The document provides an update on project progress as of October 5th, 2013. It reports that the CRS wall is being extended towards the east side and south west. It also provides details on work progress for various parts of the project including blocks 1-4, 17-20 for Part 1; blocks 15-16 for Part 2; blocks 13-14 including placement of boosters for shotfire for Part 3; and blocks 9-12 for Part 4.