SlideShare a Scribd company logo
1 of 3
Download to read offline
ECONOMICS
analysis / facts / forecast


                                                                                                                                                                       “waste to energy entrepreneurs”             teamed up, with a proposal for a          efficient, large schemes with the         planning will continue to be
                                                                                                                                                                       investing in capacity to secure             hi-tech, plasma arc gasification          capacity to treat the waste for a         contentious and high risk.
                                                                                                                                                                       long-term management contracts.             plant to produce aviation fuel.           consortium of WDAs are difficult            Due to high operating costs,
                                                                                                                                                                       Grundon and Viridor, for example,             Perhaps the most critical               to get through planning.                  government incentives including

COST MODEL ENERGY FROM WASTE                                                                                                                                           developed a speculative plant
                                                                                                                                                                       near Heathrow that has enabled
                                                                                                                                                                       them to secure long-term
                                                                                                                                                                                                                   stakeholder in UK energy from
                                                                                                                                                                                                                   waste policy is the general public,
                                                                                                                                                                                                                   which is antagonistic to some
                                                                                                                                                                                                                                                               While very large schemes in
                                                                                                                                                                                                                                                             excess of 50MW will fall within
                                                                                                                                                                                                                                                             the remit of the Infrastructure
                                                                                                                                                                                                                                                                                                       landfill tax, Renewable Obligation
                                                                                                                                                                                                                                                                                                       Certificates (ROCs) and feed-in
                                                                                                                                                                                                                                                                                                       tariffs will play a critical role in
                                                                                                                                                                       contracts with WDAs in the M4               waste management projects.                Planning Commission, this                 underpinning the economics of
There are almost as many treatment solutions as sources of waste. Simon Rawlinson and                                                                                  corridor. BA and Solena have also           Opposition is such that more              applies to few schemes, so                schemes.
Matthew Hicks of Davis Langdon weigh up the costs and the risks of options, including incineration
                                                                                                                                                                       03 / POTENTIAL BENEFITS OF ENERGY FROM WASTE SCHEMES
01 / INTRODUCTION                                                                                                                                                      Energy from waste projects need to be considered       I Waste bulk reduction. Incineration will typically     450-600kWh per tonne are possible through a
                                                                                                                                                                       as part of the wider waste management hierarchy,       reduce waste bulk by 60 to 70%, and some waste          steam turbine generator
The UK produces over 300 million tonnes of            due to landfill tax and higher gate prices, and are   encourage reduction of waste at source and by              but the UK produces more waste than can be             products may also be recyclable as aggregates           I Energy security. Waste-based energy will reduce
waste a year, 24% of which is derived from            also looking for alternatives to landfill. Waste      recycling. However, there are physical and                 effectively recycled and bulk reduction techniques     I Stabilisation of landfill. The bulk of the residual   UK dependence on imported energy sources
household or commercial sources. Historically,        disposal authorities face fines of £150/tonne if      economic limits to recycling, and few waste                such as incineration are needed to reduce waste        waste stream – bottom ash or vitrified waste – is       I Long term cost reduction. Incineration will help to
most domestic waste has been directed to              they miss their 2013 and 2020 landfill targets, a     disposal authorities (WDAs) expect to be in a              volumes. The main benefits of processes such as        stable and does not emit methane                        mitigate rising costs related to high gate prices and
landfill, and on current disposal rates, the UK has   policy which is driving waste-related investment      position to recycle more than 65% of their solid           incineration are:                                      I Energy production. Conversion rates of                rising landfill tax.
less than 10 years’ supply of landfill left.          worth £9-11bn for the public sector alone             waste stream. Unlike Europe, where incineration
  Challenging EU targets for the reduction of         between now and 2020. This is equivalent to           is well established, energy from waste is
disposal of domestic waste to landfill have           an extra 500 million tonnes of treatment              unpopular in the UK. However, with much tighter            Energy from waste as a means of treatment is
belatedly triggered a PFI market in waste             capacity per year.                                    regulation, improved technology and the growing            preferable to the last resort of landfill
recycling and treatment. Commercial waste               Government policy, articulated through the          risk of a UK energy gap, waste’s potential as a
producers have also experienced rising costs          “waste hierarchy” (see diagram below) is to           resource is now being warmly embraced.



02 / THE UK WASTE INDUSTRY
The UK waste sector is                  However, there will continue to be       evolving very quickly in an effort     tasked with reducing their
surprisingly diverse. The waste         a surplus, and energy from waste         to increase efficiency, deal with a    landfill related to biodegradable
stream is inevitably varied and         as a means of treatment is               wider range of waste streams and       municipal waste, commercial
requires different treatment and        preferable to the last resort of         to increase safety. Defra, for         waste users who want to reduce
disposal regimes. Within the            landfill.                                example, has recently provided         disposal costs, and energy users
municipal and commercial waste            Materials recovery and                 support to the development of          looking for diversified sources.
streams, there are a large number       mechanical and biological                advanced thermal techniques            There are 40 waste management
of players. Commercial                  treatment processes (MBT) sit            (ATT) such as pyrolysis.               PFIs in the UK, many of which
organisations are responsible for       above energy from waste in the             Parties involved in energy from      involve elements of energy
contracting their own waste             hierarchy and can produce fuels          waste include WDAs who are             generation, as well as a group of
disposal. In the public sector,         that can be sold on to energy
there are a host of waste               users. Solid recovered fuel is a
collection and waste disposal           product of MBT processes and, in                                           MINIMISE
authorities, as well as health          some cases, can be burned
trusts and education authorities        without treatment of flue gases.
who are responsible for their own         Energy from waste itself is
waste management. This means            an umbrella term describing
schemes may have to                     technologies used to extract the                                            REUSE
accommodate a very varied               chemical energy locked in waste
feedstock. Restrictive planning         products. Energy from waste
concessions may also limit the          techniques include thermal
sources of waste a particular           processes such as incineration, as
scheme can treat – limiting             well as a range of thermal or                                              RECYCLE
economies of scale and long-term        chemical gasification techniques
flexibility in the use of a facility.   that produce gas and liquid fuels.
  Based on the waste hierarchy            The portfolio of energy from
(see diagram, right), much              waste techniques also includes
                                                                                                                   RECOVER
investment has been targeted at         aspects of pre-treatment required                                           ENERGY
minimising the volume of waste          for biological processes such as
requiring disposal. Projects            anaerobic digestion, as well as
managed by the Waste Resource           the treatment of flue gases and                                            LANDFILL
Action Programme (Wrap) are             other by-products of the
                                                                                                                                                               ALAMY




good examples of the holistic           conversion process. Technologies
approach adopted in the UK.             used are proprietary and are

23.04.2010 BUILDING MAGAZINE
56 / economics / cost model                                                                                                                                                                                                                                                                economics / cost model / 57




                                                                                                                                                                       particularly those related to safe operation.           of lower than expected throughput is increased           Many of the risks relate to the effective operation
                                                                                                                                                                       According to Wrap, total costs of disposal via          unit costs. Lower waste conversion rates will            of plant, which makes innovation particularly
04 / ENERGY FROM WASTE TECHNOLOGIES                                                                                                                                    energy from waste range from £65 to £136/tonne.         increase cost related to landfill tax liabilities.       difficult to deliver – especially in smaller schemes
                                                                                                                                                                         In terms of operating costs, the main areas of risk                                                            that have a limited range of treatment processes.
                                                                                                                                                                       involve throughput, energy prices, the operating        Additional cost and value drivers                        There are a number of high-profile projects where
Outside the UK a range of                 treatment for energy from waste.          also reuse waste heat through           oils can potentially be used as a          and maintenance regime and the costs of disposal        Most value drivers associated with energy from           timescales and quality standards have not been
technologies have been in use for         However, they differ in the way           large-scale community CHP               bio-fuel, although currently the           of waste products. Replacement cost of plant also       waste are related to scale of operation, which is        met, and where testing and commissioning has
a long time, but very few have a          the energy value of residual              systems. Unfortunately, due to          only use is for electricity                has to be factored into the model. The implication      difficult to optimise due to planning constraint.        taken significantly longer than anticipated.
track record with the UK’s mix of         waste is increased and in the             the unpopularity of incineration,       generation using a CHP.
waste. With pressure on to have           quality of fuel produced.                 finding locations next to heat            Unlike incineration, both
waste treatment plant in place to         Production of solid recovered             users is very difficult.                gasification and pyrolysis                 06 / ADDITIONAL COST AND VALUE DRIVERS
meet the 2013 landfill deadline,          fuel via MBT or MHT gives                   The most common incineration          require pre-processing of waste
momentum is with incineration.            WDAs the option to sell on their          technology is moving grate              material. They also produce flue
However, looking forward to               recyclate without committing to           combustion. A potentially more          gases that require treatment.
2020 targets and long-term PFI            develop a dedicated energy from           efficient combustion technique,           Another emerging technology is           VALUE                                                                                RISK
deals, more advanced solutions            waste scheme.                             fluidised bed combustion, requires      plasma arc gasification. This
may be adopted.                             Incineration is the most                pre-sorting and shredding of the        involves passing waste into a              Mitigation of long-term costs to the WDA Energy from waste projects                  Certainty of availability End users need assurance that the proposed plant
  There are other sets of waste           established waste technology in           waste feedstock. Relatively few         kiln at 4,000-7,000˚C. Gases               eliminate risks of exposure to penalties from the Landfill Allowance Trading         will deliver the expected waste throughput and waste bulk reduction within
treatment techniques, including           the UK, treating over 4,000,000           of these plants are in operation.       released are collected, and any            Scheme relating to landfill disposal in excess of allowances.                        strict emissions levels and timescales.
MBT and mechanical heat                   tonnes per year. In energy from           Although well established,              waste products are immobilised
treatment (MHT) that often form           waste schemes, the heat from the          moving grate technology has             in a vitrified mass that can be            Risk transfer through procurement Turnkey procurement via PFI or a                   Certainty of delivery Where the project delivers useable output such as a
part of a PFI. Both include a             process is used in a steam                significant complexities                safely disposed of. Plasma arc             treatment contract enables clients to secure large-scale investment and to           syngas or solid recovered fuel, assurance of product quality is critical.
proportion of materials recovery          turbine to generate electricity for       associated with the optimisation        gasification promises much, but            outsource project delivery and operational risks.
from the general waste stream             the National Grid. Some projects          of combustion, reuse of energy          with few “reference” plants to                                                                                                  Project delivery Risks include integration and co-ordination of complex and
and could be used as a pre-               such as Sheffield and Teesside            and the need to meet extremely          confirm performance, adoption              Minimisation of social impacts including vehicle movements, where this can           distinct technologies for pre-treatment, combustion, flue gas treatment and
                                                                                    stringent flue gas standards.           in Europe will be gradual.                 be achieved using existing infrastructure such as rail.                              the grid connection. Site constraints to the plan or building height may limit
                                                                                    Flue gas cleaning can add                 Anaerobic digestion is a                                                                                                      the proprietary technologies that can be used in a particular location.
                                                                                    between 30% and 60% to the              biological process for the                 Economies of scale Energy from waste schemes are most cost effective
                                                                                    capital cost of the equipment.          organic portion of municipal               with a throughput in excess of 350,000 tonnes a year. For larger projects it         Planning risks Planning challenges include health concerns, traffic
                                                                                      ATT processes use heat and            solid waste. Advantages include            is claimed that doubling the throughput of a scheme only results in a cost           movement and the visual impact of a development that can include a 90m
                                                                                    pressure to extract gases and           scalability and low running                increase of 50%. Other benefits of scale include reduced land-take and               high stack. Planning consents may involve restrictions on operations such as
                                                                                    oils from waste materials.              costs. Implementation issues               higher operational efficiencies.                                                     limits on where waste can be sourced from. Other risks include delays in the
                                                                                    Gasification uses a temperature         include waste preprocessing,                                                                                                    planning process for overhead power line connections.
                                                                                    of about 750˚C and releases             and disposal of the non-organic            Recovery of value from the waste stream including heat energy and
                                                                                    useable hydrogen and methane            waste and the residual                     recyclates such as aggregate or solid waste fuel.                                    Project delivery Guarantees that transfer risk related to the availability and
                                                                                    as well as carbon monoxide.             “digestate”. Defra is promoting                                                                                                 quality of feedstock and the availability and performance of the technology
                                                                                      Pyrolysis takes place at a lower      development of anaerobic                   Quality of the business case, including good quality information, use of             will also improve viability – so long as the warranties are enforceable.
                                                                                    temperature, 300-800˚C, under           digestion capability in the UK             well-established technologies and extensive scenario modelling.
                                                                                    pressure and in the absence of          and more than 10 large-scale                                                                                                    Co-ordination of programme delivery Projects that involve a number of
                                                                                    oxygen. The process is designed         schemes are in development. The            Accurate estimation of the quality and volume of the waste stream, so that           technologically distinct but closely related components need effective
                                                                                    to extract a greater calorific          long-term vision is that bio-fuels         plant operates effectively.                                                          programme management.
                                                                                    value than gasification and will        from anaerobic digestion and
                                                                                    produce a combination of gases,         ATT will be used as part of the            Diversification of waste management processes to include waste reduction             Technology risk associated with complex processes Each new feature
                                                                                    oils and waxes. The gases and           natural gas or liquid fuel supply.         and recovery. Materials recovery and composting are cheaper and more                 incorporated to reduce emissions or increase energy recovery contributes to
                                                                                                                                                                       environmentally desirable than combustion. Larger projects that enable a             this risk.
                                                                                                                                                                       range of techniques to be cost effectively included in the treatment mix
05 / COST AND VALUE DRIVERS                                                                                                                                            should deliver optimum outcomes.                                                     Supply and demand risk Reference projects with an extended track record
                                                                                                                                                                                                                                                            of operation with a UK waste stream are important business case evidence
                                                                                                                                                                       Diversification of sources of waste – dealing with commercial and municipal          for both end-user clients and funders.
Energy from waste projects are typically procured       End user requirements Project sponsors such as        energy and by-products such as aggregates. The           waste streams together improves economies of scale and certainty of
on a build-own-operate basis, with operational and      WDAs have been in competition for scarce waste        waste gate price, currently about £60 to                 waste supply.                                                                        Viability risk related to the long-term value of incentives such as landfill tax
commercial risks being taken by a waste                 management expertise and private finance. In          £90/tonne, has increased substantially with the                                                                                               and ROCs.
consortium. The economics of energy from waste          practice, larger WDAs are in a stronger position to   support of landfill tax and typically contributes        Continuing incentivisation of waste reduction and recovery strategies.
schemes are subject to many sources of risk and         determine preferred solutions than smaller            70% of income. Certainty with regards to the                                                                                                  Supply risk associated with the volume, quality and consistency of the waste
uncertainty, so although a scheme will usually be       authorities who have in some cases struggled to       continuation of the landfill tax accelerator is an                                                                                            stream.
set up with a guaranteed feedstock source, overall      attract operator interest. Other areas where          important consideration for operators and investors.
viability will be subject to a wide range of pricing,   end-user requirements might affect the project          Depending on the technologies adopted, there                                                                                                Demand risk related to markets for recyclates such as solid recovered fuel
deliverability and performance risks. Combined with     design include the consistency of the waste           may be additional income streams related to              In summary, the risk exposure on energy to waste projects is relatively              as well as waste heat, and the prices that can be obtained for these
the requirement to secure very large values of          feedstock they can provide. Projects serving a        exported heat energy as well as income from              high – particularly for emerging technologies. Turnkey contracts are an              products.
private finance, this level of risk exposure tends to   consortium of WDAs will need to be designed to        incentives such as ROCs.                                 important mechanism to enable these complex interrelated risks to be
favour the use of well established technologies and     deal with a less consistent waste stream, with a      Costs Energy from waste schemes need                     packaged in such a way as the main objective of optimising the use of                Political risk for end users of commitment to energy from waste if incentive
solution providers.                                     consequent impact on efficiency.                      substantial investment in pre-treatment and grid         waste as a resource is met. This concentration of risk will inevitably result        to recycle is reduced.
  The main variables affecting energy from waste        Income The main sources of income are the gate        connection infrastructure, as well as land and main      in a risk premium which can be mitigated to an extent by giving suppliers
viability are as follows:                               price for the waste stream and the sale price of      generator plant. Operating costs are also substantial,   freedom over the application of technologies.

23.04.2010 BUILDING MAGAZINE                                                                                                                                                                                                                                                                                BUILDING MAGAZINE 23.04.2010
economics / cost model / 59




                                                                                                                                                                          08 / COST MODEL
                                                                                                                                                                          The cost model provides outline costs of the                  Details of the scope of external works are
                                                                                                                                                                          building facilities associated with a 600,000                 included as these are a critical element of the
                                                                                                                                                                          tonne a year combustion plant based on a                      operation of the facility.
                                                                                                                                                                          three-line moving grate technology. The                         Site preparation costs, client-side professional
                                                                                                                                                                          analysis also provides indicative costs of the                fees and VAT are excluded.
                                                                                                                                                                          combustion system and the grid connection.




                                                                                                                                                                          A / COST BREAKDOWN
                                                                                                                                                                                                                             £                £/m2 GIFA        %                                                         £               £/m2 GIFA         %


                                                                                                                                                                          Temporary works                               1,650,000              64.71           2.00   Protection installations, lightning protection and earthing and bonding, complete,
                                                                                                                                                                          Allowance for temporary works, item @ £1,650,000                                            item @ £480,000
                                                                                                                                                                                                                                                                      Protection installations, fire detection, alarm and supression systems 25,500m3 @
                                                                                                                                                                          Building shell                                34,811,600         1,365.16         46.42     £80
                                                                                                                                                                          Piling, pilecaps and ground beams, generally 11,000m2 @ £460                                Lift and conveyor installations, very heavy duty goods and passenger lifts serving
                                                                                                                                                                          Extra for base to air-cooled condenser 2,150m2 @ £150                                       seven levels, item @ £2,750,000
                                                                                                                                                                          Extra for stack base, item @ £330,000                                                       Special installations, crane and hoist installation, including crane rails, item @
                                                                                                                                                                          Floor slabs, typically 500 thick insitu concrete, below ground drainage 11,000m2 @          £300,000
                                                                                                                                                                          £185                                                                                        Special installations, building mangement and energy management systems, item @
                                                                                                                                                                          Feedstock and bottom ash storage bunkers complete, retaining walls, internal walls,         £910,000
                                                                                                                                                                          floor slabs, etc. (rate based on footprint area) 1,485m2 @ £3,650
                                                                                                                                                                          Insitu concrete frame and upper floor construction to tipping hall, including full          Ancillary building works                      2,640,500            103.55            3.52
                                                                                                                                                                          height shear wall structures (rate based on footprint area) 2,835m2 @ £1,280                HGV access ramp complete, including substructure, structure, road surface and
                                                                                                                                                                          Insitu concrete frame and upper floor construction to boiler, turbine and flue gas          safety barriers, item @ £2,150,000
                                                                                                                                                                          treatment hall, including full height shear wall structures (rate based on footprint        Allowance for gatehouses and weighbridges, item @ £375,000
                                                                                                                                                                          area) 4,500m2 @ £270                                                                        Allowance for fuel and chemical storage – foundations, interceptors, etc., item @
                                                                                                                                                                          Structural steelwork to building including long span curved trusses to roofs and            £115,500
                                                                                                                                                                          framing to process plant, stairs and access platforms (rate based on gross internal
                                                                                                                                                                          floor area) 25,500m2 @ £400                                                                 External works                                5,540,000            217.25            7.39
                                                                                                                                                                          Cladding and roofing. Flat-panel cladding panels, feature glazing, aluminium louvres,       Site preparation, generally, item @ £310,000
                                                                                                                                                                          raised seam roofing on structural deck and secondary steelwork curved to profile,           Roads and hardstandings, including traffic control systems, item @ £1,110,000
                                                                                                                                                                          roof lights, rainwater disposal, architectural cladding to stack (rate based on gross       Security fencing and gates, item @ £230,000
                                                                                                                                                                          internal floor area) 25,500m2 @ £220                                                        Drainage installations, complete, item @ £840,000
                                                                                                                                                                          Allowance for blockwork partitions and cladding lining, item @ £645,000                     External services, incoming HV supply, site water infrastructure, item @
                                                                                                                                                                          Allowance for doors and windows, item @ £345,000                                            £3,050,000
The Lakeside energy from waste plant at Colnbrook, Berkshire, is one of the few to have been                                                                                                                                                                          Preliminaries and contingencies               16,734,900           656.27        22.31
approved by planners                                                                                                                                                      Finishing and fit-out works                   1,830,000              71.76           2.44   Contractor's management, site establishment and site supervision. Allow 17% @
                                                                                                                                                                          Allowance for surface finishes, item @ £1,300,000                                           £9,836,700
                                                                                                                                                                          Allowance for partitions, finishes and fittings to offices, workshops, staff facilities     Contractors EPC design fees for building only. Allow 6% @ £3,500,000
                                                                                                                                                                          and laboratories, item @ £530,000                                                           Design reserve. Allow 5% @ £3,398,200
07 / PROCUREMENT
                                                                                                                                                                          Building services installation                11,793,000           462.47         15.72     Total construction cost – building only       75,000,000         2,941.17       100.00
Delivery of energy from waste projects is an              different solutions to be considered as part of the    purpose vehicle. SPV projects are typically              Plumbing and sanitary installation, complete, item @ £130,000
extended process, typically taking seven to 10            bidding process. Unfortunately this increases the      delivered to the service operator via an                 Mechanical services installation. Heating and ventilation including closed cycle            Turnkey technology contracts                  230,000,000        9,019.61
years. In the current market, there are many WDAs         costs of all parties. Recently, smaller authorities    engineering, procurement and construction (EPC)          ventilation system with negative pressurisation and odour abatement to tipping hall         Indicative cost of 600,000 tpa incineration and energy from waste installation, with
seeking to secure relatively scarce technological         have had difficulties in attracting compliant bids.    contract. The operator’s risk can be minimised by        and waste hoppers. Heating and air conditioning systems to offices and workshops.           planned net electricity output of 65MWe, item @ £220,000,000
and project delivery resources, and as a result, the        Private finance is more costly in the waste sector   wrapping all aspects of the capital works –              Dedicated extract systems. Hot and cold water installations. 25,500m2 @ £150                Indicative cost of National Grid connection, item @ £10,000,000
packaging of the project will be critical in attracting   than some other PFI streams because of the range       pre-treatment, main plant and grid connection            Electrical installations, substation, including associated building works, item @
interest from bidders and from PFI financiers.            of risks involved. The costs of large “back-end”       infrastructure – into a single EPC deal. However,        £440,000                                                                                    Total construction cost – building only       30,000,000           14,902 11,960.78
  Some major issues in procurement deal with              projects, such as incinerators, are such that since    these arrangements add significantly to costs            Electrical installations, HV installation, lighting and emergency lighting, small power
attracting the most appropriate bidders in the first      the loan syndication market collapsed in 2007,         related to fees, management resource and risk            and power supply to building services installations 25,500m2 @ £36
place, obtaining finance and devising the most cost       funding has been more difficult to arrange through     premium. An “unwrapped” approach, where the
effective project delivery mechanism in order to          “clubs” of lending institutions. The Manchester        SPV takes a more direct role in managing risk, may
integrate the major elements of technology.               waste PFI, worth over £1bn, received far higher        increase returns and reduce overall cost to the
  Supplier selection in the public sector presently       public sector funding through the European             public sector, but could be more difficult to finance.
involves a costly and complex competitive dialogue        Investment Bank and the Treasury infrastructure          The final, critical aspect of procurement of waste
process. The advantage to both the promoter and           finance unit, than had originally been anticipated.    treatment projects is testing and commissioning,                                                                                                     Acknowledgements
the provider is that the competitive dialogue               Another key issue concerns the management of         which in the UK requires extended evidence of                                                                                                        We would like to thank Jon Dedman, Steve Waltho and Peter Browne
process enables a range of technologically                construction delivery risk within the special          effective operation before full certification.                                                                                                       of Davis Langdon’s energy team for their contribution to this article.

23.04.2010 BUILDING MAGAZINE                                                                                                                                                                                                                                                                                              BUILDING MAGAZINE 23.04.2010

More Related Content

Viewers also liked

Sylva Rotary 11/7/2013
Sylva Rotary 11/7/2013Sylva Rotary 11/7/2013
Sylva Rotary 11/7/2013profcyclist
 
Assessment of the Environmental Impact of Landfill Sites in the East Riding o...
Assessment of the Environmental Impact of Landfill Sites in the East Riding o...Assessment of the Environmental Impact of Landfill Sites in the East Riding o...
Assessment of the Environmental Impact of Landfill Sites in the East Riding o...Mark Kwabena Gadogbe
 
Landfill Mining Poster Presentation
Landfill Mining Poster PresentationLandfill Mining Poster Presentation
Landfill Mining Poster PresentationJones Edmunds
 
SWM Master plan in Syria
SWM Master plan in SyriaSWM Master plan in Syria
SWM Master plan in SyriaAmir Alboukhari
 
Grady Road Landfill
Grady Road LandfillGrady Road Landfill
Grady Road Landfilltcooper66
 
Landfill Issues
Landfill IssuesLandfill Issues
Landfill Issuesrhendrix20
 
Part 1 Water safety plans explained: What they are and how you can get involved
Part 1 Water safety plans explained: What they are and how you can get involvedPart 1 Water safety plans explained: What they are and how you can get involved
Part 1 Water safety plans explained: What they are and how you can get involvedInternational WaterCentre
 
Incineration: A Poor Solution for the 21st Century, by Dr Paul Connett
Incineration: A Poor Solution for the 21st Century, by Dr Paul ConnettIncineration: A Poor Solution for the 21st Century, by Dr Paul Connett
Incineration: A Poor Solution for the 21st Century, by Dr Paul ConnettFrankie Dolan
 
Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...
Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...
Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...Andrea Drabicki
 
Waste Burning Inceneration
Waste Burning IncenerationWaste Burning Inceneration
Waste Burning IncenerationMUSATTI
 
Sanitary Engineered Landfill Processes
Sanitary Engineered Landfill ProcessesSanitary Engineered Landfill Processes
Sanitary Engineered Landfill ProcessesMohammad Kanawaty
 
SOLAR TREE technical seminar report doc
SOLAR TREE technical seminar report docSOLAR TREE technical seminar report doc
SOLAR TREE technical seminar report docMohsin Khan
 
SOLAR TREE technical seminar PPT(by mohsin khan)
SOLAR TREE technical seminar  PPT(by mohsin khan)SOLAR TREE technical seminar  PPT(by mohsin khan)
SOLAR TREE technical seminar PPT(by mohsin khan)Mohsin Khan
 

Viewers also liked (20)

Sylva Rotary 11/7/2013
Sylva Rotary 11/7/2013Sylva Rotary 11/7/2013
Sylva Rotary 11/7/2013
 
Assessment of the Environmental Impact of Landfill Sites in the East Riding o...
Assessment of the Environmental Impact of Landfill Sites in the East Riding o...Assessment of the Environmental Impact of Landfill Sites in the East Riding o...
Assessment of the Environmental Impact of Landfill Sites in the East Riding o...
 
Landfill Mining Poster Presentation
Landfill Mining Poster PresentationLandfill Mining Poster Presentation
Landfill Mining Poster Presentation
 
Regulation of Landfill in Ireland
Regulation of Landfill in IrelandRegulation of Landfill in Ireland
Regulation of Landfill in Ireland
 
Overliner or Landfill Mining?
Overliner or Landfill Mining?Overliner or Landfill Mining?
Overliner or Landfill Mining?
 
SWM Master plan in Syria
SWM Master plan in SyriaSWM Master plan in Syria
SWM Master plan in Syria
 
Grady Road Landfill
Grady Road LandfillGrady Road Landfill
Grady Road Landfill
 
Landfill Issues
Landfill IssuesLandfill Issues
Landfill Issues
 
Solar tree seminar ppt
Solar tree seminar ppt Solar tree seminar ppt
Solar tree seminar ppt
 
Part 1 Water safety plans explained: What they are and how you can get involved
Part 1 Water safety plans explained: What they are and how you can get involvedPart 1 Water safety plans explained: What they are and how you can get involved
Part 1 Water safety plans explained: What they are and how you can get involved
 
Incineration: A Poor Solution for the 21st Century, by Dr Paul Connett
Incineration: A Poor Solution for the 21st Century, by Dr Paul ConnettIncineration: A Poor Solution for the 21st Century, by Dr Paul Connett
Incineration: A Poor Solution for the 21st Century, by Dr Paul Connett
 
Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...
Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...
Landfill Remediation Project - Student redesigns: Land Use Sustainable Develo...
 
Waste Burning Inceneration
Waste Burning IncenerationWaste Burning Inceneration
Waste Burning Inceneration
 
Sanitary Engineered Landfill Processes
Sanitary Engineered Landfill ProcessesSanitary Engineered Landfill Processes
Sanitary Engineered Landfill Processes
 
solar tree ppt
solar tree pptsolar tree ppt
solar tree ppt
 
SOLAR TREE technical seminar report doc
SOLAR TREE technical seminar report docSOLAR TREE technical seminar report doc
SOLAR TREE technical seminar report doc
 
SOLAR TREE technical seminar PPT(by mohsin khan)
SOLAR TREE technical seminar  PPT(by mohsin khan)SOLAR TREE technical seminar  PPT(by mohsin khan)
SOLAR TREE technical seminar PPT(by mohsin khan)
 
SOLAR TREE
SOLAR TREE SOLAR TREE
SOLAR TREE
 
Incenaration
IncenarationIncenaration
Incenaration
 
Landfill revised
Landfill revisedLandfill revised
Landfill revised
 

EfW Cost Model From Building Magazine

  • 1. ECONOMICS analysis / facts / forecast “waste to energy entrepreneurs” teamed up, with a proposal for a efficient, large schemes with the planning will continue to be investing in capacity to secure hi-tech, plasma arc gasification capacity to treat the waste for a contentious and high risk. long-term management contracts. plant to produce aviation fuel. consortium of WDAs are difficult Due to high operating costs, Grundon and Viridor, for example, Perhaps the most critical to get through planning. government incentives including COST MODEL ENERGY FROM WASTE developed a speculative plant near Heathrow that has enabled them to secure long-term stakeholder in UK energy from waste policy is the general public, which is antagonistic to some While very large schemes in excess of 50MW will fall within the remit of the Infrastructure landfill tax, Renewable Obligation Certificates (ROCs) and feed-in tariffs will play a critical role in contracts with WDAs in the M4 waste management projects. Planning Commission, this underpinning the economics of There are almost as many treatment solutions as sources of waste. Simon Rawlinson and corridor. BA and Solena have also Opposition is such that more applies to few schemes, so schemes. Matthew Hicks of Davis Langdon weigh up the costs and the risks of options, including incineration 03 / POTENTIAL BENEFITS OF ENERGY FROM WASTE SCHEMES 01 / INTRODUCTION Energy from waste projects need to be considered I Waste bulk reduction. Incineration will typically 450-600kWh per tonne are possible through a as part of the wider waste management hierarchy, reduce waste bulk by 60 to 70%, and some waste steam turbine generator The UK produces over 300 million tonnes of due to landfill tax and higher gate prices, and are encourage reduction of waste at source and by but the UK produces more waste than can be products may also be recyclable as aggregates I Energy security. Waste-based energy will reduce waste a year, 24% of which is derived from also looking for alternatives to landfill. Waste recycling. However, there are physical and effectively recycled and bulk reduction techniques I Stabilisation of landfill. The bulk of the residual UK dependence on imported energy sources household or commercial sources. Historically, disposal authorities face fines of £150/tonne if economic limits to recycling, and few waste such as incineration are needed to reduce waste waste stream – bottom ash or vitrified waste – is I Long term cost reduction. Incineration will help to most domestic waste has been directed to they miss their 2013 and 2020 landfill targets, a disposal authorities (WDAs) expect to be in a volumes. The main benefits of processes such as stable and does not emit methane mitigate rising costs related to high gate prices and landfill, and on current disposal rates, the UK has policy which is driving waste-related investment position to recycle more than 65% of their solid incineration are: I Energy production. Conversion rates of rising landfill tax. less than 10 years’ supply of landfill left. worth £9-11bn for the public sector alone waste stream. Unlike Europe, where incineration Challenging EU targets for the reduction of between now and 2020. This is equivalent to is well established, energy from waste is disposal of domestic waste to landfill have an extra 500 million tonnes of treatment unpopular in the UK. However, with much tighter Energy from waste as a means of treatment is belatedly triggered a PFI market in waste capacity per year. regulation, improved technology and the growing preferable to the last resort of landfill recycling and treatment. Commercial waste Government policy, articulated through the risk of a UK energy gap, waste’s potential as a producers have also experienced rising costs “waste hierarchy” (see diagram below) is to resource is now being warmly embraced. 02 / THE UK WASTE INDUSTRY The UK waste sector is However, there will continue to be evolving very quickly in an effort tasked with reducing their surprisingly diverse. The waste a surplus, and energy from waste to increase efficiency, deal with a landfill related to biodegradable stream is inevitably varied and as a means of treatment is wider range of waste streams and municipal waste, commercial requires different treatment and preferable to the last resort of to increase safety. Defra, for waste users who want to reduce disposal regimes. Within the landfill. example, has recently provided disposal costs, and energy users municipal and commercial waste Materials recovery and support to the development of looking for diversified sources. streams, there are a large number mechanical and biological advanced thermal techniques There are 40 waste management of players. Commercial treatment processes (MBT) sit (ATT) such as pyrolysis. PFIs in the UK, many of which organisations are responsible for above energy from waste in the Parties involved in energy from involve elements of energy contracting their own waste hierarchy and can produce fuels waste include WDAs who are generation, as well as a group of disposal. In the public sector, that can be sold on to energy there are a host of waste users. Solid recovered fuel is a collection and waste disposal product of MBT processes and, in MINIMISE authorities, as well as health some cases, can be burned trusts and education authorities without treatment of flue gases. who are responsible for their own Energy from waste itself is waste management. This means an umbrella term describing schemes may have to technologies used to extract the REUSE accommodate a very varied chemical energy locked in waste feedstock. Restrictive planning products. Energy from waste concessions may also limit the techniques include thermal sources of waste a particular processes such as incineration, as scheme can treat – limiting well as a range of thermal or RECYCLE economies of scale and long-term chemical gasification techniques flexibility in the use of a facility. that produce gas and liquid fuels. Based on the waste hierarchy The portfolio of energy from (see diagram, right), much waste techniques also includes RECOVER investment has been targeted at aspects of pre-treatment required ENERGY minimising the volume of waste for biological processes such as requiring disposal. Projects anaerobic digestion, as well as managed by the Waste Resource the treatment of flue gases and LANDFILL Action Programme (Wrap) are other by-products of the ALAMY good examples of the holistic conversion process. Technologies approach adopted in the UK. used are proprietary and are 23.04.2010 BUILDING MAGAZINE
  • 2. 56 / economics / cost model economics / cost model / 57 particularly those related to safe operation. of lower than expected throughput is increased Many of the risks relate to the effective operation According to Wrap, total costs of disposal via unit costs. Lower waste conversion rates will of plant, which makes innovation particularly 04 / ENERGY FROM WASTE TECHNOLOGIES energy from waste range from £65 to £136/tonne. increase cost related to landfill tax liabilities. difficult to deliver – especially in smaller schemes In terms of operating costs, the main areas of risk that have a limited range of treatment processes. involve throughput, energy prices, the operating Additional cost and value drivers There are a number of high-profile projects where Outside the UK a range of treatment for energy from waste. also reuse waste heat through oils can potentially be used as a and maintenance regime and the costs of disposal Most value drivers associated with energy from timescales and quality standards have not been technologies have been in use for However, they differ in the way large-scale community CHP bio-fuel, although currently the of waste products. Replacement cost of plant also waste are related to scale of operation, which is met, and where testing and commissioning has a long time, but very few have a the energy value of residual systems. Unfortunately, due to only use is for electricity has to be factored into the model. The implication difficult to optimise due to planning constraint. taken significantly longer than anticipated. track record with the UK’s mix of waste is increased and in the the unpopularity of incineration, generation using a CHP. waste. With pressure on to have quality of fuel produced. finding locations next to heat Unlike incineration, both waste treatment plant in place to Production of solid recovered users is very difficult. gasification and pyrolysis 06 / ADDITIONAL COST AND VALUE DRIVERS meet the 2013 landfill deadline, fuel via MBT or MHT gives The most common incineration require pre-processing of waste momentum is with incineration. WDAs the option to sell on their technology is moving grate material. They also produce flue However, looking forward to recyclate without committing to combustion. A potentially more gases that require treatment. 2020 targets and long-term PFI develop a dedicated energy from efficient combustion technique, Another emerging technology is VALUE RISK deals, more advanced solutions waste scheme. fluidised bed combustion, requires plasma arc gasification. This may be adopted. Incineration is the most pre-sorting and shredding of the involves passing waste into a Mitigation of long-term costs to the WDA Energy from waste projects Certainty of availability End users need assurance that the proposed plant There are other sets of waste established waste technology in waste feedstock. Relatively few kiln at 4,000-7,000˚C. Gases eliminate risks of exposure to penalties from the Landfill Allowance Trading will deliver the expected waste throughput and waste bulk reduction within treatment techniques, including the UK, treating over 4,000,000 of these plants are in operation. released are collected, and any Scheme relating to landfill disposal in excess of allowances. strict emissions levels and timescales. MBT and mechanical heat tonnes per year. In energy from Although well established, waste products are immobilised treatment (MHT) that often form waste schemes, the heat from the moving grate technology has in a vitrified mass that can be Risk transfer through procurement Turnkey procurement via PFI or a Certainty of delivery Where the project delivers useable output such as a part of a PFI. Both include a process is used in a steam significant complexities safely disposed of. Plasma arc treatment contract enables clients to secure large-scale investment and to syngas or solid recovered fuel, assurance of product quality is critical. proportion of materials recovery turbine to generate electricity for associated with the optimisation gasification promises much, but outsource project delivery and operational risks. from the general waste stream the National Grid. Some projects of combustion, reuse of energy with few “reference” plants to Project delivery Risks include integration and co-ordination of complex and and could be used as a pre- such as Sheffield and Teesside and the need to meet extremely confirm performance, adoption Minimisation of social impacts including vehicle movements, where this can distinct technologies for pre-treatment, combustion, flue gas treatment and stringent flue gas standards. in Europe will be gradual. be achieved using existing infrastructure such as rail. the grid connection. Site constraints to the plan or building height may limit Flue gas cleaning can add Anaerobic digestion is a the proprietary technologies that can be used in a particular location. between 30% and 60% to the biological process for the Economies of scale Energy from waste schemes are most cost effective capital cost of the equipment. organic portion of municipal with a throughput in excess of 350,000 tonnes a year. For larger projects it Planning risks Planning challenges include health concerns, traffic ATT processes use heat and solid waste. Advantages include is claimed that doubling the throughput of a scheme only results in a cost movement and the visual impact of a development that can include a 90m pressure to extract gases and scalability and low running increase of 50%. Other benefits of scale include reduced land-take and high stack. Planning consents may involve restrictions on operations such as oils from waste materials. costs. Implementation issues higher operational efficiencies. limits on where waste can be sourced from. Other risks include delays in the Gasification uses a temperature include waste preprocessing, planning process for overhead power line connections. of about 750˚C and releases and disposal of the non-organic Recovery of value from the waste stream including heat energy and useable hydrogen and methane waste and the residual recyclates such as aggregate or solid waste fuel. Project delivery Guarantees that transfer risk related to the availability and as well as carbon monoxide. “digestate”. Defra is promoting quality of feedstock and the availability and performance of the technology Pyrolysis takes place at a lower development of anaerobic Quality of the business case, including good quality information, use of will also improve viability – so long as the warranties are enforceable. temperature, 300-800˚C, under digestion capability in the UK well-established technologies and extensive scenario modelling. pressure and in the absence of and more than 10 large-scale Co-ordination of programme delivery Projects that involve a number of oxygen. The process is designed schemes are in development. The Accurate estimation of the quality and volume of the waste stream, so that technologically distinct but closely related components need effective to extract a greater calorific long-term vision is that bio-fuels plant operates effectively. programme management. value than gasification and will from anaerobic digestion and produce a combination of gases, ATT will be used as part of the Diversification of waste management processes to include waste reduction Technology risk associated with complex processes Each new feature oils and waxes. The gases and natural gas or liquid fuel supply. and recovery. Materials recovery and composting are cheaper and more incorporated to reduce emissions or increase energy recovery contributes to environmentally desirable than combustion. Larger projects that enable a this risk. range of techniques to be cost effectively included in the treatment mix 05 / COST AND VALUE DRIVERS should deliver optimum outcomes. Supply and demand risk Reference projects with an extended track record of operation with a UK waste stream are important business case evidence Diversification of sources of waste – dealing with commercial and municipal for both end-user clients and funders. Energy from waste projects are typically procured End user requirements Project sponsors such as energy and by-products such as aggregates. The waste streams together improves economies of scale and certainty of on a build-own-operate basis, with operational and WDAs have been in competition for scarce waste waste gate price, currently about £60 to waste supply. Viability risk related to the long-term value of incentives such as landfill tax commercial risks being taken by a waste management expertise and private finance. In £90/tonne, has increased substantially with the and ROCs. consortium. The economics of energy from waste practice, larger WDAs are in a stronger position to support of landfill tax and typically contributes Continuing incentivisation of waste reduction and recovery strategies. schemes are subject to many sources of risk and determine preferred solutions than smaller 70% of income. Certainty with regards to the Supply risk associated with the volume, quality and consistency of the waste uncertainty, so although a scheme will usually be authorities who have in some cases struggled to continuation of the landfill tax accelerator is an stream. set up with a guaranteed feedstock source, overall attract operator interest. Other areas where important consideration for operators and investors. viability will be subject to a wide range of pricing, end-user requirements might affect the project Depending on the technologies adopted, there Demand risk related to markets for recyclates such as solid recovered fuel deliverability and performance risks. Combined with design include the consistency of the waste may be additional income streams related to In summary, the risk exposure on energy to waste projects is relatively as well as waste heat, and the prices that can be obtained for these the requirement to secure very large values of feedstock they can provide. Projects serving a exported heat energy as well as income from high – particularly for emerging technologies. Turnkey contracts are an products. private finance, this level of risk exposure tends to consortium of WDAs will need to be designed to incentives such as ROCs. important mechanism to enable these complex interrelated risks to be favour the use of well established technologies and deal with a less consistent waste stream, with a Costs Energy from waste schemes need packaged in such a way as the main objective of optimising the use of Political risk for end users of commitment to energy from waste if incentive solution providers. consequent impact on efficiency. substantial investment in pre-treatment and grid waste as a resource is met. This concentration of risk will inevitably result to recycle is reduced. The main variables affecting energy from waste Income The main sources of income are the gate connection infrastructure, as well as land and main in a risk premium which can be mitigated to an extent by giving suppliers viability are as follows: price for the waste stream and the sale price of generator plant. Operating costs are also substantial, freedom over the application of technologies. 23.04.2010 BUILDING MAGAZINE BUILDING MAGAZINE 23.04.2010
  • 3. economics / cost model / 59 08 / COST MODEL The cost model provides outline costs of the Details of the scope of external works are building facilities associated with a 600,000 included as these are a critical element of the tonne a year combustion plant based on a operation of the facility. three-line moving grate technology. The Site preparation costs, client-side professional analysis also provides indicative costs of the fees and VAT are excluded. combustion system and the grid connection. A / COST BREAKDOWN £ £/m2 GIFA % £ £/m2 GIFA % Temporary works 1,650,000 64.71 2.00 Protection installations, lightning protection and earthing and bonding, complete, Allowance for temporary works, item @ £1,650,000 item @ £480,000 Protection installations, fire detection, alarm and supression systems 25,500m3 @ Building shell 34,811,600 1,365.16 46.42 £80 Piling, pilecaps and ground beams, generally 11,000m2 @ £460 Lift and conveyor installations, very heavy duty goods and passenger lifts serving Extra for base to air-cooled condenser 2,150m2 @ £150 seven levels, item @ £2,750,000 Extra for stack base, item @ £330,000 Special installations, crane and hoist installation, including crane rails, item @ Floor slabs, typically 500 thick insitu concrete, below ground drainage 11,000m2 @ £300,000 £185 Special installations, building mangement and energy management systems, item @ Feedstock and bottom ash storage bunkers complete, retaining walls, internal walls, £910,000 floor slabs, etc. (rate based on footprint area) 1,485m2 @ £3,650 Insitu concrete frame and upper floor construction to tipping hall, including full Ancillary building works 2,640,500 103.55 3.52 height shear wall structures (rate based on footprint area) 2,835m2 @ £1,280 HGV access ramp complete, including substructure, structure, road surface and Insitu concrete frame and upper floor construction to boiler, turbine and flue gas safety barriers, item @ £2,150,000 treatment hall, including full height shear wall structures (rate based on footprint Allowance for gatehouses and weighbridges, item @ £375,000 area) 4,500m2 @ £270 Allowance for fuel and chemical storage – foundations, interceptors, etc., item @ Structural steelwork to building including long span curved trusses to roofs and £115,500 framing to process plant, stairs and access platforms (rate based on gross internal floor area) 25,500m2 @ £400 External works 5,540,000 217.25 7.39 Cladding and roofing. Flat-panel cladding panels, feature glazing, aluminium louvres, Site preparation, generally, item @ £310,000 raised seam roofing on structural deck and secondary steelwork curved to profile, Roads and hardstandings, including traffic control systems, item @ £1,110,000 roof lights, rainwater disposal, architectural cladding to stack (rate based on gross Security fencing and gates, item @ £230,000 internal floor area) 25,500m2 @ £220 Drainage installations, complete, item @ £840,000 Allowance for blockwork partitions and cladding lining, item @ £645,000 External services, incoming HV supply, site water infrastructure, item @ Allowance for doors and windows, item @ £345,000 £3,050,000 The Lakeside energy from waste plant at Colnbrook, Berkshire, is one of the few to have been Preliminaries and contingencies 16,734,900 656.27 22.31 approved by planners Finishing and fit-out works 1,830,000 71.76 2.44 Contractor's management, site establishment and site supervision. Allow 17% @ Allowance for surface finishes, item @ £1,300,000 £9,836,700 Allowance for partitions, finishes and fittings to offices, workshops, staff facilities Contractors EPC design fees for building only. Allow 6% @ £3,500,000 and laboratories, item @ £530,000 Design reserve. Allow 5% @ £3,398,200 07 / PROCUREMENT Building services installation 11,793,000 462.47 15.72 Total construction cost – building only 75,000,000 2,941.17 100.00 Delivery of energy from waste projects is an different solutions to be considered as part of the purpose vehicle. SPV projects are typically Plumbing and sanitary installation, complete, item @ £130,000 extended process, typically taking seven to 10 bidding process. Unfortunately this increases the delivered to the service operator via an Mechanical services installation. Heating and ventilation including closed cycle Turnkey technology contracts 230,000,000 9,019.61 years. In the current market, there are many WDAs costs of all parties. Recently, smaller authorities engineering, procurement and construction (EPC) ventilation system with negative pressurisation and odour abatement to tipping hall Indicative cost of 600,000 tpa incineration and energy from waste installation, with seeking to secure relatively scarce technological have had difficulties in attracting compliant bids. contract. The operator’s risk can be minimised by and waste hoppers. Heating and air conditioning systems to offices and workshops. planned net electricity output of 65MWe, item @ £220,000,000 and project delivery resources, and as a result, the Private finance is more costly in the waste sector wrapping all aspects of the capital works – Dedicated extract systems. Hot and cold water installations. 25,500m2 @ £150 Indicative cost of National Grid connection, item @ £10,000,000 packaging of the project will be critical in attracting than some other PFI streams because of the range pre-treatment, main plant and grid connection Electrical installations, substation, including associated building works, item @ interest from bidders and from PFI financiers. of risks involved. The costs of large “back-end” infrastructure – into a single EPC deal. However, £440,000 Total construction cost – building only 30,000,000 14,902 11,960.78 Some major issues in procurement deal with projects, such as incinerators, are such that since these arrangements add significantly to costs Electrical installations, HV installation, lighting and emergency lighting, small power attracting the most appropriate bidders in the first the loan syndication market collapsed in 2007, related to fees, management resource and risk and power supply to building services installations 25,500m2 @ £36 place, obtaining finance and devising the most cost funding has been more difficult to arrange through premium. An “unwrapped” approach, where the effective project delivery mechanism in order to “clubs” of lending institutions. The Manchester SPV takes a more direct role in managing risk, may integrate the major elements of technology. waste PFI, worth over £1bn, received far higher increase returns and reduce overall cost to the Supplier selection in the public sector presently public sector funding through the European public sector, but could be more difficult to finance. involves a costly and complex competitive dialogue Investment Bank and the Treasury infrastructure The final, critical aspect of procurement of waste process. The advantage to both the promoter and finance unit, than had originally been anticipated. treatment projects is testing and commissioning, Acknowledgements the provider is that the competitive dialogue Another key issue concerns the management of which in the UK requires extended evidence of We would like to thank Jon Dedman, Steve Waltho and Peter Browne process enables a range of technologically construction delivery risk within the special effective operation before full certification. of Davis Langdon’s energy team for their contribution to this article. 23.04.2010 BUILDING MAGAZINE BUILDING MAGAZINE 23.04.2010