of an Offshore Wind Farm in the Mediterranean Sea - GkoumasStroNGER2012
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter KyddThe Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter KyddSustainable Severn
 
IRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket StructureIRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket StructureIRJET Journal
 

Similar to Marine Centre Plymouth (20)

Final ppt of ts
Final ppt of tsFinal ppt of ts
Final ppt of ts
 
Substation Design - Anholt Offshore Wind Farm
Substation Design - Anholt Offshore Wind FarmSubstation Design - Anholt Offshore Wind Farm
Substation Design - Anholt Offshore Wind Farm
 
The management of the flood hazard of the River Derwent
The management of the flood hazard of the River DerwentThe management of the flood hazard of the River Derwent
The management of the flood hazard of the River Derwent
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_a
 
Tabs ppt
Tabs pptTabs ppt
Tabs ppt
 
IRJET- A Review on: Amphibious House
IRJET-  	  A Review on: Amphibious HouseIRJET-  	  A Review on: Amphibious House
IRJET- A Review on: Amphibious House
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 
Offshore Renewables
Offshore RenewablesOffshore Renewables
Offshore Renewables
 
Offshore cabeling: Cabling maintenance planning processes
Offshore cabeling: Cabling maintenance planning processesOffshore cabeling: Cabling maintenance planning processes
Offshore cabeling: Cabling maintenance planning processes
 
Ppt report on offshore Platform Designs
Ppt report on offshore Platform DesignsPpt report on offshore Platform Designs
Ppt report on offshore Platform Designs
 
Evaluation of Mechanical Properties of Concrete Hollow Block Masonry Units
Evaluation of Mechanical Properties of Concrete Hollow Block Masonry UnitsEvaluation of Mechanical Properties of Concrete Hollow Block Masonry Units
Evaluation of Mechanical Properties of Concrete Hollow Block Masonry Units
 
Seismic retrofitting techniques of rcc
Seismic retrofitting techniques of rccSeismic retrofitting techniques of rcc
Seismic retrofitting techniques of rcc
 
RINA_Paper
RINA_PaperRINA_Paper
RINA_Paper
 
IRJET- Design and Analysis of Floating Residence
IRJET- Design and Analysis of Floating ResidenceIRJET- Design and Analysis of Floating Residence
IRJET- Design and Analysis of Floating Residence
 
Stonecutters island plant
Stonecutters island plantStonecutters island plant
Stonecutters island plant
 
7 - Planning of an Offshore Wind Farm in the Mediterranean Sea - Gkoumas
7 - Planning of an Offshore Wind Farm in the  Mediterranean Sea - Gkoumas7 - Planning of an Offshore Wind Farm in the  Mediterranean Sea - Gkoumas
7 - Planning of an Offshore Wind Farm in the Mediterranean Sea - Gkoumas
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter KyddThe Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
The Severn Estuary - A sustainable low carbon energy resource - Peter Kydd
 
IRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket StructureIRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket Structure
 

More from rgaskill

Concrete, vol 47, June 2013 Tesco, Woolwich
Concrete, vol 47, June 2013 Tesco, WoolwichConcrete, vol 47, June 2013 Tesco, Woolwich
Concrete, vol 47, June 2013 Tesco, Woolwichrgaskill
 
Connect magazine article white city
Connect magazine article white cityConnect magazine article white city
Connect magazine article white cityrgaskill
 
Connect magazine st davids 2010
Connect magazine st davids 2010Connect magazine st davids 2010
Connect magazine st davids 2010rgaskill
 
Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011rgaskill
 
Excel london
Excel londonExcel london
Excel londonrgaskill
 
Triathlon
Triathlon Triathlon
Triathlon rgaskill
 
Connect magazine article the angel building
Connect magazine article the angel buildingConnect magazine article the angel building
Connect magazine article the angel buildingrgaskill
 
Westminster Bridge Plaza
Westminster Bridge PlazaWestminster Bridge Plaza
Westminster Bridge Plazargaskill
 
Structural strengthening Westfield
Structural strengthening WestfieldStructural strengthening Westfield
Structural strengthening Westfieldrgaskill
 

More from rgaskill (9)

Concrete, vol 47, June 2013 Tesco, Woolwich
Concrete, vol 47, June 2013 Tesco, WoolwichConcrete, vol 47, June 2013 Tesco, Woolwich
Concrete, vol 47, June 2013 Tesco, Woolwich
 
Connect magazine article white city
Connect magazine article white cityConnect magazine article white city
Connect magazine article white city
 
Connect magazine st davids 2010
Connect magazine st davids 2010Connect magazine st davids 2010
Connect magazine st davids 2010
 
Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011Connect magazine essex courts buildings 2011
Connect magazine essex courts buildings 2011
 
Excel london
Excel londonExcel london
Excel london
 
Triathlon
Triathlon Triathlon
Triathlon
 
Connect magazine article the angel building
Connect magazine article the angel buildingConnect magazine article the angel building
Connect magazine article the angel building
 
Westminster Bridge Plaza
Westminster Bridge PlazaWestminster Bridge Plaza
Westminster Bridge Plaza
 
Structural strengthening Westfield
Structural strengthening WestfieldStructural strengthening Westfield
Structural strengthening Westfield
 

Marine Centre Plymouth

  • 1. POST-TENSIONING/PRESTRESSING (Photo: Plymouth University.) Marine Centre, Plymouth Marine Building, Plymouth elimination of construction loading on the tank at University. ground floor. This was to allow the installation and Richard Gaskill of Structural Systems Limited (SSL) looks at the post-tensioning finishing works of the tank to proceed unhindered by the construction above. This restriction ruled out traditional work carried out on a new marine research in-situ formwork options and favoured a prefabricated facility building in Plymouth. off-site approach. The structural system decided upon was precast post-tensioned beams spanning 16m with secondary spanning 100mm-deep wide-slab precast units incorporating a 125mm structural screed. The he £19 million marine building at Plymouth beams are designed to work compositely with the T University will accommodate modern research facilities, including the most technically advanced wave tank and testing facilities in Europe, capable of structural screed in order to reduce the deflection which was the critical design criterion. simulating coastal and ocean environments, while Designing the beams generating currents and creating waves in excess of The 32 beams are 500 × 750mm deep at mid-span, 1m high. Due to open in spring 2012, it will place the reducing to 400 × 690mm deep some 3.4m from each university as a global centre for marine energy research. column, in order to accommodate a crane fixed to Plymouth University is the largest in south-west the underside of the beams. Each beam comprised England and is one of the biggest employers in the of two BBR CONA CMI 706 (ETAG 013- and BS EN region. Investment in the marine building is being 13391-compliant(1–2)) bonded multi-strand anchors part-funded by the South West Regional Development with single-end stressing. Total prestress in the beams Agency, Department of Business, Innovation and was an average of 5MPa, which is close to the limit of Skills, Department of Energy and Climate Change, and allowable prestress for a structural concrete element. the Higher Education Funding Council for England. Even with this large amount of prestress, deflection was The investment from BIS and DECC is part of £19.5m still an issue with a final calculated long-term deflection pledged to south-west England in 2009 to deliver the of 80mm under dead and live loading. This deflection is Low Carbon Economic Area initiative. outside normal construction tolerances and was taken into special consideration when designing the internal The ocean and coastal wave tanks partitions and details of equipment fixed to the floor. Two giant 48 × 16m ocean and coastal wave tanks – The long span and large deflections raised concerns nearly the size of an Olympic swimming pool –– will over the vibrational response of the floor under an contain 225,000 litres of water and be suspended from exciting force. A full-scale finite-element vibration the floor above, making it one of the most complex and analysis of the structure was undertaken by SSL and exciting construction schemes in the south-west today. confirmed a response factor of 3, which was acceptable to Part of the client brief during construction was the the building client for the intended use of the structure. 42 concrete JUNE 2012 www.concrete.org.uk
  • 2. POST-TENSIONING/PRESTRESSING Right: Design development CAD images of one of the 16m-span precast post- tensioned beams. ❝ Lifting under the beam self weight. Under full-load stress, The beam reinforcement was fixed in a yard off-site reversal took place and the tensile stresses in the bottom and cast in a custom-made steel mould. Using steel as of the beam took on their maximum value. The beams the formwork ensured a consistent finish to all beams, The on-site column reinforcement was fitted with weighed 13 tonnes resulting in an aesthetically pleasing concrete. The couplers at the underside level of the beam in order to and were some beam was then lifted out of the mould and allowed to receive H32 continuity reinforcement bars threaded of the largest cure. through 6 × 60mm vertical ducts formed in the enlarged precast beams to Once the concrete reached the required design hammer head end section of the beam. A fitting strength the beam was stressed using a multi-strand tolerance of 11mm horizontally was required in order be used in building jack and stored in the yard until required on-site. to achieve coupling of the column reinforcement. This construction in Transporting the 16.3m beams to site was a logistical is less than the typical construction allowance and was the UK. ❞ feat in itself and required a specialised trailer and a large achieved by paying close attention to the short-term crane on-site to lift the beams into position. The beams shrinkage characteristics of the prestressed concrete weighed 13 tonnes and were some of the largest precast and fixing reinforcement in the yard and on-site to very beams to be used in building construction in the UK. In tight tolerances. order to lift and place them onto the columns over the Once the beams were lifted into place the underside 50m building length a special high-load-capacity crane of the beam was grouted to achieve a uniform bearing was imported from Asia. surface. The bars were threaded and secured to the couplers and finally the ducts were grouted to secure the beam permanently in position. Supporting the beams Supporting the beams on a relatively small column width meant that the traditional recess provided for the multi-strand anchor interfered with the anchorage length for the support reinforcement. Placing the anchor-bearing plate on the external face of the beam removed the recess requirement but left the anchor exposed. The architect accepted the detail once a plastic end cap was sourced to minimise the impact of the protrusion on the building space. SSL (UK) also undertook the in-situ prestressing of two beams providing support for one of the suspended coastal tanks. The beams were 800 wide × 1000mm deep and carried the 300-tonne tank over a 16m span. These beams were cast in-situ at mezzanine level using traditional formwork construction. Use of two BBR CONA CMI 706 multi-strand anchors for each beam eliminated three layers of congested bottom reinforcement and provided a crack-free structure, increasing the durability and design life of the tank. ● Above: The beam Design of the beam had to consider the different reinforcement and post- tensioning was fixed and permutations involved in the lifting process. The initial installed in an off-site lift out of the mould occurred without the prestress References concrete precast yard. applied so it was crucial that sufficient reinforcement was provided to enable this lift to occur without 1. EUROPEAN ORGANISATION FOR TECHNICAL APPROVALS, ETAG damaging the beam. During the lifting process for 013. Guideline for European Technical Approval of Post-Tensioning Kits for Prestressing of Structures. EOTA, Brussels, 2002. transport to site the tensile stress in the top of the beam 2. BRITISH STANDARDS INSTITUTION, BS EN 13391. Mechanical was at its maximum due to the combined beam prestress tests for post-tensioning systems. BSI, London, 2004. and the moment arising from the lifting point locations 44 concrete JUNE 2012 www.concrete.org.uk