The document outlines proposals for a new building at Pinewood Studios, including initial design concepts, floor plans, and considerations for structure, materials, sustainability, and safety. It will provide office space, meeting rooms, and ground floor functions, and be used by Pinewood Studios employees, directors, and actors. The building services, facades, and an emphasis on natural lighting, ventilation, and energy efficiency are discussed to achieve BREEAM sustainability standards.
2. 2
07/11/2012
Who will use it?
• Employees of Pinewood Studios
• Directors and Actors
How will it be used?
• Office space
• Meetings
• Functions on the ground floor
5. 5
07/11/2012
Roof garden AHU
Toilet and
kitchen
facilities on
this side
Offices on
this side
Main
entrance
Glass atrium
6. 6
07/11/2012
Ground investigation and Foundations
• 10m of made ground
▫ Could be contaminated
▫ Ground investigation
• We think we will use bore piling as long as the ground is
safe
20. 20
07/11/2012
Building services
• 550m2 of floor space
▫ 48kw of electricity
• Total u value of the building is 0.55
▫ 0.55 x 26 x 1042 = 14900
▫ Will lose maximum of 15kw of heat
▫ 1kwh costs 17p
• AHU on the roof 700 x 700 x 5000
▫ Ventilation duct runs down the corner of the building
21. 21
07/11/2012
Facades How to attach glass to structure
Chosen Solution
25. 25
07/11/2012
Sustainability & Environmental effects
• Rain water harvesting system
• Solar panels on all the south facing
windows
• Install AHU and natural ventilation
• Use natural lighting
• Under floor heating using ground heat
These things will contribute to our
BREEAM score.
26. 26
07/11/2012
Healthy & Safety
• Fire safety
▫ Central stairs
▫ Lobby around stairs
▫ Plasterboard
▫ Sprinklers and alarms
• Safety of workers
27. 27
07/11/2012
Inclusive Design
• Lifts and stair railings
• Braille on signs
• Wider doors and corridors