Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Economics of public procurements ippc paper
1.
2. The Economics of Public Procurement on
Infrastructure Projects Delivery in
Developing countries: A case study of
Central Bank of Nigeria
By
Shuaib, M.R.
Quantity Surveying Programme, School of Environmental
Technology, Abubakar Tafawa Balewa University Bauchi,
Nigeria.
3. Central Bank of Nigeria (CBN) can be seen
as one of the biggest construction clients in
Nigeria.
Total Contract value of CBN capital projects
between 2005-2014 is over 1 billion USD
Procurement strategy
4. Design Precedes Construction
Consultants appointed by the client
Contractor engaged based on consultants
recommendation
5. Bases on which Bureau of Public
Procurement and National Council on Public
procurement was established
Served as a legislation guide on how public
funds should be expended
6. These laws provides room for proper
delivery of projects covering
conceptualization, planning , design and its
implementation
They also give opportunity(s) for award of
contract with due diligence and procedure.
All procuring entity (PE) to adhere to the
public procurement Act provision.
7. PP-Act 2007 is set to achieve the following
objectives:
Economy and Efficiency
Competition – providing level playing
ground for all strata of bidders
Achieve Value for Money
Enhance Transparency
8. The purpose of this paper is to observe and
explore the efficacy of CBN’s traditional
procurement success on capital projects
based on the provision of procurement Act of
2007.
9. CASE STUDY ‘A’ CBN Branch office project
Katsina, Kastina State, Nigeria.
CASE STUDY ‘B’ CBN Branch office project
Abakiliki, Ibonyi State, Nigeria.
10. Could the success or otherwise of these
projects be associated with the choice of the
procurement method used?
Are there other factors that could be tied to
the achievement or otherwise of the
projects objectives?
Is there efficiency in the implementation
process of the PPA 2007 laws and guidelines
on these projects?
11. The method used in this research was
Focused Group Discussions (FGDs) where
data was collected and analysed using
funnel approach starting from the general to
specific.
The level of confidence was determined as
one from the discussions held amongst the
supply chain participants on CBN projects.
12. Textbooks, PPA 2007 document, academic
journals articles and reports on
procurement were some of the primary
source of data obtained.
13. Ensued discussions with stakeholders on each
projects covering:
CBN traditional procurement method
Compliance to PPA 2007 principles and
guidelines
Why CBN projects are not completed within
time and budget.
14. CBN BRANCH OFFICE PROJECT ABAKILIKI,
IBONYI STATE.
To provide quality banking structure and
easy access to banking services
Awarded in November 2010
Completion period 104 weeks (November
2012)
Contract sum - N 7,1billion (33million Euro)
15. Project status - Ongoing
Time overruns to date - 92 weeks
Actual progress to date – 71%
Projected completion date – May, 2015
Projected time overruns – 130 weeks
No major additional work on the project
16. At Pre-contract stage, the following
information were made available prior to
tender action.
Drawings were substantially completed, but
many issues on services were not detailed.
Bill of quantity
There was advertisement, prequalification
exercise, tendering procedure before award.
17. At post-contract stage, the following issues
were identified as major setbacks.
Delay in all clients supply items
Inability of the contractor to work according
to programme of work
Incomplete services drawings even upon
engagement of the PC Items subcontractors
Lack of requisite knowledge, skills and
experience of the specialist subcontractors
18. CBN BRANCH OFFICE PROJECT KATSINA,
KATSINA STATE, NIGERIA.
To provide quality banking structure and
easy access to banking services
Awarded in February 2006
Completion period 104 weeks ( February
2008)
Contract sum - N 4.409 billion (20 million
Euro)
19. Project Status - Completed and handed over
Time overruns – 12 months
Approximate Cost overruns – N1.0m (4.5m
Euro)
Drawings were completed before tender.
Bill of quantity was also completed
There was advertisement, prequalification
exercise, tendering procedure before award.
20. At post-contract stage, the following issues
were identified as major setbacks.
Delay in all clients supply items
Inability of the contractor to work according
to programme of work
21. None of the two CBN projects achieved its
set objectives
The projects were efficiently
conceptualized, properly planned and
adequately designed but implementation
was faulty.
Late engagement of PC item subcontractors
Delay in delivery of client’s supply items to
site
22.
23. There was compliance to public procurement
principles in terms of:
Conceptualization, proper planning and
adequate design of both projects.
Advertisement, prequalification and
tendering process and award.
There were level ground for different strata
of contractors who bid for the contracts.
24. But Implementation was faulty
Cost and timely completion have not been
achieved hence, value for money.
On the whole, the core objectives of the public
procurement Act 2007 was partially achieved
on both projects.