3. MATERIAL & TOOL LIST:
• 1 pc of 2 x 10 x 5’ per student in the group
• Scraps of ½” plywood or OSB and scraps of 1½” thick stock
• Scrap piece of 2 x 4 and ¾” or ⅝” plywood
• Framing Square & stair gauges
• Tape Measure and pencil
• Circular saw & hand saw
• Hammer & nails or driver & screws
ACCE
4. ASSIGNMENT #1:
Click on the speaker icon on slide #1 for audio instructions
Complete the stair calculations on the next slide
Each group member must cut his or her own carriage
Replace the photos in the remaining slides with photos of your
project at each stage of construction
Each group member will take a photo with his or her completed
carriage - signed and labelled
ACCE
5. STAIR CALCULATIONS:
1. Total Rise = 3’ 2⅛” = ________________” ( Given)
2. # of rises = _______________________ = _________.
3. Unit Rise = ________________________ = _________.
4. Unit Run = ________________________ = _________.
5. Tread width = _____________________ = _________.
6. # of Runs = _______________________ = _________.
7. Total Run = _______________________ = _________.
ACCE